LAFA Food Distribution

Slides:



Advertisements
Similar presentations
Shunt Capacitor Switching For Power Factor Improvement Clayton H Reid.
Advertisements

B757 Review Questions.
POWER FACTOR IN ELECTRICAL ENERGY MANAGEMENT
Electrical Installation
HVAC Commercial Ref.
Freezer Alarm &Backup Systems Preventing Sample Losses * * * * * * * * * * * * * * * * * * * * * * * * Joe DeFrancesco, Gina Koskela, Peter Sturman Oregon.
Lesson 38 Shipboard Power
Automatic Transfer Switch using microcontroller
2014 NEC Code Changes Ted “Smitty” Smith E Light Electric.
DOD Microgrids The Missing Link: Microgrid Applications Michael Dempsey P.E. Burns & McDonnell June 12, 2013 © 2013 Burns & McDonnell. All Rights Reserved.
LAFA Food Distribution July 26, Introduction:
FIRE PUMP ELECTRICAL CONFIGURATIONS UNDER 600 VOLTS.
Landon Roberts Lighting/Electrical Option 11/01/07 Medical Education Building Johns Hopkins University School of Medicine Electrical Systems Existing Conditions.
Elec467 Power Machines & Transformers
The Bottom Line In Energy Cost Reduction Energy Automation Systems, Inc. EASI.
AGENDA INTRODUCTION CELLS AND COMPONENTS PV PERFORMANCE PV APPLICATIONS CODES AND STANDARDS EMERGENCY RESPONSE.
Three Phase Power Three Phase Motors
Department of Mechanical Engineering HumilityEntrepreneurshipTeamwork LearningSocial ResponsibilityRespect for Individual Deliver The Promise BS&H, GMR.
Section 4: Electric Motors
Freedom Combi Inverter
The First Central Emergency & Standby Lighting System Combining Storage Batteries & Generator Input 1 1.
Interconnect Protection of Dispersed Generators
Troubleshooting Electric Control Devices
THE ELECTRIC SUB STATION
Residential Construction Unit 5- Energy Efficiencies and Mechanicals Mr. Todzia.
Electrical Distribution Training
Module 5, Unit A Vocabulary Review Game. 2 pt 3 pt 4 pt 5pt 1 pt 2 pt 3 pt 4 pt 5 pt 1 pt 2pt 3 pt 4pt 5 pt 1pt 2pt 3 pt 4 pt 5 pt 1 pt 2 pt 3 pt 4pt.
Prepared By :.  Introduction  Techniques Used  Case Study  Advantages  Application  Conclusion OUTLINE.
E2 Motors and Motor Starting
Throw Pole Throw Pole nc no. Electric symbols Single pole single throw normally open Single pole single throw normally closed double pole single throw.
PROGRAMMABLE LOGIC CONTROLLER (PLC) AND AUTOMATION
SIMPLE TRANSMISSION OUTAGE. Nodal Protocol Definition 2.26 Simple Transmission Outage A Planned Outage or Maintenance Outage of any Transmission Element.
PowerSouth Lowman AC/DC Essential Voltage System.
Zoning Hydronic Systems. Zone Control Divides the Space to be Heated 1.Each with its own heating needs and control systems 2.There are several reasons.
Consumer’s Main Switchroom & Main L.V. Switchboard
November 4, 2013 Topic: Electric Circuit Objectives:
Electrical Power Distribution. Forms of Energy All forms of energy fall under two categories POTENTIAL Stored energy or energy of position (gravitational)
Electrical Power Distribution. Forms of Energy All forms of energy fall under two categories POTENTIAL Stored energy or energy of position (gravitational)
Machinery Cooling Water System Locations and Operations.
SERVICE ENTRANCE EQUIPMENT
C-12 ELECTRICAL CW3 RIESE 18 APRIL DC SYSTEM -24V, 34 AMP HOUR NICKEL CAD BATTERY A 30V DC STARTER/GENERATORS -AN EXTERNAL DC POWER SYSTEM.
A Training Presentation On 132 KV GSS JAIPUR Submitted in partial fulfillment For the award of the degree of BACHELOR OF TECHNOLOGY Submitted To:- Submitted.
A SEMINAR ON 400 KV GSS(RRVPNL) BIKANER.
Teknologi Pusat Data 12 Data Center Site Infrastructure Tier Standard: Topology Ida Nurhaida, ST., MT. FASILKOM Teknik Informatika.
E4 HVACR Electrical Installation
Air Line Pilots Association, International EMB 145 Oral Questions Overhead “A” Select “Slide Show” Use the space bar on your computer to advance the presentation.
Utilities & Engineering Department16 Blossom St., Boston Introduction to the Hospital Emergency Power Supply System (EPSS) Jason D'Antona,
Switches and Over Current Protective Devices Class Instructor ALPHER E. DE VERA, uap.
Distribution Automation The utilization of IEDs (Intelligent Electronic Devices) and advanced communications to unlock the benefits of operational efficiency.
April 7, 2015 Washington, D.C. Area Low-Voltage Event Operations Training Seminar 2016 Erik Johnson System Operations Training (ERCOT)
SYNERGY INSTITUTE OF ENGINEERING AND TECHNOLOGY
Automatic Transfer Switches
E4 HVACR Electrical Installation
Section 6: Air-Conditioning (Heating And Humidification)
E2 Motors and Motor Starting
Interconnect Protection of Dispersed Generators
E4 HVACR Electrical Installation
Shipboard Electrical Distribution
PRESENTED BY:AMOD SHAKYA. Power Circuit –connectoin with motor using contactor Control Circuit-using switch make a holding circuit.
E2 Motors and Motor Starting
Engineering Project Cable Management.
AGENDA INTRODUCTION CELLS AND COMPONENTS PV PERFORMANCE
EET 323 – Electrical System Design Lecture 9: Grounding
Electrical Distribution System Basics
AGENDA INTRODUCTION CELLS AND COMPONENTS PV PERFORMANCE
Dominion Energy South Carolina: Solar Equipment Requirements
Presentation transcript:

