Value Stream Mapping the Delaware Air Quality Permitting Process

Slides:



Advertisements
Similar presentations
EDDIE TERRILL AIR QUALITY DIVISION DEPT. OF ENVIRONMENTAL QUALITY AUGUST 21, 2014 EPA’s 111(d) Clean Power Plan Rule: A DEQ Perspective.
Advertisements

CP Efficiency: The Path to Success Sarah Piziali, Construction Permit Section Supervisor.
NACAA-ECOS-EPA SIP Reform Workgroup Nancy Kruger Deputy Director NACAA
Waste Site Cleanup Advisory Committee Meeting June 23, 2011 MassDEP Reform Initiatives.
1. Globally Harmonized System of Classification and Labelling of Chemicals (GHS) Presentation to RCC Stakeholders - Webinar Session January 14 th, 2014.
Peter Dessaules, U.S. Department of Energy Brian Horn, Nuclear Regulatory Commission Programmatic Lessons Learned and Path Forward.
Dr. Shawn Mackey Associate Executive Director
Child Care Regulations for Licensure Presentation Kevin Savage Licensing Administrator March 31, 2015 Healthy Children and Youth, Strong Families, Diverse.
THE MANAGEMENT AND CONTROL OF QUALITY, 5e, © 2002 South-Western/Thomson Learning TM 1 Chapter 14 Building and Sustaining Total Quality Organizations.
1 Analytical Services, Inc. Huntsville, Alabama Jack Conway Vice President Systems Management CMMI Pilot Project Coordinator.
TIA Solid Waste Consultants, Inc.1 Presented by Miriam Zimms, Senior Consultant TIA Solid Waste Consultants, Inc. Tampa, Florida Pollution Prevention Conference.
The Basics of Lean and Clean Laura Pyzik 2007 Great Lakes/Great Plains P2 Conference March 13, 2007.
Preventing and Managing a Crisis. Overview This session will cover how to: Develop a crisis communications plan Prevent crises Prepare for crises Implement.
Competency Models Impact on Talent Management
Helping the people of Canada maintain and improve their health Aider les Canadiens et les Canadiennes à maintenir et à améliorer leur état de santé Path.
ISO 9001:2015 Revision overview - General users
Professional Standards 2009 Suzanne Scott, Ph.D., IDEC, ASID, Megan Scanlan, Director of Accreditation,
Strategic Planning Staff Development Week
Mantova 18/10/2002 "A Roadmap to New Product Development" Supporting Innovation Through The NPD Process and the Creation of Spin-off Companies.
Blue Skies Delaware; Clean Air for Life Delaware’s Air Permitting Seminar 2008 Paul E. Foster, P.E. – Program Manager Delaware Department of Natural Resources.
Frank Steitz Air Quality Permitting Program 10/12/2012
State Drinking Water Administrators’ Current Issues NARUC Committee on Water Jim Taft, Executive Director Association of State Drinking Water Administrators.
Maureen B. Higgins Assistant Director, Agency Support & Technical Assistance Office of Personnel Management December 8, 2010.
Colorado Springs Utilities Environmental Services Functional Assessment Presentation for the American Public Power Association’s 2001 Engineering & Operations.
1 Value Stream Mapping: Future State (Current Permitting Process) Joanna French October 26, 2006.
1 Small Community Environmental Compliance Assistance Project May 8, 2007 Arizona’s.
Lecture #9 Project Quality Management Quality Processes- Quality Assurance and Quality Control Ghazala Amin.
LOUGHBOROUGHCOLLEGE Business Support Self Assessment
Water Supply Planning Initiative State Water Commission November 22, 2004.
Steps in the Hazardous Waste Permit Reissuance Process December 10, 2014.
U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration USDOT – PHMSA HMEP Grants Major Audit Findings NASTTPO April 25,
Florida Turnaround Leaders Program Florida Turnaround Leaders Program Preparing Leaders for Florida’s Most Challenging Schools Florida Department of Education.
Lori Hanson Title V Operating Permit Supervisor (515)
Value Stream Mapping: New Application Forms Amy Mann October 26, 2006.
Flexible Air Permitting Innovation Done Right State-EPA Innovations Symposium Denver, CO January 24, 2006.
1 FAA Customer Service Initiative by Administrator for Regulation and Certification (AVR) - BRIEFING -
RIC 2009 Rulemaking Process: “NRC and Industry Perspectives on Improving Quality, Timeliness, and Consistency in 10 CFR 50.55a “A New Approach” Jacob Zimmerman.
From Policies to Programs to Practices Establishing the Green Infrastructure Eric Friedman Director of State Sustainability Mass. Executive Office of Env.
CEO Report Board Meeting LEO Meeting.
SIP Improvement: Current initiatives Anna Marie Wood Director Air Quality Policy Division Office of Air Quality Planning and Standards U.S. EPA WESTAR.
Genesee County Arts & Cultural Groups/Organizations Presented by Jennifer Acree - BEST Project, Flint, Michigan A presentation for.
Systems Analysis and Design in a Changing World, Thursday, Feb 1.
Introduction to the Continual Service Improvement Toolkit Welcome.
Nurse Staffing Optimization Project Reducing CSO Shift Requests 2007 Dec 2008 Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec 2009 Jan Feb Mar Apr June.
Revisions to Primacy State Underground Injection Control Programs Primacy State Implementation of the New Class V Rule.
Blue Skies Delaware; Clean Air for Life Value Stream Mapping: New Application Forms Amy Mann October 8, 2008.
The Oregon Business Plan Cluster Network Leadership Council Meeting June 11, 2006.
Lecture 10 More Innovation SE3821 Software Requirements and Specification Dr. Rob Hasker (based on slides by Dr. Brad Dennis)
SOLUTION What kind of plan do we need? How will we know if the work is on track to be done? How quickly can we get this done? How long will this work take.
Confidential 1 HIPAA Compliance at Blue Cross Blue Shield of Minnesota: A Case Study Tim Wittenburg Director of Corporate Architecture & Data Management.
1 Strategic Plan Review. 2 Process Planning and Evaluation Committee will be discussing 2 directions per meeting. October meeting- Finance and Governance.
FINAL CLEAN POWER PLAN Before the Virginia Energy Efficiency Council Virginia Department of Environmental Quality November 12, 2015.
IDEM Update March 9, 2011 Office of Pollution Prevention & Technical Assistance Rick Bossingham, Assistant Commissioner.
Discussion of Priority Activities for Next Eighteen Months Action Plans.
NIST MEP Strategic Planning MEP Advisory Board1. Board Engagement in Strategic Planning Review the charge from Pat Gallagher What we have heard so far:
NGA Center for Best Practices January 10, 2001 Charleston, South Carolina National Environmental Information Exchange Network Kim Nelson Pennsylvania Department.
Project Delivery Working Group FY2016 EFCOG Annual Meeting Robert P. Miklos Idaho National Laboratory Battelle Energy Alliance Working Group Chair June.
Implementing SMS in Civil Aviation: the Canadian Perspective
A Step by step guidance for permitting and inspection
Transformation Project Overview
U.S. EPA Chesapeake Bay Program Office June 1, 2012
TM Workgroup for Electronic Data Interchange.
TM Workgroup for Electronic Data Interchange.
Department of Environmental Quality
Convergence Bidding Working Group – 10/22/09
Transitioning into Prime Pilot Phase & Implementation Phase
Building and Sustaining Total Quality Organizations
Executive Order No. 23 Update Air & Waste Management Association Conference November 16, 2018 Presentation will focus on the latest policy development.
Revolutionize USACE Civil Works
System Safety Regulation
Presentation transcript:

