19/9/2001Plenary RRB October 22, 2001 DS 1 Status Report of the M&O Scrutiny Group  Evolution of M&O Estimates  Scrutiny Group Mandate  Scrutiny Group.

Slides:



Advertisements
Similar presentations
IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Advertisements

Management’s preliminary comments to the ERC Report.
ALICE © | RRB | 17 April 2013 | Catherine Decosse 24 th meeting of the ALICE Resources Review Board CERN-RRB
Presentation to Barclay Owners November 21, 2013 Window Replacement Project Information Session.
DOE/NSF U.S. CMS Operations Program Review Closeout Report Fermi National Accelerator Laboratory March 10, 2015 Anadi Canepa, TRIUMF Anna Goussiou, University.
Personal reflections, Belgrade, November 30,2009 Markus Nordberg, CERN/ATLAS.
February 2002 Scope and Contingency; Transition to the Research Phase William J. Willis Columbia University.
Consolidation and Upgrade of the LHC Experimental Vacuum Sectors
LCG Milestones for Deployment, Fabric, & Grid Technology Ian Bird LCG Deployment Area Manager PEB 3-Dec-2002.
12 Dec 2005 J. Schukraft1 ALICE USA ALICE position towards US participation EU participation in emcal Requirements Formal steps & schedule.
Summary DCS Workshop - L.Jirdén1 Summary of DCS Workshop 28/29 May 01 u Aim of workshop u Program u Summary of presentations u Conclusion.
EARTO – working group on quality issues – 2 nd session Anneli Karttunen, Quality Manager VTT Technical Research Centre of Finland This presentation.
NSW SG 19 Nov Nov 2014 S. Zimmermann, NSW SG 1.
André Augustinus 10 September 2001 Common Applications to Prototype A two way learning process.
23 October 2001 RRB-131 Draft Budget for CMS M&O and C&I in 2002 Draft Budget for CMS Maintenance & Operation and Commissioning & Integration in the Year.
University Planning: Strategic Communication in Times of Change Cathy A. Fleuriet Ana Lisa Garza Texas State University-San Marcos Presented at the July.
DCS Workshop - L.Jirdén1 ALICE DCS PROJECT ORGANIZATION - a proposal - u Project Goals u Organizational Layout u Technical Layout u Deliverables.
Financial Matters Ferdinand HAHN. Content Cost to completion (exceptional MOF 2014/15) MOF in 2013 (Budget – Contributions - Expenses) MOF in 2014 (Budget.
Volvox Finance 2 How we will manage the Finance Angela Pettit – Contracts Officer.
AGS RSVP Weekly Meeting P. Pile 16 September 2004 AGS RSVP Weekly Meeting, 16 Sep 2004 AGS Project Office - status of funding, comments on RSVP
HiLumi LHC is co-funded by the EU FP7 Capacities Programme, Grant Agreement Svet Stavrev (EU Projects Office, CERN) Administrative Manager 17.
Stationary and Area Source Committee Update OTC Committee Meeting September 13, 2012 Washington, D.C. Hall of the States 1.
Status Update Outline  General remarks - reminder  Progress since last Annual Meeting – June 2010  Next steps - timeline EUROnu Costing Ilias Efthymiopoulos.
Financial Matters Ferdinand HAHN. Content Short Reminder: Definition of Maintenance and Operation Fund (MOF) in the MoU MOF in 2011 (Budget – Contributions.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
G. Martellotti1CSN1 14 / 10 / 2002 LHCb Category A M&O status for 2002 and estimate for 2003 Report on Common Fund and CORE expenses for RRB Ott.
Draft Budget for M&O 2007 A. Petrilli, RRB-23, October 24, 2006 CERN-RRB Cf. CERN-RRB
Scrutiny Group Meeting, May 30, 2006 A. Petrilli, 24 May 2006.
1 1. Some recent views ( ) 2 Linac tunnel
Status of ATLAS Resources Presentation to RRB Markus Nordberg ATLAS Resources Coordination CERN-RRB
Peter Chochula ALICE Offline Week, October 04,2005 External access to the ALICE DCS archives.
