Bonneville Spillway Flow Discrepancy TMT – August 4 th 2004 Laurie Ebner Hydraulic Engineering – Portland District US Army Corps of Engineers.

Slides:



Advertisements
Similar presentations
Flood Risk Analysis – the USACE Approach
Advertisements

Evaluate Spawning of Fall Chinook and Chum Salmon Just Below the Four Lowermost Columbia River Mainstem Dams Project PNNL.
Spillways Abdüsselam ALTUNKAYNAK, PhD Associate Professor,
Passage Behavior and Survival for Radio-tagged Subyearling Chinook Salmon at Ice Harbor Dam, 2006 Fish Ecology Division Northwest Fisheries Science Center.
John H. Kerr Dam and Reservoir John H. Kerr Dam and Reservoir U.S. Army Corps of Engineers Wilmington District.
WinTR-20 Calibration ProceduresFebruary WinTR-20 Calibration Procedures.
St. Louis District Water Control Operations
CHAPTER FOUR Stream flow measurement
TMT Presentation March 31, 2010 Scott English Water Quality Program Manager NWD Reservoir Control Center.
US Army Corps of Engineers BUILDING STRONG ® Methods for Determining Maximum Flood Elevations Landward of Failed Levees: An Example from the Great Missouri.
Chapter 5 LIQUID - IN - GLASS THERMOMETERS. “… the degree of their scales agree with one another, and their variations are within limits …” Daniel Gabriel.
Pumping Apparatus Driver/Operator
Engineering Hydrology (ECIV 4323)
Hydrological Information System Module 20 – Integrated Reservoir Monitoring System.
Calculate: 1) The angle of the ladder to the ground.
Making Measurements and Reading Scales
Broad-crested Weir.
31 DECEMBER VARIABLE FLOOD CONTROL DRAFT FOR LIBBY RESERVOIR U.S. Army Corps of Engineers Northwestern Division, North Pacific Region.
MANAGEMENT USES OF INFORMATION Pertemuan 02 Matakuliah: F0204 / SISTEM AKUNTANSI Tahun: 2007.
Chapter 9: Introduction to the t statistic
L Chedid 2008 Significance in Measurement  Measurements always involve a comparison. When you say that a table is 6 feet long, you're really saying that.
Federal Columbia River Power System Operations Planning.
Earth Science Making Measurements and Reading Scales 1.
Sediment transport in wadi systems
1 Brainstorming for Presentation of Variability in Current Practices Scenario B. Contor August 2007.
US Army Corps of Engineers ® Engineer Research and Development Center Coastal and Hydraulics Laboratory Greenup Locks and Dam, Ohio River.
WinTR-20 SensitivityMarch WinTR-20 Sensitivity to Input Parameters.
Hydrosystem Operations and Fish Recovery in the Columbia River Basin U
Bathymetry Changes Caused by a Tropical Storm Chris Scheiner and Gary Pelton US Army Corps of Engineers.
Population All members of a set which have a given characteristic. Population Data Data associated with a certain population. Population Parameter A measure.
MVS Mainstem Forecast Model Update: NETMISS2 by Joel Asunskis, P.E. Hydraulic Engineer, St. Louis District Water Control U.S. Army Corps Of Engineers October.
Big Horn Lake Sediment Management Study. US Army Corps of Engineers Omaha District Study Background Bureau of Reclamation and Omaha District Interagency.
Engineering History and 2008 Operation of the Bonnet Carré Spillway: A Controlled Levee Crevasse on the Lower Mississippi River Christopher G. Brantley,
Nutrient Criteria for the plains regions of Missouri.
BUILDING STRONG ® PORTLAND DISTRICT 1. BUILDING STRONG ® PORTLAND DISTRICT 2 BiOp Performance Standards for Dam Passage Survival RPA RM&E Actions - Strategy.
SPRAY EQUIPMENT Basic Components and Operations. Purposes  Used to apply agricultural chemicals  Spray pressures range from near 0 to over 300 pounds.
Hydro Power 102. Hydroelectric Models in the Northwest.
BUILDING STRONG ® Dworshak SOR # Transition to Refill Stephen Hall P.E., Reservoir Regulation Walla Walla District USACE.
IMPROVING MILLERTON LAKE FLOOD CONTROL OPERATIONS TO INCREASE WATER SUPPLY Mr. Antonio M. Buelna, P.E. Mr. Douglas DeFlitch Ms. Katie Lee October 29, 2009.
US Army Corps of Engineers BUILDING STRONG ® Willamette High Head Bypass August 2014 FPT Brief Jeff Ament, Marie Phillips, Fenton Khan Portland District.
Prepared by: Burnham – Floodplain Study October 23, 2009 Presented by: Marty Spongberg, PhD, PE, PG AMEC Geomatrix, Inc.
US Army Corps of Engineers Coastal and Hydraulics Laboratory Engineer Research and Development Center Lower Susquehanna River Watershed Assessment SedFlume.
Martin Rule Curve Study Ashley McVicar, APC Maurice James, Water Resources Consulting LLC.
WinTR-20 SensitivityFebruary WinTR-20 Sensitivity to Input Parameters.
US Army Corps of Engineers BUILDING STRONG ® Mark Twain Lake Water Control Manual Update Joan Stemler St. Louis District Water Control.
NON-TREATY STORAGE AGREEMENT “Introduction to Operations and the Non Treaty Storage Scenarios” Presenter: Jim Gaspard.
U.S. Army Corps of Engineers Wilmington District Real-Time Conservation Pool Storage Accounting for the Falls Lake Project.
Martin Rule Curve Study Ashley McVicar, APC Maurice James, Water Resources Consulting LLC.
Bradshaw Model. Upstream Downstream Discharge Occupied channel width Channel depth Average velocity Load quantity Load particle size Channel bed roughness.
Analyzing the Effects of Navigation Structures Edward Brauer, P.E. Applied River Engineering Center U.S. Army Corps of Engineers – St. Louis District.
US Army Corps of Engineers ® Engineer Research and Development Center West Bay Diversion Evaluation Integration of Results 6 Month Progress ERDC West Bay.
US Army Corps of Engineers BUILDING STRONG ® Mid-Columbia River Projects and Large Spill Events Ken Duncan Portland District PM Environmental Compliance.
Control Structure Types
Proposed PIT Tag Antenna Arrays for Bonneville Dam PH1 Ice and Trash Sluice Way PTAGIS Field Office Kennewick, Washington June 2015.
FUNDAMENTALS OF CONTROLLING DHANYA ASOKAN M120005MS.
US Customary Measurement System
Hydrological Information System
CANAL NETWORK CONTROL AJAY K BASU
Hydrological Information System
Se-Yeun Lee1, Alan F. Hamlet 1,2, Carolyn J. Fitzgerald3, Stephen J
US Customary Measurement System
CHAPTER FOUR Stream flow measurement
Gradient The land surrounding the river channel. Valley The middle section of the river. Upper Course The steepness of the river. Mid Course The part of.
2017 Flow, Debris, spill and TDG
US Customary Measurement System
US Customary Measurement System
US Customary Measurement System
CHAPTER FOUR Stream flow measurement
CHAPTER FOUR Stream flow measurement
US Customary Measurement System
Presentation transcript:

Bonneville Spillway Flow Discrepancy TMT – August 4 th 2004 Laurie Ebner Hydraulic Engineering – Portland District US Army Corps of Engineers

Flow Discrepancy Flow discrepancy between Bonneville and The Dalles reported in 2003 Project discharge at Bonneville should be higher than The Dalles (additional inflow) Discrepancy appeared to correspond to new spill patterns instituted at Bonneville in 2002 Initially uncertain if discrepancy at Bonneville or The Dalles. –Web data for The Dalles is verified by comparing to the USGS gauge data at The Dalles (just downstream of the project) – “

Bonneville Spillway Gate History Originally two gate types –50 foot high gates (Bays 4-15) –60 foot high gates (Bays 1-3, 16-18) Bonneville Rating Curve updated in 1967 In 1972 all gates were modified to 60 foot high gates and all of the gate bottom edges were modified from a flat bottom plate to one with a 45 degree angle to reduce vibration. –The modified gate edges may have changed the flow characteristics and thus the discharge coefficient.

Discrepancy between actual gate opening and reported gate opening (gate is approximately 4 inches lower than being reported) for openings of 0-2 feet. Additional measurements need to be taken to determine over what range this error applies. Bonneville Spillway Gate History

Planned Actions Develop plan for calibration of each spillway gate – available for review 8/11/2004 Calibrate/verify the gate opening for each spillway gate Verify rating curve (especially for small gate openings) Verify that changes implemented take care of the historical discrepancy in total river flow between The Dalles and Bonneville Develop strategy to communicate discrepancy so previous published work can be properly interpreted

Additional Facts Large 50 foot vertical lift spillway gates are not typically designed for fine regulation of flow. The uncertainty or range of error at small gates openings defined as less than about 10% of the gate height (5 feet for Bonneville) is large. There is always inherent uncertainty when regulating a river system. Sources of discharge error at a large project like Bonneville Dam include: –Tributary contributions –Ladder and other miscellaneous flows –At best, a 5% difference between actual and computed discharge at a project would be considered good agreement.

Additional Facts The calibration errors would be significant only when the project was trying to meet a target discharges such as the 75K daytime spill (set for adult fallback purposes) or some other target. Typically, the project discharges through the spillway at the gas cap discharge – at which time the gas concentration in the river downstream determines the spill volume that can be passed. When total river flows exceed the powerhouse capacity, the flow is discharged through the spillway, increasing the 75K daytime spill. Reducing the error in discharge measurements since the largest error occurs at low spillway discharges.

Assumes a Bonneville Forebay of 74 feet Desired is using actual gate opening requested and coefficient as determined in 1967 model work. Actual is subtracting 0.3 feet from gate opening and using the same coefficients as desired but modified based on gate opening. Spill Discrepancy Estimates Data will be updated after completion of spillway gate calibration

Recommendations Modify the measurement system at Bonneville such that the reported flow from Bonneville is closer to the actual flow. Develop and Coordinate plan to calibrate each spillway gate. Perform spillway gate calibration. Verify that corrections for each spillway gate opening account for discrepancy in total river flow between The Dalles and Bonneville. Develop communication plan for the region

Bonneville Gate Openings in Dogs and Feet Source of information is 1967 rating curve analysis. For Your Information