2007.10.11 BDS 11 Vacuum System for BDS [Completeness of RDR] Y. Suetsugu J. Noonan and P. Michelato Design principle Basic design Cost estimation.

Slides:



Advertisements
Similar presentations
KEK Update on the status of the electron cloud studies at KEKB Contents Brief review of our studies Updates Clearing electrode Groove structure SEY measurement.
Advertisements

February 17-18, 2010 R&D ERL David Pate R&D ERL Photocathode Deposition and Transport System David Pate February 17-18, 2010 Photocathode Deposition and.
Upgrade Plan of KEKB Vacuum system Pre-kickoff KEK1 Y. Suetsugu KEKB Vacuum Group Contents Challenges for vacuum system Designs for.
Study of a Clearing Electrode at KEKB - First beam test - Y. Suetsugu, H. Fukuma (KEK), M. Pivi, W. Lanfa (SLAC) 2008/3/3-61TLC08 Sendai.
R&D Plan on Clearing Electrode using the KEKB LER Y. Suetsugu and H. Fukuma, KEKB M. Pivi and L. Wang, SLAC at KEK.
11-13/10/2007 ILC BDS Kick-Off Meeting, SLAC, US 1 BDS Vacuum System Dr. Oleg B. Malyshev ASTeC Daresbury Laboratory.
Progress and Plan for Superconducting RF Cavity RF Group.
NLC Beam Delivery Area Engineering: Vacuum System Cost Model Presentation by Leif Eriksson, 02/09/99.
MICE Collaboration Meeting March 29 - April 1, CERN MICE alignment, tolerances and supports Tuesday March 30 Room Edgar Black/IIT March17-
IR2 and IR4 Summary PEP-II meeting Jan. 23, 2006 M. Sullivan.
Vacuum Pressures at IR Contents Y.Suetsugu KEKB Vac. Group 1.Outline of Vacuum System at IR 2.Behavior of Pressures 3.Remedies for Heating of Vacuum Components.
Vacuum, Surfaces & Coatings Group Technology Department Vacuum tests for CLIC module prototypes 6 November 2013 C. Garion2 Outline: Reminder: specification.
Superconducting Large Bore Sextupole for ILC
KAGRA Vacuum System Items of vacuum sub-group 1 1. Overview VAC (YS) Required Pressure “uhv (ultra-high-vacuum)” in the order of Pa, or lower.
Vacuum system in the main Linacs C. Garion CERN/TE/VSC CLIC09 workshop, October.
John Amann – ILC Mechanical Engineering 11/13/06
30/05-03/06/2007 LCWS2007 and ILC2007, DESY Hamburg Germany Vacuum System Specifications What needs to be specified in Vacuum Specification for ICL Damping.
1 Tetsuhiko Yorita JASRI/SPring-8 Acc. Div. SPring-8 Vacuum System Contents - Outline of Vacuum system - Pressure behavior - Some topics.
Status of vacuum & interconnections of the CLIC main linac modules C. Garion TE/VSC TBMWG, 9 th November 2009.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
Date Event Global Design Effort 1 Technical System Review John Noonan, ANL Yusuke Suetsugu,KEK Paolo Michelato, INFN Milano.
Vacuum Fundamentals 1 atmosphere = 760 mm Hg = kPa 1 torr = 1 mm Hg vacuum range pressure range low 760 ~ 25 torr medium 25~ high ~ 10.
Vacuum Workshop on Vacuum Systems for Synchrotron Light Sources, Barcelona, Installation and vacuum conditioning, 12 th and 13 th September 2005 L. Schulz.
SR Vacuum Systems and Front Ends
NSLS-II ASAC Review, 10/9-11/06 H-C. Hseuh,…, SR Vacuum Systems Storage Ring Vacuum Systems H-C. Hseuh, C. Foerster, J. Hu, G. Mahler, S. Pjerov, S. Sharma,
Vacuum system.
Vacuum Fundamentals 1 atmosphere = 760 mm Hg = kPa 1 torr = 1 mm Hg vacuum range pressure range low 760 ~ 25 torr medium 25~ high ~ 10.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
LCLS-II cryomodule alignment. 2 Wednesday meeting, 6/17/2015 Topics Alignment of Components inside the CM Tunnel Network Tolerances LCLS-II cryomodule.
Summary of Working Group II – Chamber Coating and Treatment Participants: Michel ChanelCERN Ping HeBNL Dick Hseuh BNL Roberto KersevanESRF Yulin LiCornell.
SuperKEKB Vacuum System - for the positron ring - Y. Suetsugu KEKB Vacuum Group Outline Design and production status of key components Beam pipes for arc.