LAFA Food Distribution July 26, 2013 LAFA Food Distribution

Introduction: ► The problem is that the Emergency Power System will not operate automatically. ► The existing Emergency Power System is powered by a 360 KW Generator. ► The generator is not powerful enough to start all of the motors at the same time, but will carry the load if the motors are started one at a time. ► The system is operated manually by first starting the generator, then each load is brought on line one at a time. ► Three different design approaches will be presented, along with costs involved, that will allow the Emergency Power System to operate automatically.

SERVICE ENTRANCE Existing Configuration MDP Equipment Room Generator 360KW Main Circuit Breaker MDP SWITCHBOARD A.T.S. N E LOAD 2500AF 2500AT 600A Switch 2500AF 2500AT Utility Power SERVICE ENTRANCE Existing Equipment

Main Distribution Panel Existing Configuration MDP Main Distribution Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Non Essential Loads Coolers Power Distribution Existing Equipment

Option 1 – Provide Automated Control System This Option will provide an automated control system for the refrigeration equipment to: ► Sequentially start the coolers so as not to exceed the system capacity. ► Shed all non essential loads ► The system shall have the capability to shed loads as required if the generator should become overburdened.

SERVICE ENTRANCE Proposed Configuration – Option 1 MDP Equipment Room Generator 360KW Main Circuit Breaker SWITCHBOARD MDP A.T.S. N E LOAD 2500AF 2500AT 2500AF 2500AT 600A Switch Utility Power SERVICE ENTRANCE New Equipment Existing Equipment

Main Distribution Panel Proposed Configuration – Option 1 MDP Main Distribution Panel Install New Contactors Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Non Essential Loads Coolers POWER DISTRIBUTION New Equipment Existing Equipment

JOHNSON CONTROL SYSTEM Proposed Configuration – Option 1 SEQUENCE OF OPERATION: When loss of power is detected, all refrigeration units are disabled, and non essential loads are shed. The generator starts, and the automatic transfer switch initiates a transfer. A timing sequence begins that starts each piece of equipment sequentially. If the generator becomes overloaded, loads will be shed until the generator returns to normal. When normal power is restored, the system resets, and all equipment will run normally. FAC Controller IOM Input/Output Modules To North Coolers To South Coolers JOHNSON CONTROL SYSTEM New Equipment Existing Equipment

Option 2 – Swap out Generator and Provide Contactors to Shed Non Essential Loads This Option will provide the following: ► Swap out the 360 KW Generator with a 480 KW Generator. The 480 KW Generator is existing and services another building on the same facility. The 360 KW generator will replace the 480 KW generator. ► Install contactors to shed non essential loads while the generator is running. They will drop out in the event of a normal power failure and automatically return when power is restored.

SERVICE ENTRANCE Proposed Configuration - OPTION 2 MDP Equipment Room Relocated Generator 480KW Main Circuit Breaker MDP Switchboard A.T.S. N E LOAD 2500AF 2500AT 2500AF 2500AT 800A Switch Utility Power SERVICE ENTRANCE New Equipment Existing Equipment

Main Distribution Panel Proposed Configuration – OPTION 2 MDP Main Distribution Panel Install New Contactors Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Non Essential Loads Coolers POWER DISTRIBUTION New Equipment Existing Equipment

Option 3 – Swap out Generator and Reconfigure Power System This Option will replace the Generator and separate the Normal Power System from the Emergency Power System. ► Swap out the 360 KW Generator with a 480 KW Generator. The 480 KW Generator is existing and services another building on the same facility. The 360 KW generator will replace the 480 KW generator. ► Reconfigure wiring at the service entrance as shown in the following diagram to connect the Main Distribution Panel in parallel with the Automatic transfer Switch.. ► Install new Emergency Power Panel and relocate power feeders from HVAC equipment to it. ► The Existing Main Distribution Panel will not be energized by the generator.

SERVICE ENTRANCE Proposed Configuration - OPTION 3 MDP MAIN 1 MAIN 2 Equipment Room Relocated Generator 480KW MDP Switchboard A.T.S. MAIN 1 MAIN 2 N E LOAD 2500AF 800AT 2500AF 2500AT 800A Switch Utility Power TO EMERGENCY PANEL SERVICE ENTRANCE New Equipment Existing Equipment

Emergency Distribution Panel Proposed Configuration – OPTION 3 MDP Main Distribution Panel - Normal Power EDP Emergency Distribution Panel J J J J Reroute Existing Loads to New Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Dist. Panel Non Essential Loads Coolers POWER DISTRIBUTION New Equipment Existing Equipment