Isotope R&D Facility A proposed addition to the HRIBF driver upgrade Mike Saltmarsh HRIBF Users’ Meeting Nov 13 th 2009.

Slides:



Advertisements
Similar presentations
WG1: High Power Targets PASI 2013 Working Group Sessions Introduction Convened by: Dr. C. Densham (STFC/RAL), Mr. P. Hurh (FNAL)
Advertisements

SUPERCONDUCTING RF (SRF) SYSTEMS Peter McIntosh (STFC) Accelerator-driven Production of Medical Isotopes 8 th – 9 th December
Nordion and TRIUMF A 37 Year Partnership EW Vogt Science Symposium February 7 th 2015 Presented by: Jerry Porter, Director Nordion Vancouver.
GEANT4 Simulations of TIGRESS
Office of Nuclear Energy 1May 20, 2013 Property Management Workshop Office of Nuclear Energy Program Perspective Delivering Nuclear Solutions for America's.
A world of hope through accelerator- based science and technologies.
Office of Science U.S. Department of Energy 1 Nuclear Physics Program RHIC Users Meeting May 2008 Jehanne Simon-Gillo Acting Associate Director of the.
Chris Tennant Jefferson Laboratory March 15, 2013 “Workshop to Explore Physics Opportunities with Intense, Polarized Electron Beams up to 300 MeV”
RaDIATE 1 st Annual Collaboration Meeting May Cost-effective Irradiations Discussion Radiation Damage In Accelerator Target Environments.
SYNERGY of Irradiation and PIE Facilities at BNL N. Simos RaDiATE Meeting December 12, 2014 BLAIRR Tandem van de GRAAFF NSLS II XPD Beamline (PIE)
U.S. Department of Energy’s Office of Science Dr. Raymond Orbach February 25, 2003 Briefing for the Basic Energy Sciences Advisory Committee FY04 Budget.
Solid Target Options NuFACT’00 S. Childress Solid Target Options The choice of a primary beam target for the neutrino factory, with beam power of
Recent highlights of isotope research and development at BLIP Dmitri G. Medvedev November 19, 2009.
Martin Freer Materials Irradiation at University of Birmingham.
A facility for Nuclear, Atomic, Material and Radiobiology Sciences. Delivering stable (from C to U) and radioactive ions (from He to Xe) in the energy.
Leveraging Government support and global partnerships to increase biologics manufacturing capacity.
Beam load estimates for the PS2 Beam Dump Systems T. Kramer, M. Benedikt, B. Goddard.
Simultaneous Delivery of Parallel Proton Beams with the EURISOL Driver
Overview of Cyclotron Facilities
Managed by UT-Battelle for the Department of Energy An Overview of the ORNL Nuclear Forensics Program June 18, 2009 Brad Patton.
CERN NuPAC meeting Dec 2005 The future of ISOLDE: accelerated radioactive beams Peter Butler 1.HIE-ISOLDE 2.EURISOL.
10-Year Vision: expanded RIB program with: three simultaneous beams increased number of hours delivered per year new beam species increased.
Office of Science U.S. Department of Energy RHIC Users Meeting BNL; June 8, 2006 Gulshan Rai RHIC/AGS Users Meeting Gulshan Rai Program Manager for Heavy.
APEC ENERGY WORKING GROUP FRAMEWORK PROPOSAL FOR IMPLEMENTING ENERGY INVESTMENT RECOMMENDATIONS (November 2004).
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
BESAC Dec Outline of the Report I. A Confluence of Scientific Opportunities: Why Invest Now in Theory and Computation in the Basic Energy Sciences?
Proposal for Experiment S291: " Residual radioactivity induced by U ions - experimental investigation and longtime predictions" GSI, Darmstadt: G.Fehrenbacher,
UKNF OsC RAL – 31 st January 2011 UKNF - Status, high lights, plans J. Pozimski.
Principle Investigators Suzanne V Smith CAD, BNL
The Materials Test Station: An Accelerator Driven Neutron Source for Fusion Materials Testing Eric Pitcher Presented at: Sixth US-PRC Magnetic Fusion Collaboration.
19-September-2007 Helsinki EURISOL-EURONS Town Meeting 1/6 High-Performance Pulsed-Power for Radioactive Ion Beams HP 3 RIB Luis Redondo ISEL, IST, CFNUL,
Production of innovative radionuclides at ARRONAX and 211 At RIT F. Haddad GIP ARRONAX.
Owned and operated as a joint venture by a consortium of Canadian universities via a contribution through the National Research Council Canada Propriété.
Welcome to Jefferson Lab R. D. McKeown Jefferson Lab Hypernuclear Workshop May 27, 2014.
