ELENA – Electron Cooler Vacuum design Benjamin Moles March 26 th 2015 on behalf of Electron Cooler team : Gerard Tranquille Jean Cenede Lars Soby Lars.

Slides:



Advertisements
Similar presentations
Tagger and Vacuum Chamber Assembly Procedure. Outline. Assembly procedure for tagger and vacuum chamber. Support stands. Alignment.
Advertisements

MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
KEK Update on the status of the electron cloud studies at KEKB Contents Brief review of our studies Updates Clearing electrode Groove structure SEY measurement.
HEL pre-design Diego Perini Superconducting solenoid Operation temperature: 4.2 K, current:about 250A, magnetic field: 5 Tesla Cooled by liquid.
Tagger and Vacuum Chamber Assembly Procedure. Preassembly of second bottom yokes and poleshoes. a) Install special support. b) Place the second bottom.
TAGGER MAGNET DESIGN Presented by Tim Whitlatch Hall D Tagger Magnet Design Review July 10,
D Walters Undulator System June 17, Undulator System Components Status Dean Walters.
ZQNA Electrostatic Quadrupoles for ELENA Transfer Lines 1.Conceptual design 2.Performance 3.Engineering details 4.Interfaces 5.Production planning D. Barna,
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
Electron Cooling Expected Performance & Construction.
30/05-03/06/2007 LCWS2007 and ILC2007, DESY Hamburg Germany Vacuum System Specifications What needs to be specified in Vacuum Specification for ICL Damping.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
DR Vacuum Component Overview April 25, 2012 Joe Conway.
LINAC 4 Project L4T/L4Z Design Status J.Humbert / B.Riffaud on behalf of EN-MME design team 1 st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud.
Vacuum system.
CLASSE prototype: mechanical concepts G. De Michele, EPFL-PSI-CERN on behalf of CERN team SLAC, 16 th April, 2012.
ELENA Support system 6/11/2014 Antti Kolehmainen on behalf of WP Support system
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
ELENA Vacuum System R. Kersevan, TE-VSC-IVM R. Kersevan, “ELENA Vacuum System”, - ELENA Project Review, Oct14-15, 2013, CERN.
Beam Line Layout – Cooling Section There seems to be two options for energy measurement: at the 180 dipole and/or in a diagnostic branch at the end of.
Low Energy RHIC e - Cooling Meeting Minutes – 11/19/14 1. Cooling Section Magnets and Power Supplies –Most of power supplies will be from ERL (R. Lambiase).
23 rd WP8 Bi-weekly meeting Lukasz Krzempek (TE-VSC-DLM) TAS-Q1 – vacuum equipment design.
ELENA Source Vacuum System, LNS R. Kersevan Integration and Installation Committe – 18 Sept 2014.
TCLDA Design status Collimation Upgrade Specification Meeting L. GENTINI.
Preliminary calculations for the vacuum system of ELENA R. Kersevan TE/VSC-IVM – 21/6/2012 The vacuum sectors, the position of vacuum pumps, flanges, and.
Booster and Collider SC magnets. Design & prototyping of UHV and cryostat systems for Booster and Collider A.Smirnov JINR, Dubna, Russia NICA Machine Advisory.
Internal H0/H- dump M. Delonca, C. Maglioni On behalf of EN/STI Thanks to: A. Christov, S. Mathot, C. Pasquino, A. Patapenka.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
Study Plan of Clearing Electrode at KEKB Y. Suetsugu, H. Fukuma (KEK), M. Pivi, W. Lanfa (SLAC) 2007/12/191 ILC DR Mini Work Shop (KEK) Dec.
Experience Fabricating the Storage Ring Vacuum Chambers for NSLSII
Stave C channel side closeout gluing jig S Yang WP4 monthly meeting at Liverpool University 26 th March 2014.
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
SKEKB Mini Work SKEKB Vacuum System – Arc Section – Contents Y.Suetsugu KEKB Vacuum Group 1.Beam Chambers 2.Pumps: Pump, Pressure,
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
Vacuum chamber fabrication Dates refer to end of fabrication, then 8 weeks are to be added for NEG coating, bake-out, acceptance tests, etc. EN-MME LNR.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review H.-C. Hseuh Vacuum Systems January 4, 2007 Project Overview.
L. Sermeus TE-ABT-FPSELENA IIC meeting 3 th April Review of ELENA Injection kicker Luc Sermeus on behalf of WP 2.8 (with informations from EN-MME)
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
RAMI Paul Aden. RAMI Analysis Reliability Visual inspection during each shutdown Service schedule for necessary components Majority of components to have.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
LWU Design Overview Paul Aden. BTM WP Scope To design, procurement and assemble; –2 Prototypes –3 Test Chambers –75 Linac Warm Units –52 Beam pipe modules.
LINAC 4 CCDTL Accelerating Structure SO SO Aluminum foil H = 0,3…0,5 mm Module of CCDTL Accelerating Structure.
SPS High Energy LSS5 Thermal contact & cooling aspects
ELENA installation progress F. Butin / ELENA collaboration.
Vacuum System P. Chiggiato TE-VSC
Assembly of the doorknob
ELENA – Vacuum chambers and vacuum activities
ELENA installation and commissioning status
The Budker Institute of Nuclear Physics
Configuration Management and Layout Database ELENA Project
ELENA – Electron Cooler
Layout Drawings and Mechanical Assembly Drawings
ELENA electron cooler and SEM grids status
TIDVG-4 TIDVG-4 Dump assembly, welding and installation Process sector BA1 February 2017 J. Humbert, (EN/MME) 06/02/2017 J. Humbert, EN-MME.
Requirements for the ELENA Electron Cooler
Parts exchange for HL-LHC AUP Q1&Q3
Magnetic gap calculation
Customer Presentation
Additional Upstream Coil Shielding
CRYOMODULE FINAL ASSEMBLY
Challenges and Deadlines for Production
Bunker Wall Design Wall ESS
Single Detector Design
Beam Finder Wire (BFW) Status
Work Unit AIK 11.2 CDR of the CDS-SL Mechanics
SNS PPU Cryomodule Space Frame
Electron Cooling in ELENA - observations and plans
AD Electron Cooler Consolidation Review
Presentation transcript:

