Mark McKinnon NSF Mid-Project Review May 11-12, 2006 1 Budget, Schedule, Contingency Mark McKinnon Project Manager.

Slides:



Advertisements
Similar presentations
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
Advertisements

14-Jun-2004EVLA Software Design Review Transition Plan Bill Sahr 1 EVLA Hybrid Array & Transition Plan.
Mark McKinnon EVLA Advisory Committee Meeting May 8-9, Budget, Schedule, Contingency Mark McKinnon Project Manager.
Project Management.
DATA TRANSMISSION SYSTEM MIKE REVNELL. OUTLINE Top level specifications Basic architecture Fiber plant DTS module Digitizers Formatter Deformatter Transition.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
M. McKinnonEVLA Advisory Committee Meeting September 6-7, 2007 Progress on 2006 Committee Recommendations Mark McKinnon Project Manager.
1 National Radio Astronomy Observatory EVLA Status -- Jim Ulvestad, for Mark McKinnon, Rick Perley, and the EVLA Team.
M. McKinnonEVLA Advisory Committee Meeting September 6-7, 2007 Project Management Mark McKinnon Project Manager.
Jim UlvestadEVLA Mid-Project Review May 11-12, EVLA Operations Jim Ulvestad Array Science Center Concept (Requirements) Staffing and Cost Plans.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
C. ChandlerEVLA Advisory Committee Meeting September 6-7, Scientific Commissioning Plan Claire Chandler.
Common PDR Problems ACES Presentation T. Gregory Guzik March 6, 2003.
EVLA Computing Overview Gareth Hunt EVLA Advisory Committee 2002 June
Systems Integration and Testing EVLA Advisory Committee Meeting, March 19-20, 2009 Jim Jackson Systems Engineer.
SJDEVLA Advisory Committee Meeting September 6-7, EVLA Production and Maintenance Steven Durand presenting for the E lectronics Division.
Mark McKinnon EVLA Advisory Committee Meeting May 8-9, Project Overview Mark McKinnon Project Manager.
1 SAGE Committee Meeting – December 19 & 20, 2008 National Radio Astronomy Observatory EVLA Goals, Progress, Status, and Projections Rick Perley Mark McKinnon.
Correlator Growth Path EVLA Advisory Committee Meeting, March 19-20, 2009 Michael P. Rupen Project Scientist for WIDAR.
Bill SahrEVLA Advisory Committee Meeting May 8-9, EVLA Monitor & Control.
Bill Sahr EVLA M&C EVLA Advisory Committee Meeting December 14-15, EVLA Monitor & Control.
Project Overview and Status EVLA Advisory Committee Meeting, March 19-20, 2009 Mark McKinnon EVLA Project Manager.
K. Y. LoEVLA Advisory Committee Meeting September 6-7, 2007 Charge to the Committee K. Y. Lo.
K band History Science workshop determined efficiency improvements necessary for K Band: weather, observing requests, mapping programs. Only enough funds.
SJDAdvisory Committee Dec Production & Maintenance Steven J. Durand December, 2004.
EVLA Transition to Science Operations: An Overview EVLA Advisory Committee Meeting, March 19-20, 2009 Bob Dickman AD, NM Operations.
Gustaaf van MoorselEVLA Advisory Committee Meeting May 8-9, 2006 EVLA Computing Software Overview.
Peter NapierEVLA Correlator CoDR Nov 2, EVLA Correlator CoDR P. Napier Overall EVLA Project Plan.
Rick PerleyEVLA Advisory Panel Meeting May , Scientific Impact of Descopes Rick Perley.
Long Term Transition Plan Gareth Hunt EVLA M&C PDR 2002 May 15.
P. NapierEVLA Advisory Committee Meeting September 8-9, EVLA Advisory Committee Project Overview P. Napier, Project Manager Management, Schedule,
P.NapierEVLA Advisory Comm, 14 Dec 2004 Project Overview Peter Napier, EVLA Project Manager Status 2003 Committee Response.
Introduction to EVLA Software Bryan Butler. 2006Dec05/06EVLA M&C Transition Software CDR2 EVLA Computing (Terse) History The original EVLA Phase I proposal.
Mark McKinnon NSF Mid-Project Review May 11-12, Baseline Project Definition Mark McKinnon Project Manager.
Mark McKinnon NSF Mid-Project Review May 11-12, EVLA Advisory Committee Reports Mark McKinnon Project Manager.
Rick PerleyNSF Mid-Project Review May 11-12, Scientific Impact of Descopes Rick Perley.
Mark McKinnon NSF Mid-Project Review May 11-12, EVLA Advisory Committee Reports Mark McKinnon Project Manager.
M. McKinnonEVLA Advisory Committee Meeting September 6-7, Project Overview Mark McKinnon Project Manager.
R. HaywardEVLA Feeds CDR – Project Budget & Schedule 17 Feb EVLA Feeds CDR Project Schedule & Budget.
Frazer OwenNSF EVLA Mid-Project Review May 11-12, Transition to EVLA
Rick PerleyEVLA Advisory Committee Meeting December 14 – 15, EVLA `Descoping’ Options Rick Perley.
EVLA Monitor & Control Software PDR Status. May 15, 2002EVLA Monitor & Control Software PDR Bill Sahr 2 Requirements, Schedule Requirements (High Level,
PCAP Close Out Feb 2, 2004 BNL. Overall  Good progress in all areas  Good accomplishments in DC-2 (and CTB) –Late, but good.
Bill SahrNSF Review May , EVLA Monitor & Control.
K-Band Focal Plane Array Steven White Program Manager.
P.NapierEVLA Advisory Committee, 10 June, EVLA ADVISORY COMMITTEE PROJECT OVERVIEW Scope Organization Schedule Budget, personnel.
Overall Data Processing Architecture EVLA timeline and priorities.
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
P.NapierEVLA Advisory Comm, 14 Dec 2004 Project Management Plan Peter Napier Project Organization Schedule Budget.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
EVLA Availability - or - When Can I Use It?
EVLA Project Peter Napier
EVLA Advisory Committee Meeting System Status
EVLA NSF Mid-Project Review System / Antenna Status
EVLA NSF Mid-Project Review System / Antenna Status
Terry Cotter LO/IF Group Leader
Budget, Schedule, Contingency
EVLA System PDR System Overview
EVLA M/C Software PDR, 14 May 2002
VLA to EVLA Transition Plan
EVLA Advisory Committee Meeting
EVLA Advisory Committee Meeting System Status
PDR Guidelines The purpose of the PDR of an EVLA Subsystem is principally to review 3 questions:   Are the top level performance requirements for the subsystem.
Gustaaf van Moorsel September 9, 2003
Mark McKinnon EVLA Project Manager
Background Information P.Napier
EVLA Operations Jim Ulvestad
EVLA Advisory Committee Meeting System Status
EVLA Construction Status
EVLA Advisory Panel Mtg. System Overview
Presentation transcript:

Mark McKinnon NSF Mid-Project Review May 11-12, Budget, Schedule, Contingency Mark McKinnon Project Manager

Mark McKinnon NSF Mid-Project Review May 11-12, Outline Schedule Milestones Budget Contingency Project Risks Risk Analysis Descope Options

Mark McKinnon NSF Mid-Project Review May 11-12, Completion Status of Budget and Schedule - 1 Definitions of terms used in plots and tables –Percent Spent: comparison between the money actually spent on a task and the value assigned to it in the original project plan –Percent Complete: comparison between the value of the work completed on a task to its total value in the original project plan

Mark McKinnon NSF Mid-Project Review May 11-12, Completion Status of Budget and Schedule - 2

Mark McKinnon NSF Mid-Project Review May 11-12, Milestone Completion

Mark McKinnon NSF Mid-Project Review May 11-12, WBS Level 2 Completion Status - 1 Project Management: 52.1% spent, 45.8% complete Systems Integration: 76.1% spent, 70.1% complete –Overspent in parts for bins and modules Civil Construction: 87.8% spent, 80.5% complete –Advance purchase of materials Antennas: 69.1% spent, 59.2% complete –Advance purchase of materials Front End Systems: 55.1% spent, 43.4% complete –Delay in receiver production

Mark McKinnon NSF Mid-Project Review May 11-12, WBS Level 2 Completion Status - 2 LO Systems: 75.5% spent, 75.1% complete Fiber Optics Systems: 64.4% spent, 58.8% complete IF Systems: 61.5% spent, 52.7% complete M&C System: 57.6% spent, 51.1% complete –Contingency applied to address overrun in contributed effort Data Management & Computing: 51.2% spent, 40.0% complete –Contingency applied to address overrun in contributed effort and to provide additional e2e staff –Staff needed to make progress

Mark McKinnon NSF Mid-Project Review May 11-12, Completed Milestones Examples (see list in information packet): Date –Install prototype system on test antennaQ –Start production assembly of antenna fiberQ –Start production of LO/IF outfittingQ –Start production of module interface board (MIB)Q –Start production of L-band feed hornsQ –Routine test observing software availableQ –Install 4P converter (T301) in test antennaQ –Start production of K-band receiver upgradeQ –Deliver EVLA antenna 14 to operationsQ –Start installation of shielded roomQ4 2005

Mark McKinnon NSF Mid-Project Review May 11-12, Remaining Milestones Examples: Date –DCAF software ready for testingQ –Test prototype of S-band feed hornQ –Deliver 7 antennas to operationsQ –Complete installation of shielded roomQ –Start production of L-band receiverQ –Complete delivery of UX converters (T303)Q –Start production of 3-bit, 4Gsps digitizerQ –Test prototype correlator on 4 EVLA antennasQ –Complete round trip phase module (L352)Q –M&C system ready for archiveQ2 2009

Mark McKinnon NSF Mid-Project Review May 11-12, Critical Path Tasks Examples: Date –TelCal software ready for testingQ –Complete prototype of L-band receiverQ –Conduct critical design review of M&C systemQ4 2006

Mark McKinnon NSF Mid-Project Review May 11-12, Maintaining Schedule -1 To maintain project schedule, we need to accelerate retrofits from the planned rate of 5 antennas per year to 5.5 Can we accelerate the antenna retrofit rate? –Retrofits are becoming an assembly line Major components stockpiled (e.g. cryo compressors, HVAC units, L-band feed horns, antenna platforms) Most electronics designs are mature –Staff continues to become more efficient in antenna retrofits –VLA antennas have been adequately maintained. Their reliability is excellent.