Value Stream Mapping the Delaware Air Quality Permitting Process Bob Zimmerman State-EPA Symposium on Environmental Innovation and Results January 23-25, 2006

Delaware Value Stream Mapping Project Partners Delaware Economic Development Office Delaware Manufacturing Extension Partnership DNREC Office of the Secretary DAWM Air Quality Management General Motors Daimler Chrysler CIBA Specialty Chemicals ILC Dover, Inc. PPG Industries DuPont

Value Stream Mapping Process Objectives Improve the permitting process without weakening regulatory requirements. Capture the experience of those who have to meet the regulatory requirements. Process redesign activity would be transparent to the public and the regulated community.

Value Stream Mapping Process Why? Listening to voice of customer DEDO report on industry clusters to Governor - early 2005 DNREC asked to identify specific process - AQ construction permitting selected Stakeholders (Public/ Industry/ DNREC) Improve permitting process Reduce processing time/effort Create greater business certainty Optimize DNREC’s resources for other functions Improve environmental quality

Perspectives from Delaware’s Business Community Cost issues due to: Cumbersome and slow permitting process No allowance for “green companies” that are proactive and stay in compliance

Delaware Value Stream Mapping For public transparency we created a web page for the DNREC/ DEDO Value Stream Mapping project: http://www.dnrec.state.de.us/DNREC2000/VSM/Index.htm All materials are available on the web page

History DNREC / DEDO Value Stream Mapping Process June 05: Initial Scoping Meeting July 05: Planning Session Aug 05: 3 Day Training / Action Plan Sept 05: 30 Day – Progress/ Plan Review Oct 05: 60 Day – Progress/ Plan Review Nov 05: 90 Day – Progress/ Plan Review Jan ’06: 120 Day – Progress/ Plan Review

Mapping the Current State Created the goal for the session Defined what was in scope and out of scope Mapped the current state of the Air Quality Construction Permitting Process.