ELENA – Electron Cooler Vacuum design Benjamin Moles March 26 th 2015 on behalf of Electron Cooler team : Gerard Tranquille Jean Cenede Lars Soby Lars Varming J. Germana Riddone Roberto Kersevan Marc Timmins Antti Juhani K. Alejandro Carlon Z. BE BI TE VSC EN MME BE OP

ELENA – Electron Cooler Location Concept overview Vacuum design Exchange with Mounting Conclusion Planning 26/03/2015Benjamin Moles EN/MME - EDS2

Location 26/03/2015Benjamin Moles EN/MME - EDS3 ELENA – Ring 4th Section

Location 26/03/2015Benjamin Moles EN/MME - EDS4 VAT 48 Sectionning valve LNR.MLNAF LNR.MCCAY LNR.MBHEK Electron Cooler

Concept overview 26/03/2015Benjamin Moles EN/MME - EDS5 Magnets Supporting system Gun & Collector Other magnets Vacuum system

Concept overview Magnets 26/03/2015Benjamin Moles EN/MME - EDS6 Main solenoïds

Concept overview Gun & Collector 26/03/2015Benjamin Moles EN/MME - EDS7 e- Gune- Collector Toroïd magnets

Concept overview Other magnets 26/03/2015Benjamin Moles EN/MME - EDS8 Orbital magnet (Kyoto style) ELENA Ring type Corrector magnet

Concept overview Supports 26/03/2015Benjamin Moles EN/MME - EDS9 ECooler supports LINAC4 Jacks (5t) Targets Supporting frame Jack Link bar

Vacuum design 26/03/2015Benjamin Moles EN/MME - EDS10

Vacuum design Interfaces 26/03/2015Benjamin Moles EN/MME - EDS11 Gun & Collector interfaces 2330 VAT 48 Valve flange Established interfaces with TESLA

Vacuum design Chambers & supports 26/03/2015Benjamin Moles EN/MME - EDS12 NEG Cartridge Standard solenoid chamber Toroïd chamber Drift solenoid chamber + 2x BPM Stripline Horizontal support 3 mm 2 mm During thermal expansion Top support x2

Vacuum design Vacuum overview 26/03/2015Benjamin Moles EN/MME - EDS13 v63xh85 Ø100

Vacuum design Top supports 26/03/2015Benjamin Moles EN/MME - EDS14 Upper collar + compression ring Upper collar + compression ring Solenoid top interfaces

Vacuum design Drift solenoid chambers 26/03/2015Benjamin Moles EN/MME - EDS15 Drift chamber BPM Stripline Longitudinal lock

Vacuum design Drift solenoid chambers 26/03/2015Benjamin Moles EN/MME - EDS16 Chamber support Clamping system Ø mm

Vacuum design Chamber support 26/03/2015Benjamin Moles EN/MME - EDS17 Left view Right view Compression point of the ring Flexible points with preload 50daN Adjustable fix points

26/03/2015Benjamin Moles EN/MME - EDS18 Ø mm thick Electrodes 85° aperture Electrodes fixation systems Electrical connexion Adjustable ceramic support with electric tightness Outgasing screws 2mm gap (x2) 4 mm gap Vacuum design BPM Strip Stripline BPM as in the Ring

26/03/2015Benjamin Moles EN/MME - EDS19 Elliptical chamber Hydroformed bellows Top fixation for electrodes Stripline interface Sectionning valve interface Feedthrough Electrical connexion Bended sheet metal Electrodes 316LN 3D forged blocks (x2) Top fixations Positionning pins Ø100 R height 85 width DN40 pumping chamber Ø110 hydroformed bellows 63x85 elliptic Ø100 Ø40 Ø100 Vacuum design Toroid chamber

Vacuum design Electrode fixations 26/03/2015Benjamin Moles EN/MME - EDS20 Ceramic spacer Circlips Welded studs Threaded ceramic part Top fixationsBot fixations

Vacuum design Toroid frame 26/03/2015Benjamin Moles EN/MME - EDS21

Vacuum design Instrumentations 26/03/2015Benjamin Moles EN/MME - EDS22 NexTorr NEG Pump D500 x2 Pirani / Penning Gauges on Sector valves x2

Exchange with 26/03/2015Benjamin Moles EN/MME - EDS23 Integration of TESLA models already began

Mounting 26/03/2015Benjamin Moles EN/MME - EDS24

Conclusion 26/03/2015Benjamin Moles EN/MME - EDS25 Vacuum pending points : NEG cartridge : strips ? bars ? To be detail : Gun & Collars Redo collector drawings then production Bottom effect calculation Final TESLA design & integration Material ordering Drawings & approval Final vacuum design

Benjamin Moles – EN/MME–ED March 26 th 2015 Thank you, for your attention. Any questions ?

ELENA – Electron Cooler Planning Marc Timmins EN MME

Delivery Kick-off meeting with TESLA Installation 1 month late on schedule (Will be caught up in production) Design (vacuum, instrumentation) Detailed integration Magnet designMagnet production Green light for production * * Design approval Assembly in the ELENA facility Vacuum system production Today