Accelerator Physics in Finland RECFA A. Virtanen.
HRIBF HRIBF - proton-rich beams Dan Stracener HRIBF Users Workshop November 13, 2009.
HWDB: Operations at the Spallation Neutron Source Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager.
Authorization and Inspection of Cyclotron Facilities Design, Layout and Shielding.
Proton Driver Keith Gollwitzer May 31, Initial Design Overview For design purposes, the following is assumed –H - beam comes from PIP II and follow-on.
Managed by UT-Battelle for the Department of Energy Authorized Limits Request for Release of Neutron Scattering Experiment Samples From SNS and HFIR Donald.
Approach for a High Performance Fusion Power Source Pathway Dale Meade Fusion Innovation Research and Energy ARIES Team Meeting March 3-4, 2008 UCSD, San.
Electron Sources for ERLs – Requirements and First Ideas Andrew Burrill FLS 2012 “The workshop is intended to discuss technologies appropriate for a next.
SECONDARY-BEAM PRODUCTION: PROTONS VERSUS HEAVY IONS A. Kelić, S. Lukić, M. V. Ricciardi, K.-H. Schmidt GSI, Darmstadt, Germany  Present knowledge on.
Prepared by Collaborative Economics. EXECUTIVE SUMMARY  San Diego is participating in a new global innovation economy  San Diego’s global reach has.
Beam development for the Center of Excellence for RIB Studies for Stewardship Sciences – Target and ion source for screening studies at Oak Ridge Workshop.
ARIEL Building Pierre Bricault. Proton Beam specification The proton beam energy must be between 450 to 500 MeV. 200 µA with proton beam intensity losses.
Vertex detector R&D Work Plan in /3/11 Y. Sugimoto for KEK-Tohoku-TohokuGakuin-Niigata- ToyamaCMT Collaboration.
Interprofessional Learning Clinical Placement Toolkit Module: Capacity What type of placement can we offer? “Building and sustaining training in WA”
Summary of the State of the Art of Programme Implementation CENTRAL EUROPE PROGRAMME Project development seminar Prague, 1-2 February 2010 Monika.
Itacil C. Gomes I.C.Gomes Consulting & Investment inc. Project X Forum on Spallation Sources for Particle Physics March 19-20, 2012 Fermi National Accelerator.
Proton Driver Keith Gollwitzer Accelerator Division Fermilab MAP Collaboration Meeting June 20, 2013.
LOGO Status and activities of the Korea Proton Accelerator Users Association *Korea Proton Accelerator Users Association S. J. Noh Department of Applied.
Target Proposal Feb. 15, 2000 S. Childress Target Proposal Considerations: –For low z target, much less power is deposited in the target for the same pion.
Alternative Methods for Production of Ac225 James Harvey 1, Jerry A. Nolen 3, Thomas Kroc 4, Itacil Gomes 5, E. Philip. Horwitz 2, Daniel R. McAlister.
Improved performance of Variable Energy Cyclotron(VEC) Variable Energy Cyclotron Centre Kolkata P S Chakraborty, B Ch Mandal, S K Thakur, M Das, S Som,
1 RHIC NSRL LINAC Booster AGS Tandems STAR 6:00 o’clock PHENIX 8:00 o’clock 10:00 o’clock Polarized Jet Target 12:00 o’clock RF 4:00 o’clock (AnDY, CeC)
Summary of IAP comments from 2007 EURISOL Town Meeting
Plans and Activities at CERN
Outline Introduction : KOMAC & RI production plan Beam line design
Massachusetts Clean Energy Center Budget Overview
KIT TA Status Felix Bögelspacher, Bärbel Bräunling, Wim de Boer, Alexander Dierlamm Prof. Dr. Max Mustermann | Name of Faculty.
Witold Nazarewicz (HRIBF scientific director)
The BLAIRR Irradiation Facility Hybrid Spallation Target Optimization
Improvement of beam current in KIRAMS-13 using upgrade of
Design of a PET-isotope-based hadron therapy facility
Susan Hogle, Julie G. Ezold
MAX IV Laboratory National Synchrotron Light Source – two storage rings (1.5 & 3.0 GeV) and a Short Pulse Facility Characteristics of User Program: 15.
W. T. Weng Brookhaven National Laboratory
K. Tilley, ISIS, Rutherford Appleton Laboratory, UK Introduction
A world of hope through accelerator- based science and technologies.
Presentation transcript:

Isotope R&D Facility A proposed addition to the HRIBF driver upgrade Mike Saltmarsh HRIBF Users’ Meeting Nov 13 th 2009