Goal for VSM Project Develop and implement an air permitting process that results in expeditious issuance of environmentally sound, operationally flexible and achievable permits in a timeframe not to exceed 90 days and ensure requirements are identified clearly prior to submittal reducing re-work in the process to 50%

In Scope Out of Scope • Interpretation of DNREC Rules, Policies, & Guidance Documents • Internal Organizational Structure • Internal Permit Process and Timing • Applicant Internal Process & Timing • Electronic Submittals • Application Content and Format • Permit and Technical Memo Format • Special Condition Content • Communication (Internal/External) Out of Scope • EPA Regulations • Interpretation of EPA Rules, Policies, and Guidance Documents • Modifying Existing DNREC Rules • Additional Resources • Permit Appeal Process • New Software/Computer Systems • Mandated Public Participation Requirements • Permits Involving Enforcement Action • Public Hearing Process/Officer

I know this is really small, I will provide handouts of this for each participant.

Mapping the Current State Lessons learned: Majority of process problems stem from the permit applications! First pass quality yield was < 1% Assuming perfect customer input, first pass quality yield was 18% Re-work was nearly 100%! Construction permits issued within 180 days

Mapping the Current State Identified opportunities for improvement called “Kaizen Bursts.” “Kaizen” are rapid improvement processes focused on eliminating waste, improving productivity, and achieving continual improvement. “Kaizen Bursts” were used to help create the Future State.

Again, I will pass out handouts for people to read

Creating the Future State Defined our future state – where we wanted to be in one year: Internal first pass quality yield - 80% Customer information quality - 80% Administrative completeness - 100% Technical completeness - 80% Re-work less than 50% Construction permit issued within 90 days

I will pass out handouts for people to read

Achieving Our Future State Identified and scheduled specific tasks to accomplish. These tasks included: create visual tracking boards; implement a First-In-First-Out system; create permitting checklists; seek applicant feedback; modify our applications to make them more user friendly; modify application review process; and collecting new performance metrics.

Visual Tracking Board

Project Highlights Surveyed applicants to discuss why they submitted incomplete applications and learned important information. Reduced our permitting backlog from 199 AQ construction permits on 8/24/2005 to 48 on 1/11/2006. Implemented a First-In-First-Out system. Now issuing AQ construction permits within 61 days of receiving a complete application I’ll update the backlog progress for this week before I send this to DEMEP.

What We Learned from Applicants Difficult to know which form to complete Difficult to know where and how to obtain information that is requested Difficult to know which questions to answer and which ones are not applicable Applicants would like help with engineering calculations Applicants would like to know why specific information is requested

Important Process Improvements Future State includes three important changes to the permitting process: Pre-Submittal Meeting Administratively Complete Gate Technically Complete Gate

DNREC Value Stream Mapping Air Permitting Process Cross Functional Communications Top Down Commitment PLUS: Employee Involvement Customer Focus and Communications First Time Quality Partnership Support Future State SEPTEMBER, OCTOBER & NOVEMBER 05’ Reduced Waste in: MINUS: Motion Waiting Processing Rework Lead time Current State Created a permitting process that is environmentally sound, operationally flexible and achievable.

Next Steps We are still working on some of the action items required to implement the process. We are seeking volunteers (especially our permittees) to participate in the permit application redesign. We are reviewing/revising the metrics for permit processing.

Schedule Feb 06 - Complete drafts of all VSM action items Mar-April 06 - Train regulated community on new processes and documentation May-June 06 – Debug new processes July 06 – complete full implementation of new processes

For more information: Robert J. Zimmerman Office of the Secretary, Director of External Affairs Robert.Zimmerman@state.de.us 302-739-9000 Ali Mirzakhalili Program Administrator, Air Quality Management Ali.Mirzakhalili@state.de.us 302-739-9400 Amy Mann Environmental Engineer III, AQM Amy.Mann@state.de.us 302-323-4542

Lessons Learned by Nebraska, Michigan and Delaware Worth the effort Carefully select the situation or process There is a lot more waste than you realize Eliminating waste doesn’t mean eliminating people Goal-setting is critical Communications (before, during and after) Active and visible management support Be prepared for resource issues Follow- thru essential to keep on track