1 E. Bong 1 XCS Final Instrument Design Review Engineering Status April 21, 2009 LUSI WBS 1.4 X-Ray Correlation Spectroscopy Final.

Slides:



Advertisements
Similar presentations
1 Paul Montanez, P.E. 1 CXI Final Instrument Design Review June 3, 2009 Coherent X-ray Imaging WBS 1.3 CXI Component Status,
Advertisements

Tom Fornek LUSI June 17, LUSI UPDATE – June, 2008.
Stefan Moeller XES FAC Review – April 16, 2006 X-Ray Endstation Systems (XES) Status Stefan Moeller.
Jose Chan and Kathleen Ratcliffe FAC Review- LTU/DUMP installation Status & 6/16/08 1 Linac Installation Status, Schedule.
1 David Saenz 1 Hutch Construction in FEH June 08, 2009 Hutch Construction in Far Experimental Hall David Saenz – Project Manager.
J. B. Hastings LUSI Overview LCLS FAC March 20, 2007 LUSI Overview J. B. Hastings January 2007 Lehman Review Response to Lehman Review.
John Arthur X-ray June 17, X-ray Overview XTOD current status XES current status Schedule to first experiments.
1 Stefan Moeller 1 AMO Instrument Schedule ARR AMO Instrument Schedule Stefan Moeller – XES Manager June 30, 2009.
Aymeric Robert XCS 11/12/2008 SLAC National Accelerator Laboratory 1 X -ray C orrelation S pectroscopy Instrument Aymeric.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
John Arthur Photon October 27, Photon Systems Overview John Arthur SLAC.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
John Arthur Photon April 20, 2006 Photon Systems Update John Arthur SLAC Photon Systems Manager.
Eliazar Ortiz LUSI Diagnostics & Common November 11-13, 2008 SLAC National Accelerator Laboratory 1 Diagnostics/Common Optics:
1 Michael Rowen 1 SXR Instrument FAC SXR Instrument Michael Rowen – Engineering Physicist June 9, 2009.
XCS Aymeric ROBERT 1 LUSI X-ray Correlation Spectroscopy Instrument Advanced Procurement Review : Large Angle Detector Mover.
David Saenz FAC November 11, 2008 SLAC National Accelerator Laboratory 1 Far Experimental Hutches David Saenz Project Manager.
David Fritz XPP June 17, The X-ray Pump-Probe Instrument Instrument Scientist: David Fritz Second Scientist:
1 T. Fornek 1 LUSI CXI FIDR June 3, 2009 Thomas Fornek Project Manager June 3, 2009 LUSI Coherent X-Ray Imaging Instrument Final.
1 T. Fornek 1 LUSI XCS FIDR June 17, 2009 Thomas Fornek Project Manager June 17, 2009 LUSI X-Ray Correlation Spectroscopy Instrument.
E. Michael Saleski PPS and April 20, 2006 LCLS Personnel Protection System and Beam Containment System E. Michael Saleski.
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
Stefan Moeller XES Plan for FAC Review - April 20, 2006 X-Ray Endstation Systems (XES) Status and Plan for FY06 Stefan Moeller.
David Pindroh Procurement Overview LUSI DOE Review 8/19/08 – 8/21/08 p.1 LCLS Ultrafast Science Instruments (LUSI) David Pindroh – LCLS Procurement Manager.
XCS Aymeric ROBERT 1 LUSI X-ray Correlation Spectroscopy Instrument Advanced Procurement Review : Large Offset Monochromator.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Michael P. Bromfield Construction Engineer NSLS II Conventional Facilities Advisory Committee.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.
M. Reichanadter LCLS Project November 2008 FAC Meeting Slac National Accelerator Laboratory Report to the LCLS.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
Felix B. Fernandez LUSI DOE Review August 20, 2008 PMCS Overview p. 1 LCLS Ultrafast Science Instruments (LUSI) Felix B. Fernandez.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
Spreaders & Recombiners Beam Transport Michael Bevins May 30, GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation.
Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 1 Project Management Cost and Schedule Nadine Kurita ANSI/EIA-748-A Standard.
Mike Scharfenstein LUSI DOE Review August 19, 2008 ES&H Overview p. 1 LCLS Ultrafast Science Instruments (LUSI) M. Scharfenstein.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
S. Boutet P. Montanez LUSI DOE Review August Coherent X-Ray Imaging (WBS 1.3) 1 LUSI Coherent.
Nadine Kurita - LUSI Chief Engineer
Project Management W. J. Foyt
2K CB FDR Overview:  Agenda, Charge, Review Process
LUSI X-ray Correlation Spectroscopy WBS 1.4
X-ray Pump-Probe Instrument
Far Experimental Hall Hutches Civil Construction
Development of LCLS Far Experimental Hall Hutches
Far Experimental Hall Hutches Civil Construction
Coherent X-ray Imaging WBS 1.3
X-ray Pump-Probe Instrument
Installation of Photon Beam Transport to FEH
Thomas Fornek Project Manager July 15, 2009
X-Ray Endstations Update
LUSI Controls and Data Systems W.B.S. 1.6
LUSI MANAGEMENT OVERVIEW
Project Management Issues John N. Galayda, SLAC April 24, 2002
LUSI WBS 1.2 X-ray Pump Probe Status Review
NEH - Status Stefan Moeller.
LCLS Personnel Protection System and Beam Containment System
X-ray Correlation Spectroscopy Instrument
LCLS Injector System Overview D. H
DOE Review of the LCLS Project October 2006
Conventional Facilities
CF Scope, Management & Organization
X-Ray Endstation Systems (XES) 2006 Schedule
LUSI Controls and Data Systems W.B.S. 1.6
Presentation transcript:

1 E. Bong 1 XCS Final Instrument Design Review Engineering Status April 21, 2009 LUSI WBS 1.4 X-Ray Correlation Spectroscopy Final Instrument Design Review Engineering Status Eric Bong April 21, 2009

2 E. Bong 2 XCS Final Instrument Design Review Engineering Status April 21, 2009 Outline WBS 1.4 Scope Early Science/CD-4 Deliverables Progress since PIDR Status Engineering/Design Status Cost & Schedule Performance Critical Path Risk Identification & Mitigation Safety Summary

3 E. Bong 3 XCS Final Instrument Design Review Engineering Status April 21, 2009 WBS 1.3 – Early Science/CD-4 Deliverables Early Finish – August 2011 Early Finish – January 2012 (B/L Early Finish – November 2012)

4 E. Bong 4 XCS Final Instrument Design Review Engineering Status April 21, 2009 Progress Since PIDR BCR - Reconfiguration of XCS Instrument Moved Large Offset Monochromator Addition of “Post Monochromator” to project scope Moved Split & Delay into alcove upstream of Hutch 4 Relocated diagnostics to characterize beam before and after the monochromators Eliminated long beam-line transport in XRT XRT Beam-Line Design Extensive modification of LLNL design required Negotiated redesign of XRT to minimize re-work Split redesign cost with LCLS Now far less rework required to install XCS components

5 E. Bong 5 XCS Final Instrument Design Review Engineering Status April 21, 2009 Progress Since CD-2 Translation of XCS onto CXI Line Supports Early Science Documentation for Long Lead Procurement PRDs, ESDs, SOWs, Diffractometer Large Angle Detector Mover Large Offset Monochromator Held Long Lead Procurement Review, April 23, 2009 Commercial alternative for diagnostic stopper Vendor indicates modification of existing stopper design to add B4C wafer on face is possible Savings of design and fabrication time Updates P3 to indicate change in acquisition strategy

6 E. Bong 6 XCS Final Instrument Design Review Engineering Status April 21, 2009 Progress Since CD-2 XCS Engineering/Design staff Added 1 Mech Engineer / Designer – February 2009 Added 2 Mech Engineer / Designers – May 2009 Preliminary Design Reviews (PDRs) Vacuum: XRT & Hutch4 Supports: XRT & Hutch 4 Granite Tables Large Angle Mover Vacuum Assembly PDRs complete Baseline vibration data obtained in the LCLS Far Experimental Hall Vertical/Horizontal PSD, 1-100Hz (Compliments P. Montanez, J. Turner)

7 E. Bong 7 XCS Final Instrument Design Review Engineering Status April 21, 2009 Engineering & Design Status Engineering & Design Staff Ted Osier, Michael Kosovsky, Henry Alvarez, Navtej Hundal, Eric Bong Large Offset Monochromator Post-Monochromator Split and Delay Area Hutch 4 Optics, Diffractometer Large Angle detector Mover X-Ray Transport Hall (XRT) XCS Instrument Scientist Aymeric Robert XCS Visiting Scientist Soo-Heyong Lee

8 E. Bong 8 XCS Final Instrument Design Review Engineering Status April 21, 2009 Engineering/Design Status Documentation CAD system model documentation hierarchy (CAD Drawing Tree/File Structure) released XRT& FEH H4 beamline layouts complete with all available models implemented & updated PRDs/ESDs/ICDs/Purchasing Specs – complete. Hutch Design Reviewed 30%, 60%, 90% & 100% A&E drawings FEH Hutch construction – June thru December 2009 (LCLS) APP and Risk Identification/Registry complete and up to date