LHCbComputing Manpower requirements. Disclaimer m In the absence of a manpower planning officer, all FTE figures in the following slides are approximate.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 LHCC RRB SG 16 Sep P. Vande Vyvre CERN-PH On-line Computing M&O LHCC RRB SG 16 Sep 2004 P. Vande Vyvre CERN/PH for 4 LHC DAQ project leaders.
IRDTS 2008 – reasons for revision, revision process and recommendations of the 39 th session of the SC Workshop for African countries on the Implementation.
Firmware - 1 CMS Upgrade Workshop October SLHC CMS Firmware SLHC CMS Firmware Organization, Validation, and Commissioning M. Schulte, University.
Medium Term Plan, with a Long Term Projection to 2010 L. Maiani. CERN Finance Committee June 19, 2002.
Management’s preliminary comments to the ERC Report FINANCE COMMITTEE June 19, 2002.
Review of the operation scenarios and required manning of the activities P. Schnizer and L. Serio.
The ATLAS Collaborative Tool Project A broad overview.
1 Integration and Milestones Elton Smith Hall D Detector Review October 20-22, 2004.
Status of ATLAS Resources Presentation to RRB Markus Nordberg ATLAS Resources Coordination CERN-RRB
DJ: WLCG CB – 25 January WLCG Overview Board Activities in the first year Full details (reports/overheads/minutes) are at:
Computing Division FY03 Budget and budget outlook for FY04 + CDF International Finance Committee April 4, 2003 Vicky White Head, Computing Division.
19/10/2001DJ for RRBs 22-23/10/ M&O MoUs - History so far 14 MarchIntent announced in RRB-D mid June - 12 JulyInitial draft formulation.
NA62 Organisation of the work - proposal 2/24/20161PD/DT/PO-MH.
CLIC - CDR Status (Volume 2) Hermann Schmickler, ILCW2010.
LHC Computing, SPC-FC-CC-C; H F Hoffmann1 CERN/2379/Rev: Proposal for building the LHC computing environment at CERN (Phase 1) Goals of Phase.
Most Common Fund spending now goes on infrastructure. In the course of next year, essentially all the remaining funds will be spent on finishing the sub-detectors.
Interface of FP420 to LHC FP420 meeting 28-Sep-2006.
Status of Contributions, Draft Budget Request for 2005 and Outlook for the Longer Term Future Martyn Davenport 8 TH October 2004 CAST FRC-D
"If you know how to spend less than you get, you have the philosopher's stone." - Benjamin Franklin.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
First discussion on MSS for Katrin March 26, 2013 M.Capeans CERN PH-DT.
Service Agreements Emmanuel Tsesmelis CERN / TS-LEA RRB Scrutiny Group 31 August 2006.
Emmanuel Tsesmelis RRB Scrutiny Group Meeting August 2010.
1. Road to the EDR 2 Requirements Safety system Transfer line concept Plant concept design Requirements Evaporator concept and performance Transfer line.
Status of ATLAS Resources Presentation to RRB Markus Nordberg ATLAS Resources Coordination CERN-RRB
Collaboration Board 27/09/ Next RRB in October - Core and Common Funds in Projected M&O Cat. A budgets for the coming years - Received funds.
Completion and Pre-Exploitation Costs for the Initial ATLAS Detector
East Hall under construction
ATLAS M&O General Comments
30th meeting of the ALICE RRB C. Decosse
LHCC referees’ questions, comments, requests
4th FRC meeting, Antti Onnela, CERN-PH-DT
International Review of the Conceptual Design of the Cold Powering system for the HL-LHC Superconducting Magnets J.Ph. Tock
DG Environment, Unit D.2 Marine Environment and Water Industry
5.b3 Monitoring & Reporting 2019
East Hall under construction
Presentation transcript:

19/9/2001Plenary RRB October 22, 2001 DS 1 Status Report of the M&O Scrutiny Group  Evolution of M&O Estimates  Scrutiny Group Mandate  Scrutiny Group Timetable  Scrutiny Group Members  Strategy for the Scrutiny  Recommendations  Results  Conclusions

