1 3/12/2009 PHENIX WEEKLY PLANNING 3/12/2009 Don Lynch.

Slides:



Advertisements
Similar presentations
1 4/9/2009 PHENIX WEEKLY PLANNING 4/9/2009 Don Lynch.
Advertisements

1 12/3/2009 PHENIX WEEKLY PLANNING 12/3/2009 Don Lynch.
1 05/14/2009 PHENIX WEEKLY PLANNING 5/14/2009 Don Lynch.
1 2/11/2010 PHENIX WEEKLY PLANNING 2/11/2010 Don Lynch.
1 6/25/2009 PHENIX WEEKLY PLANNING 6/25/2009 Don Lynch.
1 4/30/2009 PHENIX WEEKLY PLANNING 4/30/2009 Don Lynch.
2/2/20121 PHENIX WEEKLY PLANNING 2/2/2012 Don Lynch.
1 3/19/2009 PHENIX WEEKLY PLANNING 3/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/15/2007 Don Lynch. 2/15/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress All.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
Technical Support /5/08 PHENIX WEEKLY PLANNING 6/5/2008 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 5/31/2007 Don Lynch. 5/31/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6 or 6/13/07?
1 7/02/2009 PHENIX WEEKLY PLANNING 7/2/2009 Don Lynch No Meeting this week due to July 4 th holidays. Slides have been updated. Next planning meeting will.
1 2/12/2009 PHENIX WEEKLY PLANNING 2/12/2009 Don Lynch.
1 1/22/2009 PHENIX WEEKLY PLANNING 1/22/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/21/2008 Don Lynch. 2/21/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /26/08 PHENIX WEEKLY PLANNING 10/2/2008 Don Lynch.
1 1/13/2011 PHENIX WEEKLY PLANNING 1/13/2011 Don Lynch No Meeting Today Due to snow shortened work week, today’s planning meeting has been cancelled. Slides.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
1 3/5/2009 PHENIX WEEKLY PLANNING 3/05/2009 Don Lynch.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
1 4/2/2009 PHENIX WEEKLY PLANNING 4/2/2009 Don Lynch.
PHENIX WEEKLY PLANNING 3/8/2007 Don Lynch. 3/8/207 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Continues…. All Up Commissioning In Progress.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 2/26/2009 PHENIX WEEKLY PLANNING 2/26/2009 Don Lynch.
1 4/16/2009 PHENIX WEEKLY PLANNING 4/16/2009 Don Lynch.
1 11/12/2009 PHENIX WEEKLY PLANNING 11/12/2009 Don Lynch.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /1/08 PHENIX WEEKLY PLANNING 5/1/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
Technical Support /8/08 PHENIX WEEKLY PLANNING 5/8/2008 Don Lynch.
1 05/07/2009 PHENIX WEEKLY PLANNING 5/07/2009 Don Lynch.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
1 12/30/2010 PHENIX WEEKLY PLANNING 12/30/2010 Don Lynch.
1/26/20121 PHENIX WEEKLY PLANNING 1/26/2012 Don Lynch.
1 10/15/2009 PHENIX WEEKLY PLANNING 10/15/2009 Don Lynch.
1 05/21/2009 PHENIX WEEKLY PLANNING 5/21/2009 Don Lynch.
PHENIX WEEKLY PLANNING 11/15/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going11/30.
5/12/11 1 PHENIX WEEKLY PLANNING 5/12/2011 Don Lynch.
Technical Support /19/08 PHENIX WEEKLY PLANNING 6/19/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
Technical Support /18/08 PHENIX WEEKLY PLANNING 12/30/2008 Don Lynch.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
1 12/17/2009 PHENIX WEEKLY PLANNING 12/31/2009 Don Lynch.
1 1/28/2010 PHENIX WEEKLY PLANNING 1/28/2010 Don Lynch.
1 12/17/2009 PHENIX WEEKLY PLANNING 12/17/2009 Don Lynch.
1 5/19/2011 PHENIX WEEKLY PLANNING 5/19/2011 Don Lynch.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
1 7/16/2009 PHENIX WEEKLY PLANNING 7/16/2009 Don Lynch.
3/7/20131 PHENIX WEEKLY PLANNING 3/7/2013 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
1 6/4/2009 PHENIX WEEKLY PLANNING 6/4/2009 Don Lynch.
1 7/9/2009 PHENIX WEEKLY PLANNING 7/9/2009 Don Lynch.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
1 8/20/2009 PHENIX WEEKLY PLANNING 8/20/2009 Don Lynch.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 2/4/2010 PHENIX WEEKLY PLANNING 2/4/2010 Don Lynch.
Presentation transcript:

1 3/12/2009 PHENIX WEEKLY PLANNING 3/12/2009 Don Lynch

2 3/12/2009 RPC Grounding Issues (IR & Tunnel Access) MuTRigger FEE Issues? HBD Repairs (open both carriages) MuID issues Tunnel access? CM lift table Other Work requests? Next Maintenance Access Day – March 18

3 3/12/2009 Run Support & Other Ongoing Work Run Technical Support (mech, elec., gas) As needed  always takes priority RPC Factory Support (continuing) (see slides later) Prep for 2009 Shutdown Design PC1 East maintenance support fixtures design 3/31, fabrication 5/31 MMS Scaffolding Design design Done, ordering/fabrication 5/1 RPC3 North installation Prep Installation plan (including inst’n site prep plan) 3/6 RPC Quarterly Review 3/12 & 3/13 Installation fixture design 4/3 Installation fixture fabrication 6/26 Upgrades Support New Beampipe supports (back logged) NCC prototype design support (on-going) VTX fabrication tooling design (on-going) VTX installation design (on-going) FVTX design/eng’g support (no support req’d yet) Maintenance & Overhead Tasks Procedure Review/Updates (ongoing) Rack Room, AH, Trailer, Mixing House, etc. (ongoing) ’09 Technical Support

4 3/12/2009 New DCM Racks in Place

5 3/12/2009 MMS Scaffolding Design

6 3/12/2009 PC1 East Repair Fixturing Design Repairs to be performed during ’09 Shutdown New Column Supports Under railway extensions New Railway extensions will allow DC to be pulled out ~ 3 feet more Access to PC1 is adequate to remove and replace module

7 3/12/2009 RPC Factory Support RPC Factory Change in Scope Remaining Action Items:  Review the mechanical design of the burn-in assembly and the dolly system to be used in moving the ½ octant units. Design In Progress, Review to follow  Update the RPC high voltage and gas procedures if necessary (Giannotti, Pisani Mar 13, 2009) In progress, Safety systems procedure revision is Done  Add individual output valves to the burn-in unit gas schematics (Pisani, Mar 13, 2009) In progress

8 3/12/2009 RPC Factory Support Tasks: Complete the Dark Current Test Stand (Done) Order materials for Burn-in Test Stand (Done) Complete design of Tilting Transport Table (Done Review needed) Order materials for the Tilting Transport Table (In Progress) Order additional shelf units for gap, module and RPCstructural component storage (Done) Design and order environmental control system for Burn-In Test Stand (3/20) Assemble gap & module storage with humidity control existing shelves (3/13), full complement of shelves (3/27) Assemble structural component storage existing shelves (2/27), full complement of shelves (3/13) Assemble tilting transport table 3/20 Assemble burn-in test stand (bike rack) 4/10 Extend gas, electric and safety systems to Burn-In Test Stand (4/10)

9 3/12/2009 RPC Factory Module and Gap Storage with humidity Control Burn-in test stand (bicycle rack) Tilt Table for Assembly and Handling ½-octants and later station one octants Detail parts storage for Module and ½ octant structural parts Dark Current Test Stand

10 3/12/2009 RPC Factory Dark Current Test Stand under construction Safety cushioning on edges

11 3/12/2009 RPC Factory Half-Octant Assembly Tilt Table Mechanical Analyses Completed and submitted for review Component parts are ready for assembly

12 3/12/2009 RPC Factory Burn In Test Station For Octant and Half Octant Burn-in Tests Mechanical Requirements: Slots for 20 detector units, max. 10 under test and 10 storage Each detector weighs ~ 750 lb Each slot to have 2 rollers Separation between rollers spaced to allow half octant to rest in slot with unit center of gravity mid way between rollers Rollers must be sufficiently close to catch unit before center of gravity passes first roller

13 3/12/2009 New Beampipe PHENIX SCD Brush- Wellman CAP Revised CAP rec’d last week; forwarded to CAD vacuum engineers for review/approval. Still waiting for quotes for transition and spool sections from CS.

