1 New Orleans District Morganza to the Gulf 23 May 2008 Carl Anderson, Senior Project Manager, USACE.

Slides:



Advertisements
Similar presentations
US Army Corps of Engineers Budgeting Process
Advertisements

US Army Corps of Engineers BUILDING STRONG and Taking Care of People! Ecosystem Restoration Along the Los Angeles River: Creativity within Concrete Dan.
Restoring and protecting Louisiana’s coast January 18, 2011 CPRA Meeting David Peterson Asst. Attorney General and AG Designee to CPRA Civil Division Lands.
CPRA Board Meeting, Baton Rouge, LA May 15, 2013 Coastal Protection and Restoration Authority.
Storm Protection & Coastal Restoration: Moving in to the 21 st Century Denise J. Reed University of New Orleans Restore or Retreat March 2009.
Update on Southwest Louisiana Projects Office of Coastal Protection and Restoration.
Sector New Orleans NEW FINAL HURRICANE RNA RULE Regulated Navigation Area.
US Army Corps of Engineers Northwestern Division Northwestern Division 1 System Flood Control Review: Regional Agency Review Briefing Lonnie Mettler Northwestern.
Host: Falcolm E. Hull, Vice President/Technical Expert, ARCADIS, U.S. Inc. Attending: Cherie Coffman, Coastal Projection Project, TAMUG Bill Merrell, George.
The Coastal Wetlands Planning, Protection and Restoration Act Presentation for the National Science Teachers Association Meeting New Orleans, LA November.
A Coastal Barrier Protecting the Houston/Galveston Region from Hurricane Storm Surge Center for Texas Beaches and Shores Texas A& M University at Galveston.
“Closing” the Mississippi River Gulf Outlet (MRGO): Environmental and Economic Implications Coastal Wetland Planning, Preservation, and Restoration Act.
Compensatory Mitigation in Coastal Louisiana Keith Lovell, Administrator Office of Coastal Management Department of Natural Resources 10/03/121.
Coastal Protection and Restoration Authority Presentation to Coastal Financing Authority July 30, 2008.
TROPICAL STORM LEE September 1-6 After Action Report.
April, 2008 Office of Coastal Restoration & Management PROJECT UPDATE Office of Coastal Restoration & Management PROJECT UPDATE.
COMPREHENSIVE FLOODPLAIN MANAGEMENT : Promoting Wise Uses of Floodplains CA Department of Water Resources/ CIFMCG Workshop July 2006.
Coastal Texas Protection and Restoration Project
OCPR Performance During Hurricane/Flood Fights (Disasters Averted) (Disasters Averted) October 29, 2008 Jerome “Zee” Zeringue Governor’s Office Coastal.
Regional Flood Plain Management Council April 15, 2015 H-GAC December 2nd.
DRAFT CORPS OF ENGINEERS CONTRACTS: Louisiana Coastal Area, Mississippi River Gulf Outlet, and Lake Pontchartrain & Vicinity Presented to the Coastal Protection.
1 Technological Innovations and Future Vision of Technical Support Louisiana Coastal Protection and Restoration and Mississippi Coastal Improvements Program.
Integrated Ecosystem Restoration and Hurricane Protection: Louisiana’s Comprehensive Master Plan for a Sustainable Coast.
Community Resiliency, Morganza to the Gulf and. Community Resiliency Resiliency is frequently defined as the capacity of human and natural/physical systems.
1 U.S. ARMY CORPS OF ENGINEERS AND ST. JOHNS RIVER WATER MANAGEMENT DISTRICT Indian River Lagoon North Restoration Feasibility Study Public Meeting September.
Module 11 STEPS 4 & 5 Conduct Reconnaissance Study & Report Certification Civil Works Orientation Course - FY 11.
US Army Corps of Engineers BUILDING STRONG ® The Nature Conservancy’s Climate, Risk & Resilience 2013 Learning Exchange Col. Richard Hansen U.S. Army Corps.
Morganza to the Gulf of Mexico Project State & Local Views and Path Forward Jerome Zeringue CPRA.
Oil Spill Restoration Planning – NFWF Proposal No.1 Kyle Graham Deputy Director CPRA July 17, 2013 committed to our coast.
“Getting the Funding Right” Kim Koleos Juris Doctor, University of Florida.
World Association for Waterborne Transport Infrastructure (PIANC) and the International Environmental Commission Technical Seminar October 28, 2009 Westin.