NLC - The Next Linear Collider Project NLC Beam Delivery Lehman Review, May 1999 Vacuum System Cost Model Presentation by Leif Eriksson.
2009/1/16-18 ILD09 Seoul 1 Notes for ILD Beam Pipe (Technical Aspect) Y. Suetsugu, KEK Parasitic loss Vacuum pressure profile Some comments for beam pipe.
5 K Shield Study of STF Cryomodule Norihito Ohuchi, Norio Higashi KEK Xu QingJin IHEP 2008/3/3-61Sendai-GDE-Meeting.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
56 MHz SRF Cavity Thermal Analysis and Vacuum Chamber Strength C. Pai
Study Plan of Clearing Electrode at KEKB Y. Suetsugu, H. Fukuma (KEK), M. Pivi, W. Lanfa (SLAC) 2007/12/191 ILC DR Mini Work Shop (KEK) Dec.
Date 2007/Oct./25 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Report N. Ohuchi KEK 1.Cryomodule & Cryogenics KOM 2.GDE-meeting discussion I.Interface.
56 Mhz Vacuum Mike Mapes Mhz Insulating Vacuum TURBO PUMP WITH GATE VALVE AND GAUGE SET MOUNTED ON TANK SIMILAR TO RHIC CRYOSTAT & VALVE.
Solar Cells need a top side conductor to collect the current generated They also need a conductive film on the backside.
1 Vacuum chambers for LHC LSS TS Workshop 2004 Pedro Costa Pinto TS department, MME group Surface Characterization & Coatings Section.
CM28 - Vacuum System Update Matt Hills Mike Courthold 1.
SKEKB Mini Work SKEKB Vacuum System – Arc Section – Contents Y.Suetsugu KEKB Vacuum Group 1.Beam Chambers 2.Pumps: Pump, Pressure,
2007/09/17-21 SLAC IRENG07 1 A Basic Design of IR Vacuum system Y. Suetsugu, KEK Possibility of a pumping system without in-situ baking at z < L*
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review H.-C. Hseuh Vacuum Systems January 4, 2007 Project Overview.
THIN FILMS FOR CLIC ELEMENTS Outline Motivation The role of MME-CCS DB and MB transfer lines Main beam Main beam quadrupoles Other issues conclusions CLIC.
The integration of 420 m detectors into the LHC
RF power couplers vacuum issues J.M. Jimenez Vacuum, Surfaces and Coatings Group (TE-VSC)
Overall Layout 1 IP2 64 m LEReC-I (1.6-2MeV): Gun to dump SRF gun used as a booster cavity Booster Cavity and Gun move (next slide)
E-cloud Remedies and PS2 vacuum design J.M. Jimenez AT Department – Vacuum Group CARE-HHH-APD BEAM’07 Thursday 04 October Session 2: PS2 E-cloud.
AT-VAC SPC Nicolaas KOS Beam Screens for Inner Triplet Magnets LHC Upgrade Phase 1 Nicolaas KOS  LHC Upgrade phase 1  Inner triplet BS Requirements.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Vacuum Technology and Components for Cryogenics
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
LHC Beampipes Ray Veness / AT-VAC FP XII 08Beam Vacuum- R.Veness.
2008/12/10 INFN R&D on Low Impedance Beam Chamber and Components Y. Suetsugu, for KEKB Vacuum Group Contents Introduction Beam Chamber Components Connection.
24 September 2012 Immanuel Gfall (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
2007/09/17 SLAC IRENG07 1 Comment on IR Vacuum system Y. Suetsugu Pumping System without in-situ baking at z < L*
Vacuum System P. Chiggiato TE-VSC
Vertical Electropolishing at Marui & KEK
RTML Vacuum System RDR Summary FermiLab October 24, 2007
Preliminary Y-chamber specifications – First draft
CEPC Vacuum System Dong Haiyi 2017/11/5.
Challenges for FCC-ee MDI mechanical design
Thermal Outgassing Rate for Various Beam Line Materials
XFEL Collimation and Beam Switchyard Vacuum Issues
Discussion on the TDI impedance specifications
CEPC Vacuum Systems Design Consideration
Presentation transcript:

BDS 11 Vacuum System for BDS [Completeness of RDR] Y. Suetsugu J. Noonan and P. Michelato Design principle Basic design Cost estimation Issues to be discussed Summary