9 E. Bong 9 XCS Final Instrument Design Review Engineering Status April 21, 2009 Engineering/Design Status XCS Optic & Support Tables (WBS 1.4.2) Hutch 4 Granite Support Tables (WBS ) Modification of XPP support table design Granite base with movable strong-back PDR 29 May 2009 Leveraging existing designs (when applicable) reduces overall engineering & design effort. Use of common parts reduces maintenance costs. Safety: Earthquake restraint of granite base, covered pinch points. Budget at Completion (BAC) ≈ $200k Stoppers (WBS ) Diagnostic stoppers not PPS. Changed plan from modification to PPS stopper design to Commercial Item. Worked with vendor on modification of an off- the shelf product to incorporate 10mm on face of stopper. Commercial stopper uses same controls as vacuum valves. Issued BCR to change P3. Budget at Completion (BAC) ≈ $187k

10 E. Bong 10 XCS Final Instrument Design Review Engineering Status April 21, 2009 Engineering/Design Status XCS Diffractometer (WBS ) Planed as SLAC assemble. Changed to build to spec, same as XPP. Processed BCR. PRD, ESD & Purchase Spec complete Procurement Review Held. Ready to release RFQ Safety: Earthquake restraint pinch points, interlock of automatic motion. Design reviews required at vendor. LUSI controls interface required. Budget at Completion (BAC) ≈ $685k XCS Large Angle Detector Mover (WBS ) Processed BCR to split effort between carriage motion and upper assemblies. Carriage motion build to spec. Vacuum, detector positioner and beam stop; SLAC design. PRD, ESD & Purchase Spec complete. Procurement Review Held. Requisition in purchasing. Safety: Earthquake restraint pinch points, interlock of automatic motion. Design reviews required at vendor for carriage. LUSI controls interface required. Budget at Completion (BAC) ≈ $856k

11 E. Bong 11 XCS Final Instrument Design Review Engineering Status April 21, 2009 Engineering/Design Status XCS Hutch Utilities (WBS 1.4.5) Hutch layout design complete. LCLS responsible for hutch construction. Crane installation moved from LUSI to LCLS XCS responsible scientist and engineer involved hutch 4 specification and design reviews. Tasks to be completed by XCS Raised flooring Storage cabinets, work benches and tool chests Utilities distribution Budget at Completion (BAC) ≈ $369k

12 E. Bong 12 XCS Final Instrument Design Review Engineering Status April 21, 2009 Engineering/Design Status XCS XRT Vacuum (WBS ) Quantity of drift tubes finalized. Vacuum component selection complete. Vacuum support design well advanced. Completed preliminary design report. Ready to purchase all vacuum equipment. Safety: Pressure vessel code requirements mitigated using burst disks. Budget at Completion (BAC) ≈ $363k XCS Hutch 4 Vacuum (WBS ) Designed to shift to CXI line. Vacuum component selection complete. Uses many XRT support designs. Completed preliminary design report. Ready to purchase all vacuum equipment. Safety: Pressure vessel code requirement mitigated using burst disks. Budget at Completion (BAC) ≈ $400k

13 E. Bong 13 XCS Final Instrument Design Review Engineering Status April 21, 2009 Engineering/Design Status XCS Installation (WBS 1.4.7) LUSI Installation Coordinator Obtain required installation permits. Conduct daily tailgate meeting w/ UTR (University Technical Representative). Conduit to engineering for field installation issues. Provide installation status for incorporation into LUSI schedule. XCS XRT Installation Phased with LCLS and CXI installations. Advanced schedule could combine all XCS XRT installation with CXI except monochromators. Budget at Completion (BAC) ≈ $351k XCS Hutch 4 Installation Early Science All components except XCS detector Install duplicate XPP detector to commission and early science Early Finish – June 2011 CD-4 XCS Detector Early Finish – January 2012 Budget at Completion (BAC) ≈ $613k

14 E. Bong 14 XCS Final Instrument Design Review Engineering Status April 21, 2009 Engineering/Design Status Large Offset Mono (WBS ) Planed as build to specification. Vendor build complete Option for SLAC to build crystal holder PRD, ESD & Purchase Spec complete. Procurement Review Held. Review requires revisions to PRD, ESD & Purchase Spec Safety: Earthquake restraint. Design reviews required at vendor for carriage. LUSI controls interface required. Budget at Completion (BAC) ≈ $1,778k Post Mono (WBS ) Fabrication of existing ANL design. ANL drawings have been requested. SLAC will review drawings prior to purchasing components. Safety: Earthquake restraint. LUSI controls interface required. Budget at Completion (BAC) ≈ $455k

