Measurement and Payment

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

Field Orders on Construction Contracts Guidance Document CLC-8 May 13, 2013.
ISTISNA’.
Contract CloseOut.
Presented by: Fouad Al-Malazi ID No.: Managing Construction Contracts By Robert D. Gilbreath Chapter 1 CONSTRUCTION CONTRACTS: Roles and Relationships.
CERTIFICATE 4 IN BUILDING BCGBC4004A. 18 week course First 10 weeks in classroom Following 8 in computer room 1.30pm pm (with 15 min break) Assessments.
Cargo Direct International
Funds administration, also referred to as funds control, funds disbursement, funds management, and escrow, is a method that sureties use to offset the.
Nabil dmaidi1 Miller Act H Enacted in 1935 H Federal Contracts over $25,000 H Contractor shall provide Bonds H Performance Bonds in the amount to protect.
4/13/2017 1:54 PM.
1 MOSS ADAMS LLP | 1 Case Studies in Contract Close Out Audits May 2014.
Setting Up The Project Project Manager Academy Section Five JOB LOOP 5.0Post Project Review 4.0Project Management 3.0Project Pricing 2.0Project Estimating.
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
OCR Payment Process Training 01/17/2012. Article 9 – Compensation and Payment General Conditions – Article 9 – 9.1 Preconstruction Stage Compensation.
Resolve Business Disputes and Select and Prepare a Construction Contract Lesson Seven Cert IV - M. S. Martin March 2012.
Marcy Mealy Procurement Specialist CDBG Program
Construction Operations Ch 15. Opening a Project Before Contractor is allowed on site it must –Make sure contractor has all required insurance –Obtain.
Work Breakdown Structure –Early compilation of significant work items w/ associated cost and schedule considerations –Overview of project –First look.
Project Close Out CTC-470.
Estimating CTC-415. Estimate Types Concept Detailed Definitive.
Subcontracting. Subcontractors % of work is subbed –Significant impact on costs and schedule –Want to develop a working relationship with good.
EM15 – Contractors COST MANAGEMENT
HOW TO WRITE A BUDGET…. The Importance of Your Budget Preparation of the budget is an important part of the proposal preparation process. Pre-Award and.
Procedural Requirements For Force Account Work on Federal and State Projects 2015 ACCA Conference Orange Beach, Alabama.
Completing the State Aid Payment Request (SAPR). Tips Each spring check on the State Aid Finance web page for the current version of the State Aid Pay.
Cost and Time Control. Project completed on time and on budget –Want to get done early –Lower costs –More profit.
Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed.
Mock State Aid Project County Highway Accountant’s Conference 2015.
1 Expenditure Documentation Review. 2 The Purpose of the Expenditure Documentation Review Beginning with Fiscal Year , the Office of Family Planning.
Construction Materials and Workmanship. All workmanship, materials, equipment, and articles incorporated into the work are to be of the best available.
TYPES OF CONTRACTS.
ARC 807: Professional Practice and Procedure Department of Architecture, Federal University of Technology, Akure, Nigeria ARC 807: Professional Practice.
Chapter 15 Payments. Payments typically made monthly. Retainage typically withheld (5% - 10%) Project payment: –series of periodic payments –single final.
Financial Management Back to Table of Contents. Financial Management 2 Chapter 21 Financial Management Analyzing Your Finances Managing Your Finances.
CONSTRUCTION ADMINISTRATION Measurement and Payment Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
Estimates and Quotes Apply procedures to develop plans, estimates and quotes Objective 4.03 Remember key terms, abilities needed, and items included in.
Project Closeout Module #14 Prepared by Dr. Randy R. Rapp July 2005.
1 PS&E Plans, Specifications and Estimate. 2 Contract Letting Plans-Show what is being built Plans-Show what is being built Specification-Show how project.
Project Cash Flow.  In order to make a workable project plan, the resources needed for the project and their availability must be checked.  Money is.
Estimating CE-147 Week 2. Estimate Types Concept Detailed Definitive.
Measurement and Payment Module #5 Prepared by Dr. Randy R. Rapp July 2005.
CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-Anazi CEM 520 February 27,1999.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
CASUALTY LOSS RESERVE SEMINAR SESSION 2 SEPTEMBER 10, 2001 CONTRACT SURETY CASE RESERVES STEPHEN J. TRECKER SENIOR VICE PRESIDENT XL SURETY PHILADELPHIA,
Service Quality Innovation Trust Safety The Samet Way “Managing the Company Cash Position” Accounts Payable (AP) should always be less than Accounts Receivable.
CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE.
Financial Management and Budgeting The Details. What Is a Budget? A useful tool for keeping track of funds. A useful tool for keeping track of funds.
1 PS&E Plans, Specifications and Estimate. 2 Contract Letting Plans-Show what is being built Plans-Show what is being built Specifications-Show how project.
Office of Procurement Services.  Vendor Application Website: 
Measurement and Payment
TOPIC-7- PROJECT CASH FLOW
Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.
Subcontractors and Suppliers Procedures for Receipt of Payment.
Presented by: Brienne Berscheid Assistant Vice President & Construction Escrow Underwriter Construction Escrow Documentation Requirements.
HORTICULTURE II - LANDSCAPE Unit B Landscape Design.
COST PLUS. Reasons for Cost-Plus Can’t agree on a price Specialty work Notice of Changed Conditions.
- Special Education Needs (SEN) Network Administrative and Financial Aspects.
Heritage Trust Fund Grant Orientation Session. HTF Staff and Contact Information Katrina Ringler Grants Manager ext. 215
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
Discussion of the Differences Public Works Law and Bid Law
County Highway Accountant’s Conference 2015
Estimating Project Costs
CHAPTER FOURTEEN THE VOUCHER SYSTEM.
What Small and Emerging Contractors Need to Know Understanding Funds Administration © Copyright 2017 NASBP.
TOPIC-7- PROJECT CASH FLOW
Completing the State Aid Payment Request
TOPIC-7- PROJECT CASH FLOW
ARCH 435 PROJECT MANAGEMENT
C2 Follow the Capital Risks
Directed Change Constructive Change
Presentation transcript:

Measurement and Payment

Construction Progress Payments Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed (quantities) RPR reviews Approves (sends to owner) or disapproves (calls contractor) Contractor gets paid

Approval of Payment Requests RPR responsible for checking quantities and costs Quantity take off Inventory of equipment and materials on site but not used Field measure work completed or claimed Construction Cost Estimate of all completed work Audit of Invoices and costs Review of claims for extra work and completed change orders Check of retention amount Check method used for profit and overhead, material costs for estra work or change orders

Basis for Payment Amounts Accuracy of field measurements determined by contract type Lump sum contracts do not need accurate field measurements Cost plus or Unit price contracts need very accurate field measurements Pg 432

Schedule of Values v. Cost loaded CPM Schedule Unit Price Contracts Do not call for Cost Loaded CPM Schedule Conflicts with line items on unit price sheet Do not call for schedule of Values A breakdown of all line items is submitted w/ contractor’s bid and is binding throughout job

Lump Sum Contracts with Cost Loaded CPM Do not ask for Schedule of Values – cost loaded CPM is equal Request Cost loaded CPM be submitted before first pay period ends Lump Sum Contracts w/o Cost loaded CPM Do not ask for a cost loaded CPM schedule Do not ask for a bid breakdown Request a schedule of values before starting work on project

Evaluation of Contractor’s Payment Requests Contractor submits request for payment at a prearranged date each month for previous month’s work Lump sum contract – payment based on a fair estimate of work completed plus overhead and profit Unit Price Contracts – contractor gets paid based on quantity used – RPR must have accurate field measurements +/- 25 % is okay more or less allows for renegotiations by either party

Equipment And Materials delivered but not used Contractor brings stuff on site early May try to bill owner since stuff is on site Contractor only paid when stuff is used Includes materials used but not completed – pipe not paid for until covered and tested Unit price contracts are usually for installed in place materials – on site is not in place Can make exceptions for long lead items which arrive on site early

Force Account Daywork or for any type of cost plus payment In US associated with extra work and change orders May be used to pay contractor when it is difficult to provide adequate measurements or estimate cost of certain items of work Should be last choice when setting up items for payment

Force Account Change order is a must Force account payments not authorized for supers. Allowances for supers is in contractors O&P. Foremen working full time on item would be covered by account PM has authority to direct every aspect of force account work

PM and Contractor must agree on Labor Classification and approximate N of workers, wage rates, travel allowance, subsistence, are foremen included Equipment Types to be used including size, rating, capacity, which indicate that item can do work required, owned or leased, cost per hour for use Materials Cost and freight charges, purchased for project or from contractor’s stock

PM prepares lists of equipment and labor classifications actually used and corresponding rates Equipment list includes complete nomenclature of the equipment to establish rental rate from a Rental Rate Book Labor list includes labor classification and composite hourly rate (basic wage + added costs listed in DOT standard specs)

Payments for Extra Work and Change Orders Usually laid out in Contract Common is cost plus with a reasonable allowance for O&P State agencies may allow 15, 20, 24,33 % on labor and then 15% on equipment, 15% on materials 5% on primary subs (not subs subs)

RPR must evaluate all change orders and requests for payment of extra work RPR should consult PM or owner to determine the exact terms of the agreement that cover extra work RPR keeps daily record of extra work performed and materials used