NOAA Restoration Center Implementing the Gulf Regional Sediment Management Master Plan …responding to an ongoing emergency, improving responses to new.
Increase Atchafalaya Flow to Terrebonne Governor’s Advisory Commission Meeting 7 August 2013 committed to our coast.
SOUTHWEST COASTAL AND SOUTH CENTRAL PROJECTS – Update and Path Forward CPRA Meeting January 22, 2013 committed to our coast.
CPRA UNO Meeting August 13, urplus Funds 2008 $300 Million Surplus Funds Act 3 of the nd Extraordinary Legislative Session provides for:
Climate Change and Water Resources Planning Kim Shugar Department Director Intergovernmental Programs Kim Shugar Department Director Intergovernmental.
Coastal Restoration Updates September 10, 2007 Coastal Restoration Updates September 10, 2007 Louisiana Department of Natural Resources Louisiana Department.
Recreational Impacts of Coastal Restoration Projects CNREP Presentation Joseph Berlin May 28, 2010.
One Team: Relevant, Ready, Responsive, Reliable US Army Corps of Engineers 1 Coastal Protection and Restoration Advisory Committee 3 April 2006 D
05C112011B Template Master – Update Tracking Number and Date Information Here Update tracking number and date on this slide Template Master – Update Tracking.
Oil Spill Restoration Planning Part 2 (RESTORE Act, Criminal, NRDA, SEPs) Kyle Graham Deputy Director CPRA May 15, 2013 committed to our coast.
BUILDING STRONG ® Mississippi River Ship Channel Gulf to Baton Rouge, LA Propeller Club for Port of New Orleans 24 September 2015.
“There are only two kinds of levees, those that have failed and those that will fail.”
The Science and Policy of Louisiana Coastal Ecosystem Restoration.
Building Strong 1 1 MRGO Ecosystem Restoration Plan Feasibility Study Gregory Miller Senior Project Manager Corps of Engineers New Orleans District October.
US Army Corps of Engineers BUILDING STRONG ® Boise River Feasibility Study Ellen Berggren, PMP Outreach Coordinator/ Project Manager Idaho Governor’s Roadless.
Central & Southern Florida Project George Horne Deputy Executive Director Operations & Maintenance Resource Area.
Catharine Cyr Ransom Principal The Accord Group. Stafford Act Structured approach to disasters Partnership between local, state, Federal governments Authority.
Evaluation of Preliminary DFIRMs Phase I Findings Terrebonne Parish June 22, 2009.
Implementing the Master Plan Kyle Graham Deputy Executive Director CPRA June 20, 2012 committed to our coast.
1 Atchafalaya River and Bayous Chene, Boeuf, and Black, Louisiana Dredged Material Management Plan (DMMP) Kick off Meeting April 13, 2005 Project Manager.
Donaldsonville, LA to the Gulf of Mexico Feasibility Study.
August 19, 2015 Port Bienville Rail EIS Scoping Meeting Presented by: Rhea Vincent Mike McGuire.
1 Hydraulic and Hydrologic Considerations in Planning.
Donaldsonville, LA to the Gulf of Mexico Feasibility Study.
U.S. Section International Boundary and Water Commission Rio Grande and Tijuana River Flood Control Projects Programmatic EIS.
US Army Corps of Engineers BUILDING STRONG ® OVERVIEW OF THE CIVIL WORKS PROCESS Planning Principles & Procedures – FY 11.
Texas GLO & US Army Corps Join on Texas Upper Coast Storm Barrier Study.
1 Calcasieu River & Pass, Louisiana Dredged Material Management Plan (DMMP) Kick off Meeting February 2, 2005 Project Manager Mireya Laigast, Civil Engineer,
Climate Change Threat Sea-Level Rise 1. Potential Impacts from Sea-Level Rise How might our community be impacted by sea-level rise? 2.
Donaldsonville, LA to the Gulf of Mexico Feasibility Study.
Wetlands Workshop Presented by Em LeBlanc. Let’s go on a Field Trip!
NOAA Working In Partnership Marine Partnership-MIST Cluster
Louisiana’s Coastal Protection and Restoration Update
Continuing Authorities Program
Louisiana Coastal Area
Beneficial Use of Dredged Material
Fab-Five Projects New Orleans FY19-FY23
GOMESA and RESTORE Funding
Challenges and Opportunities in Addressing Climate Change
Presentation transcript:

1 New Orleans District Morganza to the Gulf 23 May 2008 Carl Anderson, Senior Project Manager, USACE

2 Morganza to the Gulf Purpose Reduce flood damages (10,000 homes flooded during Hurricane Rita, 3,000 severely damaged)Reduce flood damages (10,000 homes flooded during Hurricane Rita, 3,000 severely damaged) Reduce coastal wetlands lossReduce coastal wetlands loss Minimize adverse impacts on navigation and industryMinimize adverse impacts on navigation and industry Reduce flood damages (10,000 homes flooded during Hurricane Rita, 3,000 severely damaged)Reduce flood damages (10,000 homes flooded during Hurricane Rita, 3,000 severely damaged) Reduce coastal wetlands lossReduce coastal wetlands loss Minimize adverse impacts on navigation and industryMinimize adverse impacts on navigation and industry Hurricane Flood Damage

3 Morganza to the Gulf Authorized by Congress in WRDA 2007 Total Project Cost = $912M (Oct price levels) Cost-sharing 65%-35%Cost-sharing 65%-35% –LADOTD will be construction sponsor –TLCD will sponsor OMRRR

4 Morganza to the Gulf Project Features 64 Miles of Earthen Levee64 Miles of Earthen Levee 13 Sector Gate Structures for Flood Control13 Sector Gate Structures for Flood Control 13 Tidal Exchange Structures13 Tidal Exchange Structures Houma Navigation Canal Lock ComplexHouma Navigation Canal Lock Complex Mitigation for direct impacts would require creatingMitigation for direct impacts would require creating 1,352 acres of new marsh

5 Existing Hydrologic Barriers

6 System Wide Circulation Model

7 Larose GIWW Cocodrie B. Grand Caillou B. Lafourche GIWW Presquile Boudreaux B. Petit Caillou Lafourche Parish Lafourche Parish Terrebonne Parish Terrebonne Parish N N Bourg Ashland 56 Chauvin Dulac Morganza to the Gulf of Mexico Project Morganza to the Gulf of Mexico Project REACH A REACH B Sector Gates Houma Navigation Canal Lock and Sector Gate Houma Navigation Canal Lock and Sector Gate Work in Kind (WIK) Levees Recommended Alignment Montegut REACH E REACH F REACH H REACH G REACH I REACH K REACH L Houma REACH J-1 B. Terrebonne REACHJ-2REACHJ-2 REACHJ-3REACHJ-3 55

8

9 Proposed Houma Navigation Canal Lock Complex Proposed Houma Navigation Canal Lock Complex Proposed Floodgate Right-of-Way Boundary B. GRAND CAILLOU Proposed Bypass Channel Proposed Closure Proposed Flood Gate Provides flood control, salinity control and enhanced navigation opportunitiesProvides flood control, salinity control and enhanced navigation opportunities Currently in detailed design of the lock complex which consists of a 110’ x 800’ lock and 250’ floodgateCurrently in detailed design of the lock complex which consists of a 110’ x 800’ lock and 250’ floodgate Proposed HNC Lock Proposed Access Road

10 Louisiana Coastal Area The Multi-purpose operation of Houma Navigation Canal (HNC) Lock is listed as a near term critical restoration feature in the final programmatic EIS for Louisiana Coastal Area Ecosystem Restoration Study for Subprovince 3.The Multi-purpose operation of Houma Navigation Canal (HNC) Lock is listed as a near term critical restoration feature in the final programmatic EIS for Louisiana Coastal Area Ecosystem Restoration Study for Subprovince 3. A Record of Decision for this FPEIS was signed in January 2005 and was authorized in Water Resources Development Act of 2007.A Record of Decision for this FPEIS was signed in January 2005 and was authorized in Water Resources Development Act of 2007.

11 LaCPR Draft Technical Report Lists the two primary structural alternative strategies considered for this area as the Morganza to the Gulf alternatives which are variations on the currently proposed 100-year Morganza to the Gulf project Lists the two primary structural alternative strategies considered for this area as the Morganza to the Gulf alternatives which are variations on the currently proposed 100-year Morganza to the Gulf project Also includes a set of GIWW alternatives, which would provide a second line of defense further inland along the Gulf Intracoastal Waterway Also includes a set of GIWW alternatives, which would provide a second line of defense further inland along the Gulf Intracoastal Waterway

12 Summary of Benefits Flood ProtectionFlood Protection –100-yr level of protection to be provided –Safeguard approximately 150,000 residents Safe HarborSafe Harbor –System would reduce damages, transportation and storage costs and increase navigation opportunities

13 Summary of Benefits Ecosystem ProtectionEcosystem Protection –Reduce saltwater intrusion and the frequency of wetland flooding for 83,000 acres of existing wetlands –Potential for managing freshwater flow and improving rapidly deteriorating wetlands Water SupplyWater Supply –Reduce annual water treatment costs, equipment replacement and maintenance costs –Reduce the need for capital projects Dredging/expansion of current reservoir or purchasing purification systemsDredging/expansion of current reservoir or purchasing purification systems

14 Current Efforts Hydraulic ModelingHydraulic Modeling –System wide analysis –Storm surge and wave modeling DesignDesign –HNC Lock Complex & adjacent features (50% design by summer 2008)

15 Current Efforts Revised Programmatic Environmental Impact Statement (RPEIS)Revised Programmatic Environmental Impact Statement (RPEIS) – Includes lock as constructible feature – Completion expected in summer 2009 Post Authorization Change Report (PAC)Post Authorization Change Report (PAC) –Completion expected in summer 2009

16 Work by Sponsor Construction of Levee Reach J-1Construction of Levee Reach J-1 Design of Levee Reaches J-2, H-2, H-3, & Point aux ChenesDesign of Levee Reaches J-2, H-2, H-3, & Point aux Chenes Design of access road for lockDesign of access road for lock Coordinating with federal and state agenciesCoordinating with federal and state agencies

17 Project Web Page /prj/mtog/