2Managed by UT-Battelle for the U.S. Department of Energy Presentation_name Proposed Isotope Production R&D Facility National Context There is a national need for a reinvigorated DOE isotope program – selected recommendations from NSAC report – “Support a sustained research program…. In the production and supply of isotopes….” – “Investment in new production capabilities” – “Investment in workforce development”

3Managed by UT-Battelle for the U.S. Department of Energy Presentation_name Shared use of the C70 is unusually attractive A substantial allocation of beam time to the isotope program would be available ( ~ 4500h/yr) Little or no impact on the HRIBF mission or flexibility would be incurred Concurrent construction of the isotope facility would not significantly impact the C70 upgrade construction ORNL already has all the required isotope infrastructure from production through transportation The incremental capital cost to the isotope program would be modest (7-10M$) The opportunity to share operations costs would benefit both programs

4Managed by UT-Battelle for the U.S. Department of Energy Presentation_name Elements of the proposed facility Dedicated isotope target vault Two beamlines from the C70 to the isotope vault Two target stations, one a commercially available standard, the other compatible with the BNL/LANL target systems Systems for remote transfer of the target modules from target station to transfer cell. A transfer cell to package irradiated modules for transfer to the ORNL hot cells Currently estimated total incremental cost is 7-10 M$ Items in red are part of the isotope facility

5Managed by UT-Battelle for the U.S. Department of Energy Presentation_name IBA Solid Target System Specifications Maximum power dissipation of target assembly (on blank copper target): 12 kW Beam profile on target: Gaussian 6 mm FWHM, rotated to uniform flat beam Angle of target face to beam: 6 degrees

6Managed by UT-Battelle for the U.S. Department of Energy Presentation_name Beams available from the C70 IonExtraction E min MeV E max MeV I max  A H-H- stripping D-D- stripping H2+H2+ ESD-3550 α ESD-7050

7Managed by UT-Battelle for the U.S. Department of Energy Presentation_name Important Characteristics of the C70 and it’s anticipated operating regimes Very high reliability (~ 95% for commercial C30) – Expectations for the HRIBF operating environment ~ 6600h/yr of extracted beam availability. 42 weeks, 156 h/week, 7 day operation. Dual extraction capability for negative ion beams – HRIBF needs for RIB production ~ 4000 h/yr – Most RIB production (3000h/yr) requires the full energy proton beam at intensities 50  A and higher – Allows simultaneous use of 70 MeV protons by isotope program. Independent intensity control (within limits) HRIBF operation includes periods of days-weeks when C70 beams not required – h/yr of dedicated beams (including alphas) available for the isotope program

8Managed by UT-Battelle for the U.S. Department of Energy Presentation_name Elements of the Proposed Isotope Program would address many of the needs identified in the NSAC report Radioisotope production R&D – New production regimes, eg for 225 Ac – Excitation functions, thick target yields – Nuclear and radiochemistry – High power target design Radioisotope Production – Research isotopes, eg 211 At, 68 Ge, 7 Be – Commercial Isotopes, eg 82 Sr, 68 Ge Education and Training

9Managed by UT-Battelle for the U.S. Department of Energy Presentation_name Production R&D example Short-lived (46 m) alpha emitter 213 Bi offer great promise for radioimmunotherapy – Attach radionuclide to suitable antibody – Antibody preferentially attaches to tumor cell – Radiation delivered within ~100  of tumor cell, not elsewhere Supplies are limited, hindering clinical trials – Currently source is 233 U Th (7880y) Ac (10d) as a generator for 213 Bi – R&D required to investigate other possible production methods – Funded proposal to look at excitation functions and thick target yields for protons on 230 Th and 232 Th targets* at HRIBF – *

10Managed by UT-Battelle for the U.S. Department of Energy Presentation_name ORNL Infrastructure Available for Education and Training Production R&D – Seek University partnerships Training programs using ORNL facilities – Production facilities – Hot cells for target processing – Radiochemistry labs – Animal facilities – Transportation Workshops – Workshop on next generation of radiochemists planned for spring 2010

11Managed by UT-Battelle for the U.S. Department of Energy Presentation_name Shared use of the C70 is unusually attractive A substantial allocation of beam time to the isotope program would be available ( ~ 4500h/yr) Little or no impact on the HRIBF mission or flexibility would be incurred Concurrent construction of the isotope facility would not significantly impact the C70 upgrade construction ORNL already has all the required isotope infrastructure from production through transportation The incremental capital cost to the isotope program would be modest (7-10M$) The opportunity to share operations costs would benefit both programs