ENERGY INTENSIVE USERS GROUP Ian Langridge Chairman January 2010 Eskom’s Revenue Application for Multi Year Price Determination MYPD (2)

Slides:



Advertisements
Similar presentations
1 Why the World Bank Successful Privatisations are Useful for the Audit of Privatisation? The World Bank rich experience worldwide through providing technical.
Advertisements

THE ECONOMIC DEVELOPMENT IN AFRICA REPORT st January 2014 Chapter 4 Policies for Accelerating Investment in Africa: National and Regional Aspects.
22 August 2012 Regulating for productive efficiency – an assessment of the regulatory framework faced by Eskom Presented at the South African Economic.
Responding to the Electricity Challenges: Five Point Plan Overview 19 December 2014 Confidential 1.
1 By: Mr. Zafar Mahmood Chairman, Water and Power Development Authority OCTOBER 2014.
Portfolio Committee on Energy Securing financial sustainability (in response to lower tariff decision) May 2013.
Click to edit Master title style 0 Eskom’s MYPD2 Tariff Application 03 December 2009 Brian Dames – Chief Officer (Generation Business)
Black Business Council 7 June South African partner : 40 % 2. Local content, job creation & BEE: 30 % 3. Contribution towards local community.
Key Policies Improving Business and Investment Climate Presenter: Governor CBBH: Kemal Kozarić, MA.
 Dr. Ibrahim Togola The challenges of African Energy Policy in the 2010 Berlin,14th June 2010.
Section 1.1 Financial Decisions and Goals.  Definition: arranging to spend, save, and invest money to live comfortably, have financial security, and.
PROJECT FINANCE INITIATIVE and PUBLIC PRIVATE PARTNERSHIPS Simon Par Keeling, Société Générale Paris.
Transport Policy as an Enabling Framework for Green Growth in South Africa Ngwako Makaepea Department of Transport 18 May 2010.
1 Georgian National Energy and Water Supply Regulatory Commission Tariff Regulation Gocha Shonia Department of Methodology and informational provision.
Response to the Eskom Revenue Application for the Multi Year Price Determination for the period 2010/11 to 2012/13 (MYPD 2) Presentation by Business Unity.
Page 1 3/13 – Lynchburg 4/23 – Fredericksburg 3/28 – Charlottesville 4/12 – Danville.
SOLAR PARK TP Nchocho Group Executive: Investment Banking Division 28 October 2010 Development Bank of Southern Africa.
What if we are in for a decade of slow/low growth? Where and how should funds invest? JOSEPH BUSHA, BSc, BSc. Hons, MSc, MPhil.
Why are economic and financial instruments needed? A presentation made by Noma Neseni, IWSD.
09/09/20151 ESKOM’S PROPOSED REVENUE APPLICATION MULTI-YEAR PRICE DETERMINATION 2010/11 TO 2012/13 (MYPD2) NERSA’s PUBLIC HEARING 19 January Port.
1 27 March 2013 MYPD3 Briefing Session – Portfolio Committee on Energy.
Influence of foreign direct investment on macroeconomic stability Presenter: Governor CBBH: Kemal Kozarić.
An Introduction to Public Private Partnerships: Why Government needs to work with the private sector Vilnius 22 nd November 2006 Stephen Harris - Head,
Ideas for liberty The Energy Challenge for Europe – and Lithuania Vilnius, 21 October 2008 Carlo Stagnaro Director, Research & Studies Istituto Bruno Leoni.
CITY OF CAPE TOWN’S SUBMISSION ON ESKOM’S MULTI-YEAR PRICE DETERMINATION – 2010/11 – 2012/13 (MYPD 2) City of Cape Town represented by : Alderman Ian Neilson.
A new start for the Lisbon Strategy Executive summary Increase and improve investment in Research and Development Facilitate innovation,
1 Click to edit Master subtitle style 5/24/12, Version Control South African Electricity Supply Sector ISMO Bill Independent System and Market Operator.
MYPD2 SACCI VIEWS AND RECOMMENDATIONS TO NERSA 21 January 2010 Peggy Drodskie Executive Advisor to the CEO.
Towards an Affordable, Stable Electricity Supply MISSION CRITICAL FOR SOUTH AFRICA Public Presentation To NERSA by Nick Holland Chief Executive Officer.
APEC ENERGY WORKING GROUP FRAMEWORK PROPOSAL FOR IMPLEMENTING ENERGY INVESTMENT RECOMMENDATIONS (November 2004).