BDS 22 Design principle_1 General remarks –The vacuum system of RDR = The minimum design for cost estimation Cost per unit length –No detailed design exists, that is, the layout of pumps and the diameter of pipes, for example, were determined from a general consideration. Not responding to each component –Use standard UHV vacuum system

BDS 33 Design principle_2 Use standard UHV vacuum system_1 –Use standard materials: SS, Cu, Al-alloy, Cu-plated SS Depend on SR power, impedance requirement –Use standard pumps: Ion pumps, Ti-sublimation pumps, NEG (coating) TMP (Turbo-molecular pump), scroll pump for rough pumping Lumped pump system, basically

BDS 44 Design principle_3 Use standard UHV vacuum system_2 –Use standard monitors: Vacuum gauge = BA gauge (Hot cathode type) Mass Analyzer = Quadrupole Mass Spectrometer –Use standard components: Conflat UHV flange Manifolds compatible to Conflat flanges Bellows chamber with RF shield inside Gate valves with RF shield inside Fire-retardant, radiation resistant cables Etc.....

BDS 55 Basic design_1 Requirement for pressure (equivalent to N 2 /CO ): –5  Pa (50 nTorr), basically. –1  Pa (1 nTorr) for some region at upstream side of IP

BDS 66 Basic design_2 Beam duct –Duct material: Stain-less steel, basically Al-alloy or copper depending on SR power, and requirement from impedance – No in situ. baking, basically –Each duct for an element is considered as a stand- alone one, that is, the flanges are at both sides of a duct. –The maximum length of a beam duct is 10 m. –The minimum length is 1 m. –One magnet has one beam duct –Circular cross section –Cooling channel at one side, if necessary

BDS 77 Example_1 Ex. SS_  110mm duct

BDS 88 Example_2 Ex. SS_  40mm duct

BDS 99 Basic design_3 Aperture –Basically the apertures are the same to those of elements. The thickness of duct should follow the conditions as follows. [D: Diameter, t: thickness] D < 20 mm : t = 1 mm 20 mm  D < 60 mm : t = 2 mm 60 mm  D < 100 mm : t= 3 mm 100 mm  D : t = 4 mm Gap between a duct and cores of a magnet should be larger than 1 mm, to avoid interference. Beam pipes with a different aperture should be connected through a taper (~45  ).

BDS 10 Basic design_4 Connection flange –Connection flange is ICF conflat type. –The diameter of the flange, D f [mm], are: [D f : Flange diameter, D : duct diameter] D < 20 mm : D f = 34 mm (ICF 034) 20  D < 40 mm : D f = 70 mm (ICF 070) 40  D < 60 mm : D f = 114 mm (IFC 114) Etc..... –Stainless-steel –Copper gasket –RF bridge between flange, if necessary.

BDS 11 Basic design_5 Surface treatment –Basically, the inner surface of the duct should be cleaned by a detergent. –The acid cleaning should etch the surface by about 1 micron to remove contaminated layer. –Following the cleaning by pure water, the duct should be dried by dry nitrogen. –Individual ducts will be baked, and leak checked as part of the vacuum system quality control.

BDS 12 Basic design_6 Accuracy of manufacturing –Total length =  2 mm for 10 m. –Tilt between the end flanges is 0.5 degree. –Displacement of the duct against the axis in the horizontal and vertical plane is  2 mm. –Slant of the end flanges against the axis of the duct is 1 degree. –Displacement of the center of end flanges against the axis of the duct is less than  0.5 mm. –Width of a gap inside should be less than 0.5 mm. –Inside step should be less than 0.5 mm.

BDS 13 Basic design_7 Thermal gas desorption rate –Assumed to be 5  Pa m 3 s -1 m -2 ~ 5  Torr l s -1 cm -2 –Assumed thermal gas desorption rate was relatively large, because no baking in situ. was basically assumed. Photo-desorption Rate –Assumed to be 1  molecules photon -1. Some extent of vacuum scrubbing is expected. –Photon density was assumed to be 1  photons s -1 m -1 for the copper region, and 1  photons s -1 m -1 for other regions.

BDS 14 Basic design_8 Bellows chamber –With the same radius to adjacent beam pipes –With finger-type RF-shield

BDS 15 Basic design_9 Pumps –Pumps: Sputter ion pumps –Lumped pump scheme. –Effective pumping speed, S [m 3 s -1 ], are: [D: Diameter, S: Pumping speed] D < 20 mm : S = 0.02 m 3 s mm  D < 40 mm : S = 0.04 m 3 s mm  D < 60 mm : S = 0.06 m 3 s -1 Etc –Pumping speed includes the conductance of pumping slot. The actual pumping speed is the twice of the effective pumping speed.

