Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
LHC Status Sat Morning 18-June Bernhard Holzer, Gianluigi Arduini et al Tentative Planning: Luminosity 1092 x 1092 Access: installing low pass filter at.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
Nominal intensity bunches ● First ramp with nominal intensity bunches suffered from an instability appearing around 1.8 TeV. ● Nominal intensity bunches.
LHC 8:30 meetingEBH 11 Thursday 24 November 2011.
RF observation from Saturday morning Observation of beam induced voltage/power following the two klystron trips: 03:18 3B1 just at end ramp, 1.26E14 p.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Monday :00 Injection for physics fill # :00 Stable beams fill #1816, luminosity ~1.2x1033 cm-2s-1 11:08 Beams dumped. QPS trigger on detector.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Monday 12 th November 04:50 Beam dump, trip of RF line 4B, integrated L ~120 pb-1. Access for RF. 07:00 Injecting. FBCT phasing. Line steering. 09:59 Beam.
LHC Fri 6 & Sat 7 Nov :00 End instabilities MD, dump to refresh air at dump TDE cavern 08:00 Access for vacuum team at the TDE starting 10:30 Access.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
Proposal to change bunch length during physics fills to assess beam induced heating after LS1 M. Barnes, P. Baudrenghien, A. Burov, S. Claudet, S. Jakobsen,
Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Injection issues overnight 10:50 Access  QPS & EPC  Vacuum leak SPS – magnet to be replaced Monday – cycling for FT and LHC only over the weekend 12:15.
:00 meetingEBH 1  6:39 beam dump by BLM 655ms RS on BLMEI.05L4.B2E10_MBRB (which is downstream of BSRT B2).  The losses increased during.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
Tuesday 3 rd October STABLE BEAMS until 12:25 when we switched to ADJUST for a EOF test for Tobias  dump B2 first and then B1.  Dump at EOF test because.
Monday – Morning L. Drosdal: Injection line TI8: IQC threshold for BPM H from 2mm to 2.5mm to avoid unnecessary latches due to variations.
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Machine Coordinators: G. Arduini, J. Wenninger
Friday 15th June 01:11 Injection.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Tuesday Fill lost #1855 at 7:28 due to the trip of RQX.R1. This was traced to a software bug in the FGC… The Class 51 (LHC_PC) FGC software has been upgraded.
Wed :55 Fill 2653 stable beams 1.40e11 ppb, cm-2s-1peak lumi, 11.6 pb-1 total lumi delivered. 09:31 Dumped by collimator interlock:
Last 24 hours RQ5.L1 RQ4.L1 RF trip Line4B LHC status.
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Saturday 12:00 Fill 1992 in stable beams.
Monday 6th August & night
Summary of Week 11: 14 – 21 March
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Wednesday 31 October: Morning
Friday 31st August & night
Sunday morning Recovering from 400 kV disturbance.
Friday :00 machine setup for luminosity run. Better b-to-b stability from injectors. 01:58 stable run with 228 bunches 11:00 luminosity leveling.
Finally.... We had to wait a long time.... We had many problems....
Friday Morning 7:30 injection for fill 2908
LHC Morning Meeting - G. Arduini
Summary Thursday h21: Stable beams fill #1303.
Sunday/Monday & :30 Stable beams. Fill #1851.
Monday 24 October hours of 25ns MD
Mon Access for switching temperature probe DFB L7.
LHC Morning Meeting - G. Arduini
IP8 aperture measurements (07:30-10:30)
Tue/Wed 12/ :00 Probe beam back again
Thursday – Morning Energy matching at injection with H CODs
Monday 6th 07:39 Dump fill #1854, RQ6.L2 tripped, followed by access
Saturday Wire scans at end of fill 1253 B1H : 4.2 B1V : 4.3 B2H : 5 B2V : 7.2 Beams dumped (after ~14h of collisions) Some issues during refill.
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Monday :15 fill 3523 dumped by BPMs IP6
Thu 04:00 Fill #2729 Stable Beams. Initial lumi 6.5e33 cm-2 s-1.
Fri :52 Stable beams fill #2536
Saturday 24 September 2011.
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Monday 27th August & night
Thu :00 Dumped beams, refill for Pb-Pb physics. No more protons in 2011… Some changes: Increase of flat top total voltage to 14 MV. Feed-forward.
Saturday 28th 08:17 Fill #1812: Stable beams, peak luminosity ~1.1x1033 cm-2s-1 19:00 Go to adjust for RF-checks; Record fill lumi of 31.7 pb-1 for CMS.
Saturday 26 November 2011.
Wednesday 8th (I) 09:22 Fill #1855. Beams dumped by Alice dipole trip Stable beams for 10.5 hours; int. lumi 31 pb-1 After investigation EPC could not.
Tuesday
Presentation transcript:

Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10 RF voltage reduced from 12 MV to 9 MV. 11:51 Opened TCLs to test for future retraction tests: OK 12:00 TCL tests finished. 12:08 Beams dumped by operator. Integrated lumi 216/0.20/211/25.1 pb-1. 13:10 Access for experiments, EPC and CV.  There is nothing like ‘A Quick Access’ 15:26 QPS trip of matching section R8, related to EPC intervention on RD2.R8 earlier. 18:00 Bad contact found, start pre-cycle. 18:54 Injecting probes. 19:50 Ramp started fill # :50 Beam dumped by LBDS at start of ramp, energy tracking MKD B2, generator L. 21:12 Injecting physics beam fill # :55 Stable beams, initial lumi’s 6.5e33 cm-2s-1. 03:32 Beam dumps two correctors tripped in 5 Problems refilling: RF crowbar (solved, not understood), PC faults IT.R5: access LHC 8:30 meeting 30/10/2012

Kept beam in because injection kicker temp. MKI.8C still hot  But prepared to temporarily increase temperature interlock after analysis of SoftStart data with ‘hot’ magnet.  Temporarily because temperature increase on this magnet not ‘normal’, likely due to HOMs. Tube damping ferrite getting very hot, about 180  C.  Temperature interlock on this magnet increased from 58.3 degrees to 60.5 degrees. LHC 8:30 meeting 30/10/ Tube temperature Yoke ferrite

End of fill – LHC RF Team Reduction of RF voltage on both beams in steps from 12 MV to 9 MV lead to bunch length increase by 100 ps. Then bunch length was decreasing slowly as before (5-6 ps/ hour). Small reduction of luminosity at the moment of changes was observed and then lifetime was restored to the previous value.  Beneficial effects was observed on the ALFA pots. Next fill:  Batch by batch blow up with new target value of 1.5ns (instead of 1.4ns)  We decrease voltage during ramp with correspondingly increased bunch length target during blow-up (10 MV and 1.36 ns) to keep the same longitudinal emittance. We will monitor...  Future: Voltage can be increased again during physics (slowly) to recover the luminosity geometrical factor if necessary.  Longer bunches can be beneficial not only for beam induced heating but for transverse stability. LHC 8:30 meeting 30/10/2012

The end of an 18 h fill Not a record – longest is 22.8 h ATLAS and CMS integrated lumi’s well over 200 pb-1 LHC 8:30 meeting 30/10/2012

Access & Problems Access for all experiments EPC (2,4,6) and CV (water pump) Vacuum pumps at P6 were switched on, but an intervention is needed to fix VRPA.25.4R6.B EPC RD2.R8 intervention followed by QPS problems of the complete matching section  Another access needed, bad contact found. First ramp beam lost at start of ramp due to LBDS tracking error on MKD generator L  PLC problem – will need two hour access with specialists  Temporarily reduced redundancy from 1oo4 to 1oo3 LHC 8:30 meeting 30/10/2012

Fill #3238 Not the best beams from the injectors, large spread in bunch intensity Stronger batch by batch longitudinal blow-up resulting in losses at warning level (32 %) on IP3 momentum collimators. Reduced RF voltages at flat-top Losses of 10 % on the 6 non-colliding bunches. Initial lumi’s rather low, 6.7e33 cm-2s-1 While in physics, observed smaller temperature rise in BSRT beam2, as well as MKI beam2. B. Salvant also reports less heating on Alfa. 03:32 Beam dumps two correctors tripped in 5. Int lumi 81 pb-1. LHC 8:30 meeting 30/10/2012

MKI heating MKI.8C heating less  But (peak) lumi was lower as well LHC 8:30 meeting 30/10/2012 tube yoke

Refill for fill #3239 RF crowbar ACSLine1B2 ACSLine4B2 ACSLine3B2 ACSLine2B2 Lost RQX.R5, RTQX1.R5 and RTQX2.R5; PC fault Access for EPC - ongoing LHC 8:30 meeting 30/10/2012

On the list Access  Vacuum VRPA.25.4R6.B Recurring problem: “Had to restart the SIS monitoring for VAC_VGPB.137.5L2.B_ACQ. “  LBDS energy tracking MKD B2, 2 hours. Operational development  ADT tests at injection, 1-2 hours Intervention on fiber optics Wednesday morning  Most likely no beam, may be access LHC 8:30 meeting 30/10/2012