Make it a fixed cost that is on every bid Mobilization Costs Initial expenditures contractor makes before any work towards progress payment Permits, insurance, bonds Equipment Tools and supplies to do work Field Office Make it a fixed cost that is on every bid Contractor cannot inflate

Make sure that all items allowed in the mobilization cost are listed Can then either Prorate mobilization based on % complete Or Lump sum when all complete Other items to include RPR Field Office & Utilities & Communications Pg 448

Mobilization Lump Sum Projects Unit Price Projects Mobilization terms must be in a separate technical section Lump sum for mobilization Unit Price Projects Part of Measurement and Payment section with a separate line item and an A/E determined cost

Partial Payment to Contractor Waiver of Lien Procedure After each progress payment GC, subs, suppliers all sign waivers of liens for that payment Owner knows subs and suppliers are paid Limits the amount of the lien to only what has not been paid

Total Cost Pricing of Change Orders Compares total cost to do work with bid cost to do work, owner pays difference Allowed when Nature of claim makes it v. difficult to establish an accurate price Contractor’s bid was realistic Contractor’s costs were realistic Contractor’s actual costs were realistic Contractor was not responsible for any of the increased cost

Forward pricing of Change orders GC and Owner establish a mutually agreed lump sum payment for work Contractor cannot be forced to forward price work Contractor needs to make sure price is right – they are stuck with it

Retainage 5 – 10% of contract price Gives owner $ to satisfy lien claims if GC does not pay Also is the profit Can do either a lump sum or it can be computed based on each months progress payments

Retainage given to GC 35 days after completion of work if all lien releases turned in All employees paid Approval of the performance insurance CO. GC gets all but the amount representing the value of uncompleted or substandard work or materials.

Liquidated Damages during construction Can have liquidated damages for missed milestones Throws other contractors behind Deduct from next progress payment

Interpreting the Contractor’s Bid Bidding Errors Mathematical errors (unit price x quantity) Adding up bid items Ask for values in words and numbers Words rule GC may or may not get released from bid

Unbalanced Bids Contractor raises prices on some items and lowers prices on others w/o changing total project cost Should be rejected if found

Why do unbalanced bids To discourage certain types of construction and encourage others that the Contractor is good at Contractor thinks A/E estimate is low can make unit price high and make extra profit Increase unit prices on first items of work to be completed => receive excessive early payments then default on the job Leaves Surety with too little $ to do job

Can build up working capital – eliminates squeeze due to 10% retention Detecting an Unbalanced Bid Usually an unbalanced bid indicates and A/E error in estimate Use a spreadsheet to compare bids to find wide swings in bid prices All contractor’s should be in the same price range if normal bid

Resolving an Unbalanced Bid Easiest way is to reject all bids (owner’s perogative) Take bids to A/E point out area where possible error exists in estimate Get a new estimate Rebid job

Measurement for Payment Certain measurements do not represent true pay quantities Pipeline paid for by amount shown on drawing Drawing shows horizontal distance not length of pipeline on grade Does not include pipe overlap (bell & spigot joint) Contractor must take this into account when bidding job RPR must know how to measure bid item

Rock and Earth Quantities Compacted earth takes up less area than earth in natural state (shrinkage) shrinkage depends on material and compaction methods Fine Sand 6%, Sand and Gravel 8%, Ordinary Clay 10%, Loam 12%, Surface Soil 15% Rock takes up more space when removed (swell) from ground

Truckloads of loose material RPR and contractor should agree on a method of measuring material and use it throughout project Truckloads of loose material Water content can change weight of load 10% WC = 500lbs extra / 10 ton load Pay for materials in place as calculated from dimensions shown on the plans Must be careful on a unit price bid to make sure contractor is not over excavating to use more material.

Paving Quantities Small differences in depth can make a huge difference in price 0.5” over a 12’ lane 1 mile long = 2200# Also need to make sure that asphalt is at temperature when spread

Measurement Guidelines for Unit Price Quantities Pipelines – depend on contract can be horizontal distance (drawings), measures along top of joined pipe Do not measure along side of pipe Curbs – top edge facing the street Channels – use same location in channel for each measurement Sewer Lines – measure edge of manhole to edge of manhole – manholes separate item

Fencing – horizontal or along top rail of fence Pavements – area but watch for underruns on pavement thickness Retaining walls – each wall is measured as a prism, where walls meet do not double count

Final Payment to Contractor After CO contractor can apply for final payment Contractor must pay all bills or other indebtedness Must submit receipts, releases, and waivers of liens Consent of Surety must be obtained Less retainage

When computing contractor’s last payment consider for deduction in addition to retainage Any liquidated damages Twice the value of all outstanding punch list items The value of any lien claims already on file Final payment should not be approved until after formal acceptance of the work by owner (Notice of Substantial completion)