19/9/2001Plenary RRB October 22, 2001 DS 2 Evolution of M&O estimates 12/99Updated draft “General Conditions for Experiments performed at CERN” (GC) to ACCU for comments 12/99Working Group mandated H. Foeth (CMS), H. De Groot (ALICE), H.J. Hilke (LHCb), D. Jacobs (sec.), D. Plane, L. Robertson (IT), P. Schmid (ATLAS), A. Smith, R. Voss (chair) consults, agrees on headings, gathers estimates at the same time, ATLAS and CMS formed internal working groups that contributed greatly to the process concludes in time for the 10/00 RRB 4/00Presentation to RRB plenary session revised GC in force, the comments made having been taken into account progress of the Working Group

19/9/2001Plenary RRB October 22, 2001 DS 3 Evolution of M&O estimates 10/00 Presentation to RRB plenary session progress of the Working Group outline categorization of M&O preliminary cost profiles and levels 4/01Discussion in all RRB sessions plenary presentation of RRB-D with detailed categorization and estimates, and ideas on sharing. Announced drafting of M&O MoU and invited input on all aspects. Introduced idea of RRB Scrutiny Groups. discussion of these matters in all experiment sessions Since then: 5/01 - Collaborations check categorization in RRB-D /01 - Collaborations revise estimates to 2006 start-up 8/01 - Scrutiny Group starts operating

19/9/2001Plenary RRB October 22, 2001 DS 4 Scrutiny Group Mandate critically review the M&O cost estimates, especially for Categories A and C flag items (or time periods for items) that are more correctly linked to Construction or Commissioning & Integration than to Maintenance & Operation flag items for which cost estimates are intrinsically unreliable or likely to vary with time flag items for which a change of strategy might produce economies e.g. gas recycling versus consumption identify activities related to shutdown activities but occurring before full machine operation identify the cost drivers do not scrutinize the on-line computing items for now. These will be treated later, partially in the light of the estimates being made by the LHC Computing Grid project.

19/9/2001Plenary RRB October 22, 2001 DS 5 Scrutiny Group Timetable Most of the Scrutiny Group’s business was conducted remotely. The full Scrutiny Group met together at CERN on 23 August and 10 September.

19/9/2001Plenary RRB October 22, 2001 DS 6 Scrutiny Group Members Atul Gurtu, Tata Institute Bernard d’Almagne, CNRS, IN2P3 Brigitte Bloch-Deveaux, CEA, DAPNIA Franco Cervelli, Paolo Giubellino, INFN Guy Liujckx, NIKHEF, Jim Yeck, DoE Kai Koenigsmann, University of Freiburg Peter von Handel, DESY Peter Chochula, Comenius University, Bratislava Steinar Stapnes, University of Oslo Sven-Olof Holmgren, University of Stockholm T. Camporesi, D. Plane, T. Taylor, D.Schinzel (Chair) and E.M. Rimmer (Secretary), CERN

19/9/2001Plenary RRB October 22, 2001 DS 7 Strategy for the Scrutiny  Concentrate on A costs and on 2002/2007  Scrutinize thoroughly a limited number of cost entries (The list of 8 questions). Detector related costs (#) 1.Explain how the costs for magnet, magnet controls, magnet power supply, external and proximity cryogenics, and cryogenic fluids have been reached. Indicate the amount of manpower. 2.List and explain the manpower requirements for shutdown activities, detector (re-) integration & survey. Secretariat 3.Explain why costs (at least during the next 4-5 years) are considered as M&O. Communications 4.Give the assumptions used for charging; in the 2002/2007 totals there is a factor of >15 between the smallest and the largest estimates.