14 3/12/2009 Gas Pad Upgrade & Ar Dewar Additional Pad area for storage of empty gas bottles New Liquid Argon Dewar to meet current and future demand General location as shown, footprint (size) TBD We are preparing a spec package for the additional pad req’ments. New dewar to be leased; supply company to provide requirements for dewar section of pad.

15 3/12/2009 Roof leak in utility bathroom at northwest corner behind tech offices. Roof leak over door between rack room and assembly hall. Trailer bathroom slop sink (for Custodians). Heat wrap tape for trailer bathroom toilet drains to preven freeze/clogging in winter. Improved Rack Room AC performance (This item has been addressed time and again but unsatisfactorily. Currently the AC fails periodically and is repaired only to fail again. On-condition maintenance is not adequate…an engineered solution is needed.) 2009 Building Maintenance Issues

16 3/12/2009 Shutdown ’09 Major tasks (expect 5 month shutdown): 2009 shutdown Begins April 10, or July 1, 2009 or July 15 or ????? End run, remove wall, MuID collars down, EC to AH (3 weeks) Install Station 1 South scaffolding (1 week) Install Station 2/3 scaffolding (2 weeks) PC1 East repair (4 weeks) Install stations 1, 2 and 3 south MuTrigger FEE’s (12 weeks) MuTr decapacitations: station 3 south (3 weeks) RPC Station 3 North (see next slide) Mechanical/Electrical Plumbing installation of (4) new DCM racks Add Ar Dewar and expand gas pad to add storage (12 weeks) Prep for future upgrades/existing equipment maintenance & Repair (as necessary) Shutdown ’09

17 3/12/2009 RPC3 North Installation Schedule Installation Concept FinalizedMar. 31 Half-Octant Brackets, Connecting Blocks, under detector translating support designMar. 31 Installation Fixturing and Tooling DesignApr. 30 Redesign crystal palace/IR Gas BarrierMay 29 End of Run 9 June 28 Fixturing/Tooling, Brackets/Block/support FabricationJune 30 Move Shielding/Remove Crystal PalaceJune 29-July31 Move cable trays and piping in gap 5June 29-July 31 Simulated (practice) installation with new fixturing/ toolingJuly 13-July 31 Install, level & survey support structure Aug. 3 - Aug 14 Half Octant Testing and Assembly Complete Aug. 17- Sep. 18 (1 st half Octant ready by Aug.17, 16 th by Sep.18) Mechanical Install Align & survey RPC3 N Aug 17 – Sep. 30 Install 3 elect. Racks, all cables & gas systemOct. 1 – Oct. 30 Commissioning Nov. 1 – Nov. 30 Install new crystal palace/IR Gas Barrier & ShieldingNov. 1 – Nov. 30 Start Run 10Dec. 1

18 3/12/2009 Safety, Security, etc. 1.Engineering Analyses reviews in progress: CM access ladder exception RPC Factory Burn-in Test Stand RPC Factory Tilting Transport Table MMS Scaffolding PC1 Repair Fixturing 2. BNL Lessons Learned – Inadequate fan guarding may lead to injury

19 3/12/2009 Where To Find PHENIX Engineering Info Links for the weekly planning meeting slides, archives of past meeting slides,long term planning, pictures, videos and other technical info can be found on the PHENIX Engineering web site: Happy St. Patrick’s Day 3/17 ! Parade info: Oldest – Boston Longest continually running: Montreal Largest New York (Savanna?) Largest (southern hemisphere) – Sydney Shortest – Hot Springs Arkansas or Boulder Colorado (one block) Newest – Glascow? (2007) St. Paddy’s parades are held in at least 47 of the states + DC + Virgin Islands, at least 27 countries including Argentina, Russia, China, Croatia, Serbia, Turkey, Dubai, Montserrat, South Korea, Japan, and many more