NIRANTHARA JYOTHI SCHEME Niranthara Jyothi Project is a prestigious scheme of Government of Karnataka, to provide 24 hrs 3 phase power supply to non-agricultural loads like domestic, commercial, water supply, street light, rural industries, milk dairies etc., in rural areas by segregating the agricultural loads, which is a boon to the rural economy. Objectives : This will enable BESCOM to give 24X7 supply to Non-Agricultural loads in Rural areas Reduction in transformer failure Increase in metered sales Reduction in technical losses Improved load management The plan of implementation and progress is shown separately. 1
STAGES OF IMPLEMENTATION Phase I 25 Lots, 261 feeders, 19 taluks. Project cost :Rs 355.85 cr. Expected completion : Dec-2013. Phase II 24 lots, 289 feeders, 23 taluks. Project cost :Rs 385.71 cr. Work Award issued for 6 Lots(86 feeders), DWA issued in Nov 2011, Jan-2012 & works are under progress. Work Award issued for 10 Lots (96 feeders) , DWA issued in Oct, Nov 2012 & Works are under progress. For the 5 Lots (57 feeders), LOI is issued , DWA issued in May 2013 Work under Progress For the 2 Lot ( 34 feeders), LOI is issued , DWA issued in June 2013 Work under Progress For the 1 Lot ( 14 feeders),DWA issued in Oct-2013 Work under Progress. Note: Out of Proposed 289 feeders,287 feeders work executed by PTK and 2 feeders are to be executed by Departmentally.
BANGALORE ELECTRICITY SUPPLY COMPANY LIMITED Physical Progress of Phase-I
No. of proposed NJ feeders Estimate cost (Rs. in Lakhs) As per DPR STATUS OF NIRANTHARA JYOTHI PHASE-I IN BESCOM Sl No Name of the District Division Name of the Taluk No. of villages covered No. of existing feeders No. of proposed NJ feeders Estimate cost (Rs. in Lakhs) As per DPR Progress Achieved Completion Date Feeders completed Feeders commisioned 1 Kolar Kolar (pilot project) Malur 272 20 10 18.67 Feb-14 2 Ramanagara Kanakapura 483 31 19 3184.78 18 3 Magadi 26 140.42 4 Chitadurga Chitradurga Hosadurga 208 13 1606.12 5 Davanagere DVG Channagiri 147 53 1667.33 6 Harihara Harapanahalli 113 1616.06 7 Chikkaballapura CB pura Bagepalli 17 12 1588.41 8 Tumkur Kunigal 414 23 16 2718.96 9 Madhugiri 259 1897.95 Gubbi 185 68 11 1824.75 Sira 289 2423.93 Honnali 103 29 1194.42 Hiriyur 237 2455.56 14 Jagalur 106 1218.54 15 Chintamani Siddlaghatta 268 1969.07 Bangalore Rural Yalahanka Hosakote 222 35 2469.73 Chandapura Anekal 86 1102.06 569 60 25 3179.20 Tiptur 224 1877.97 Devanahalli 1450.45 Total 4691 555 271 35604.38 270 269
BANGALORE ELECTRICITY SUPPLY COMPANY LIMITED Physical Progress of Phase-II
STATUS OF NIRANTHARA JYOTHI PHASE-II IN BESCOM Sl No Name of the District Name of the Division Name of the Taluk LOT NO. No. of villages covered No. of existing feeders No. of proposed NJ feeders Estimate cost (Rs. in Lakhs) As per DPR Progress Achieved Completion Date Feeders completed Feeders commisioned 1 Bangalore Rural Nelamangala Doddaballapura 240 26 17 1283.81 9 7 March-14 2 235 1828.84 3 Ramanagara Ramanagar 20 301.97 WUP _ 4 Channapatna 168 21 10 2014.55 5 Tumkur Madhugiri Koratagere 212 11 1513.75 8 6 Tiptur Turuvekere 207 22 14 2043.53 Gubbi (part)** 190 23 1867.91 Chikkanayakana halli(Lot-8) 179 15 1434.704 Chikkanayakana halli(Lot-7) 157 1255.366 Kolar KGF Bangarpet 356 33 16 2229.28 Mulbagal 233 12 1876.28 258 40 2292.5 13 Chintamani 300 2196.41 Srinivaspura 328 2372.22 Chikkaballapura 156 1392.63 Gowribidanur 318 31 19 2303.21 Gudibande 77 487.67 18 Chitradurga 183 24 1346.22 Holalkere 194 32 1761.23 Hiriyur Challakere 173 1807.49 Molakalmur 142 25 1480.78 Davangere Harihara Harihara** 58 705.05 Davanagere 129 42 1859.4 Tumkur part 3 (Additional NJY) 94 917 Total 4607 542 289 38571.80 110 65