BDS 16 Basic design_10 Rough pumping unit –Oil-free system –A rough pumping unit consists of: A turbo-molecular pump (S ~ 0.3 m 3 s -1 ) A scroll pump (S ~ 0.3 m3 min -1 ) A manifold (cross tube, for example), A Pirani-gauge, a cold cathode gauge, A leak valve, an electrical valve. Controllers of pumps and gauges. –Number of the rough pumping system is 20. –Removed during beam operation.

BDS 17 Basic design_11 Gate valves –All metal valves –Each region (EFF1 and so on) has at least one gate valve. –Valves are located every 250 m at minimum –Apertures of gate valves are : [D: Diameter, A: Aperture size] D < 60 mm : A = ICF mm  D < 100 mm : A = ICF mm  D < 150 mm : A = ICF203 Etc.....

BDS 18 Basic design_12 Gauge –Vacuum gauge: BA (hot cathode), QMA –The interval of gauge is 200 m. L-Angle Valve –All-metal L-angle valve is located every 50 m. –Rough pumping system is connected to the valve when the duct is evacuated from atmosphere.

BDS 19 Cost estimation_1 General remarks –Basically, obtained from major vacuum manufactures. –Discussed among TS leaders to find reasonable numbers in all regions. –Based on TS leaders’ experience so far. For example, in Asia, KEK B-factory (~1996). –The present cost estimation, however, is not yet well optimized. Diameter, lengths, etc.

BDS 20 Cost estimation_2 Included terms –Beam ducts –Bellows chambers (with finger-type RF-shielding) –Pumps (and controllers, Rough pumping unit) –Vacuum gauges (and controllers) –Gate valves (and controllers, with RF-shielding) –Manifolds (6 ports for rough pumping unit and gauges) –Gaskets, bolts, Supports (in average number) –Control cables between components and controllers –Interlock box per one gate valve –Baking heaters and thermal insulators: Option –Preparation before installation, such as assembling, pre-baking of beam pipe, testing, etc.

BDS 21 Cost estimation_3 Not included terms –All R&D –Spares –Man power for Installation, such as transportation, setting, connection, alignment, leak-checking, (baking) 4 km per year by 7 persons (1 specialist) –Power supply for baking: Option –Others (facilities) Electric power, Cooling water system, Storage area of vacuum components before installation, and so on

BDS 22 Cost estimation_4 Ambiguity in the present cost estimation –Overall specifications and requirements are clear. But, the detailed specification are not yet given. Required pressure Accuracy of manufacturing Surface treatment Gap between magnets, etc... –Design is not yet fixed. The manufacturer counted a risk factor. Beam pipe radius, lengths the structure of RF shielding at pumping port, etc...

BDS 23 Issues to be discussed_1 Required pressure should be updated, at first. Detailed design responding to each component and region –Aperture, lengths, etc... Simplification of structure –bellows chambers and gate valves R&D –Way to reduce gas desorption rate without baking Passivation, for example –Quick connection flange Optimization

BDS 24 Issues to be discussed_2 Optimization_ Ex. Choice of duct material –SS (stainless-steel), Al, or Cu. –In general, SS is cheaper and (may be) has higher reliability (for baking). –For ducts with a small radius the extrusion of Al pipe has an advantage in manufacturing. –SS pipe with Cu coating inside is also difficult to control the quality of the coating (and expensive). –Gas desorption rate of Al is comparative, if the surface is treated appropriately.

BDS 25 Issues to be discussed_3 Optimization_ Ex. Baking (in situ.) or not –Baking in situ. can much reduce the gas desorption rate, and can reduce the number of pumps. –Baking (up to 200 degrees), furthermore, make it possible to consider the NEG (Non Evaporable Getter) coating, which could improve the vacuum, especially for pipes with mall radius. –Uniform baking along the beam pipe is difficult due to the firm fixing of the cavity BPM at present. The tuning of BPM will be required after baking.

BDS 26 Summary The design principle and the basic design of the vacuum system for BDS in RDR phase were summarized. The design is sufficient for the rough cost estimation, but primitive for the actual system. Detailed design and elaborative discussion should be required for ED phase. –Design responding each component and region –Simplification of structures –Optimization of system