Annual Results Presentation 27 August 2009 Jacob Maroga – Chief Executive Empowering the South African dream.
The Institute for Municipal Finance Excellence NERSA HEARINGS 20 JANUARY 2010 Eskom’s Revised Revenue Application MYPD 2010/11 – 2012/13.
SMART ELECTRICITY Planning and building a modern infrastructure for South Africa SMART Electricity Planning a healthy, modern, affordable electricity supply.
Critical Issues Electricity Distribution Industry Restructuring Electricity Distribution Interests of Distributors Power Shortages and the Economy Importance.
Introducing Competition in the ESI Naresh Singh Head: Compliance.
Africa Utility Week 05 Challenges of Undertaking an IPP in South Africa as a PPP James Aiello 17 May 2005.
The Multi- Year Price Determination MYPD Presented by: Thembani Bukula Regulator Member – Electricity Regulation.
2008 Electricity Distribution Maintenance Summit Stream 3A: Funding, Investment and Financial issues 10 June 2008 Theo van Vuuren Divisional Executive.
Deepening Integration in SADC - Macroeconomic Policies and Their Impact South African Country Study 3rd – 6th April 2006 Zambezi Sun Hotel, Livingstone,
Structural Transformation and Natural Resources in Africa ( Second Part ) Presented by Xia Li (Sherry)
United Nations Framework Convention on Climate Change (UNFCCC) Twelfth Conference of Parties (COP12) – Second Meeting of Parties (MOP2) Climate Change.
Submission to NERSA on Revised Eskom MYPD2 Chemical and Allied Industries Association January 2010.
Presentation to Select Committee on Economic Development
Municipal involvement in the energy crisis Select Committee on Labour & Public Enterprises.
An embedded cogenerators response Andrew Carr
Ferrial Adam Energy and climate change campaigner GREENPEACE AFRICA PRESENTATION TO PORTFOLIO COMMITTEE: PROPOSED NATIONAL WATER.
A Presentation to the: Portfolio Committee on Minerals and Energy (30 August 2001) Given by: Barry Bredenkamp Bonesa Electricity (Pty) Ltd Efficient Lighting.
Supply-Side Economics
BIDDER’S CONFERENCE: Eskom Grid Connection Process and related matters Date: 16 August 2012.
ITCILO/ACTRAV COURSE A Capacity Building for Members of Youth Committees on the Youth Employment Crisis in Africa 26 to 30 August 2013 Macro Economic.
Is your project investable? Key tips to make sure it is. 15 th March 2016 A Presentation at Power and Electricity World Africa conference, Sandton Convention.
Understanding the Integrated Resource Plan (IRP 2010 Rev 2)
Building a Sustainable Funding Model
REFLECTED IN JAMAICA’S ENERGY POLICY
SECRET.
NERSA presentation at the PPC meeting held on 24 May 2006
EIUG Energy Intensive Users Group Comments on the Energy Bill
Medium-Term Expenditure Framework: Lessons
United Nations Framework Convention on Climate Change (UNFCCC) Twelfth Conference of Parties (COP12) – Second Meeting of Parties (MOP2) Climate Change.
Creating a ‘country compact’ to ensure a secure and sustainable future
Creating a ‘country compact’ to ensure a secure and sustainable future
Creating a ‘country compact’ to ensure a secure and sustainable future
Creating a ‘country compact’ to ensure a secure and sustainable future
Creating a ‘country compact’ to ensure a secure and sustainable future
The Role of Takaful in Economic Development of Africa By Mohsin M
Creating a ‘country compact’ to ensure a secure and sustainable future
Creating a ‘country compact’ to ensure a secure and sustainable future
FFC Briefing to the Portfolio Committee on Energy
SOUTH AFRICAN INSURANCE ASSOCIATION
Presentation transcript:

ENERGY INTENSIVE USERS GROUP Ian Langridge Chairman January 2010 Eskom’s Revenue Application for Multi Year Price Determination MYPD (2)

Introduction The EIUG is the association of large energy intensive consumers in South Africa. Membership currently consists of 38 of the largest energy consumers That together, consume 40% of the total electricity sales in South Africa.