19/9/2001Plenary RRB October 22, 2001 DS 8 Strategy for the Scrutiny On-line computing 5.Give the the total number of boxes and the number of boxes per FTE of manpower assumed for system management. Test beams, calibration facilities 6.Explain why costs (at least during the coming 3-4 years) are considered to be M&O. Laboratory Operations 7.In the 2002/2007 totals for these activities, there is a factor of >20 between the smallest and the largest experiment. This discrepancy should be explained. General Services (#) 8.Explain how cooling & ventilation costs have been reached.  Separate out C&I costs from M&O costs: M&O consists of work in or close to the pit C&I consists of work in assembly and test areas

19/9/2001Plenary RRB October 22, 2001 DS 9 Strategy for the Scrutiny  M&O consists of two categories  I. From now on Running the collaboration that includes Outreach activities, administrative and secretarial assistance, stationery (economats), stationery office (print shop for collaboration documents, etc...) Maintaining test beam facilities, workshops, active and passive storage areas Maintaining installations (cryogenic compressors, vacuum, detectors, etc…)  II.From 2005 onwards Running the experiment Keeping detectors in running order, all shutdown activities, etc…

19/9/2001Plenary RRB October 22, 2001 DS 10 Strategy for the Scrutiny  Reasons for C&I costs:  Scale of experiments was not fully appreciated.  Unforeseeable circumstances (i.e. delays in civil engineering or necessary changes in integration strategy)  In the past, one part of C&I costs were paid from exploitation budget of the CERN group participating in the experiment  Only ATLAS and CMS have at present C&I costs

19/9/2001Plenary RRB October 22, 2001 DS 11 Strategy for the Scrutiny  ATLAS Cryogenics: M&O and C&I

19/9/2001Plenary RRB October 22, 2001 DS 12 Strategy for the Scrutiny  Example: Simultaneous separation of M&O and C&I, and Point1 and B180 ATLAS POINT 1 [kCHF] ATLAS B180 (West Hall) [kCHF]

19/9/2001Plenary RRB October 22, 2001 DS 13 Strategy for the Scrutiny  Example: Cooling and Ventilation (0.5% to 2.5% of capital investment, 50% Manpower and 50% Consumables)

19/9/2001Plenary RRB October 22, 2001 DS 14 Strategy for the Scrutiny  Example: ATLAS Magnet and Controls Cost reduction achieved by change of strategy

19/9/2001Plenary RRB October 22, 2001 DS 15 M&O SG Recommendations Video-conferencing should not be listed as an M&O item, since Collaborating Institutions operate their own video-conferencing facilities free of charge. Cooling & Ventilation as well as Power (in General Services) should not exhibit a step function behaviour starting in 2002, but rather a ramp-up reaching a plateau value in 2005/6. Reliable Power metering should be introduced. Transparent accounting for CERN services. The ventilation systems of experimental areas and auxiliary buildings are linked to personal safety. They should therefore appear under Safety (a C cost). Secretarial Assistance (in Secretariat) should show a reasonable ramp-up.

19/9/2001Plenary RRB October 22, 2001 DS 16 Results Visible cost reduction was achieved in the case of Magnet Controls by changing a foreseen service contract into a result- and multitask-oriented contract. C&I was separated out from both Category A and B M&O costs. The manpower requirements for Shutdown Activities, Detector (Re-) Integration and Survey, General Technical Support (General Services) have been determined. The transitions from C&I to M&O for these activities have been identified. Service contracts have been identified as cost drivers, but were difficult to scrutinize in the time available. The Cooling & Ventilation and Power costs have been re- assessed and now show a reasonable ramp-up. Shutdown activities now start in 2005

19/9/2001Plenary RRB October 22, 2001 DS 17 Results M&O costs in categories A and B now show a “plausible” shape:

19/9/2001Plenary RRB October 22, 2001 DS 18 Results C&I costs now show a “plausible” shape:

19/9/2001Plenary RRB October 22, 2001 DS 19 Conclusions  M&O and C&I costs as far as scrutinized are sound  Time profile of C&I costs indicates urgency to find means to cover these costs  Adequate subsystem oriented templates for category B costs to be prepared  Scrutiny of B costs and C costs still to be done  Collaborations are asked to find ‘novel’ ways to reduce manpower costs