Mark McKinnon NSF Mid-Project Review May 11-12, Up until now, we have been pursuing the mechanical and electrical outfitting of EVLA antennas serially, with testing proceeding in parallel. Antenna Retrofit Sequence: Current

Mark McKinnon NSF Mid-Project Review May 11-12, In full production, mechanical outfitting of antennas can proceed in parallel with both electrical outfitting and testing. Antenna Retrofit Sequence: Future Project Plan

Mark McKinnon NSF Mid-Project Review May 11-12, Retrofit Duration

Mark McKinnon NSF Mid-Project Review May 11-12, Maintaining Schedule-2 Antenna rate of up to 6 per year is possible if : –Duration of mechanical overhaul is 2 months. –Duration of parallel activities for electrical outfitting and testing is 1 month each. … but need to monitor impact on reliability of VLA antennas. Possible issue for VLA users. Expect progress in software areas of the project because of additional e2 staffing resources and finalization of M&C design. Shift front end production emphasis to Ka-band while solving design issues with wideband OMT.

Mark McKinnon NSF Mid-Project Review May 11-12, Budget Funding = $93.8M (FY06) –NSF project funds$58.7M –NRAO contributed effort$16.3M –Canadian partner$17.0M (C$20M) –Mexican partner $1.8M

Mark McKinnon NSF Mid-Project Review May 11-12, Contingency Corr. Exclusive Corr. Inclusive Contingency, $ $2.8M Cost to Complete $32.1M $44.8M Contingency, % 8.7% 6.2% Detailed calculation of percent contingency depends upon whether or not project contingency is used to cover the cost to complete the correlator (corr.). Correlator project carries its own contingency

Mark McKinnon NSF Mid-Project Review May 11-12, External Risk Factors NRAO operating budget –Project dependence upon contributed effort. –Ability of operations budget to absorb personnel (e.g. e2e and CASA) moving from project to operations. Ability to support science staff. Plan developed. Strength of Canadian dollar Correlator funding profile Commodity prices –Aluminum, steel –Gold plating

Mark McKinnon NSF Mid-Project Review May 11-12, Retirement of Risk Bulk purchase of half transponders Bulk purchase of module interface boards M&C software support of transition mode observing, including successful implementation of reference pointing Eliminated spurious correlation with redesign of digitizer in DTS Solved timing problem between EVLA and VLA antennas Solved image rejection problem in 4P downconverter (T301) with new filter design Solved aliasing problem in baseband downconverter (T304) that limited sensitivity with new filter design Selected appropriate fire protection system for new correlator shielded room

Mark McKinnon NSF Mid-Project Review May 11-12, Project Risks Failure to stay on manpower curve$1.2M Correlator peripherals$0.8M Contribute to EPO program$0.5M Improve RFI protection$0.3M Additional module parts $0.3M Additional feed costs (S, X, Ku)$0.3M Spare correlator boards$0.2M Improve phase stability & RTP $0.2M Improve wideband OMT$0.2M Improve synthesizer (L302)$0.1M Correlator installation manpower$0.1M Redesign 3-bit, 4Gsps samplers $0.1M IF retrofits $0.1M Feed demoisture system $0.1M

Mark McKinnon NSF Mid-Project Review May 11-12, Risk Analysis Sum total risk = $4.5M Root sum square risk = $1.7M Contingency = $2.8M. Comparable to value of a year ago. Conclusion: –Still possible that project can be completed within budget and nearly on schedule. –Contingency coverage of risk is marginal, but no urgency now to implement descope options. Goal for FY06 is to refine contingency and risk analysis at finer level of detail (i.e. increase contingency and more accurately assess risk).

Mark McKinnon NSF Mid-Project Review May 11-12, Value of Possible Descope Options Eliminate receiver bands: –X (8-12 GHz) $1.0M2009 (date to decide on descope) –Ku (12-15 GHz) $1.3M2009 –S (2-4 GHz) $1.4M2007 –Ka (26-40 GHz)$1.2M2006 Purchase receiver components, but assemble/install as part of operations. Labor savings to project are: –X $0.2M –Ku $0.2M –S $0.4M –Ka $0.2M Eliminate solar observing mode $0.2M Transfer project-funded e2e effort (6 FTE years) to operations budget $0.7M

Mark McKinnon NSF Mid-Project Review May 11-12, Other Possible Descope Options Reduce number of antenna retrofits Shut down the VLA part of the array for some time period Halve the observing bandwidth