Context Eskom needs a long term sustainable return on its capital invested, However Eskom’s funding request of a 35% increase per year for the next three years poses a real economic threat, which will result in lower economic growth rates, lower employment growth and ultimately job losses. This is unacceptable and, we believe, unnecessary in achieving the reliable and cost effective supply of electricity.

EIUG Focus South Africa deserves and is entitled to, reliable and affordable electricity for all. As bulk consumers the EIUG members have a vital role in the economy in stimulating bulk electricity demand on a 24 hour a day basis, 7 days a week. This infrastructure supports cost effective and reliable supply to consumers who require less energy at particular times in the day

The NERSA dichotomy It is clear that the challenge facing NERSA is the trade off between a strong electricity sector and a strong economy The price increase needed to sustain Eskom supports neither of the above aspirations Eskom needs a cash injection and an improvement in its operating efficiency to support a strong economy No provision has been made for the cash injection and the increase in operational cost must be borne by the consumer Electricity is a production input cost to all in the economy and has a significant multiplier effect

Key elements of the EIUG submission South Africa needs a comprehensive Integrated Resource Plan [IRP] The IRP in its present form is not adequate to enable NERSA to make a rational cost determination Large power plants, be they conventional coal or nuclear require long planning horizons Serious and urgent effort needs to be allocated to establishing the IRP The IRP requires a funding model and plan This plan must define how the income for feasibility studies, construction and operating costs, equity, debt and private sector investment; and the make up of the energy and technology mix for the country is optimised to make best use of our limited skills and resources for the benefit of all South Africans

Eskom Efficiency Last year at the interim price increase hearings the EIUG and COM defined a number of areas where Eskom could improve on its operational efficiency, notably in the coal procurement arena. It is recommended that Eskom be requested to deliver an improvement plan as part of these deliberations so that operating cost reductions can begin to materialise The EIUG would support Eskom provision for expenditure in the transmission and distribution sectors but is mindful of the logistical difficulties in spending large sums of money effectively in a short time span

Eskom Cash Injection The proposal for Eskom to divest part of the Kusile project is a step in the right direction, however Kusile will have limited uptake as has been discussed by many other speakers but primarily due to the fact that construction risk has already been managed by Eskom and potential bidders cannot apply their expertise to enhance their capital return The Kusile project risk is with Eskom and the South African consumer – not so some of the older established power stations with good track records where potential investors would be keen to show their skills – if the market became encouraging for them The current market for IPPs is considered hostile so urgent attention is required to tap into this opportunity

Key elements of the EIUG submission The “country plan” Eskom funding Security of Supply Limiting job losses The long term price cone Non core issues

The “Country Plan” The development of a country plan [in the form of an IRP] is urgent and will present some short term options allowing for a more manageable roll out of the long term build program The appropriate legal and regulatory framework to convert SA from an IPP hostile environment to facilitate the introduction of IPPs must be urgently introduced

Eskom Funding A revision of the Eskom funding model is urgently required Eskom estimates need challenging: Cost of capital Asset value and valuation methodology Depreciation Primary energy and operating costs Capital expenditure Medupi and Kusile are too expensive and late

Security of Supply One factor that has reduced the price increase from 45% to 35% is by reducing the RSA forecast demand based largely on an aggressive DSM uptake However past uptake has been low and the increased uptake is not supported by a change in DSM management Similarly the mass role out of solar water heaters is both financially and operationally constrained

Limiting Job Losses It is imperative that there is adequate and affordable electricity capacity to promote economic growth and that our price leadership role in this arena is not lost Eskom has conceded that it is not in a position to meet all future demand, Hence the integrated roll of IPPs is critical by Development of an appropriate legal, regulatory and commercial framework to facilitate IPPs

The Long Term Price Cone This needs to be reduced by: Reducing Eskom return on investment Managing and reducing the new build cost Alternate funding including sale of assets Accelerating the pace of IPPs Decreasing Eskom’s operating expense inflation Bringing Eskom’s operating efficiencies under control

Non core Issues Eskom has removed some expenditure on non core assets however it is not clear that this responsibility has been accepted by counter parties [e.g. road maintenance]

Thank You