15 E. Bong 15 XCS Final Instrument Design Review Engineering Status April 21, 2009 XCS Instrument Design Status Summary System/ComponentReviewBaselineAdvanced IntegrationFIDR8/5/096/30/ Hutch Granite TablePDR6/29/095/29/ Diagnostic StopperCOTS6/9/095/15/ DiffractometerLLPR4/21/094/23/ Large Angle Mover CarriageLLPR12/14/094/23/ Large Angle Mover VacuumPDR5/29/ Hutch SpecificationFDR2/28/ Hutch Utilities & EquipmentPDR10/2/ XCS XRT Vacuum DesignPDR3/4/095/19/ XCS H4 Vacuum DesignPDR3/2/09 5/19/ Large Offset MonochromatorLLPR6/5/094/23/ Chanel Cut MonochromatorPR8/31/09

16 E. Bong 16 XCS Final Instrument Design Review Engineering Status April 21, 2009 Cost and Schedule Performance (2) Cum data through Feb09 CPI = 1.08 = BCWP/ACWP SPI = 0.96 = BCWP/BCWS

17 E. Bong 17 XCS Final Instrument Design Review Engineering Status April 21, 2009 Cost Performance Report March Data April Data

18 E. Bong 18 XCS Final Instrument Design Review Engineering Status April 21, 2009 XCS Critical Path DCO Harmonic Rejection Mirror Preliminary Design Review DCO X-ray Focusing Lens and Harmonic Rejection Mirror Awards XCS Diagnostics Stopper Design Effort Removing budgetary constraints will move critical path to XCS long lead items Re-plan of stopper acquisition will move stopper off critical path

19 E. Bong 19 XCS Final Instrument Design Review Engineering Status April 21, 2009 XCS Look Ahead Six month “look-ahead” of XCS Instrument milestones ARRA advanced schedule Purchasing started on Diffractometer and Detector Mover Carriage. Large Offset Monochromator purchasing start requires revision of specifications dictated by procurement review. Non LLP item purchasing must wait for CD3 approval.

20 E. Bong 20 XCS Final Instrument Design Review Engineering Status April 21, 2009 Risk Identification & Mitigation Risk Identification/Registry complete and up to date as per “LCLS Risk Management Plan” PMD r4 15 risks identified at CD-2 for XCS WBS Risks for BNL Detector Schedule - late MOU Schedule - late design Schedule - late fabrication Schedule - late testing Technical – does not meet requirements 5 Risks each for for Large Angle Detector Mover & Diffractometer Schedule – Procurement Placement Schedule - late design Schedule - late fabrication Schedule - late testing Technical – does not meet requirements 2 risks identified at CD-2 for DCO Monochromator WBS Risks for Monochromator Schedule – Manufacturing Technical – Optical Stability

21 E. Bong 21 XCS Final Instrument Design Review Engineering Status April 21, 2009 Safety LUSI Hazard Analysis Report (PM ) complete Safety issues are considered at every stage of the design, fabrication and installation process Safety considerations (some examples) Ionizing Radiation Hutch walls will comply with SLAC Radiation Safety memo RP-RPG MEM-01 Hutch PPS Pressure/Vacuum Vessel Safety Compliant with 10CFR851 Seismic Safety Designs compliant with: Seismic Design Specification for Buildings, Structures, Equipment, and Systems, SLAC-I-720-0A24E-002-R002 Mechanical Interlocks for equipment protection Engineered solutions that prevent potential “pinch-points” with moving machinery Hoisting and Rigging Positioning of devices that require the use of the FEH H4 overhead crane shall be performed by only by qualified personnel with an approved lift plan.

22 E. Bong 22 XCS Final Instrument Design Review Engineering Status April 21, 2009 Summary XCS instrument configuration design is complete. All preliminary design reviews complete. XCS scope is stable following BCR to move monochromators. Acquisition strategy for stoppers and large angle detector has been integrated into the schedule. Long Lead Procurement Review for diffractometer, large angle detector mover and large offset monochromator has been completed. Purchasing of LLP items has begun. Releasing budgetary constraints moved critical path to long lead procurement items. Scheduled early CD3 spending authority advances schedule. ARRA funding re-baseline advances XCS schedule providing early science in August 2011.

23 E. Bong 23 XCS Final Instrument Design Review Engineering Status April 21, 2009

24 E. Bong 24 XCS Final Instrument Design Review Engineering Status April 21, 2009 Expanded CSSR – by CAM

25 E. Bong 25 XCS Final Instrument Design Review Engineering Status April 21, 2009 Control Accounts & Work Packages – by WBS L2

26 E. Bong 26 XCS Final Instrument Design Review Engineering Status April 21, 2009 Control Accounts & Work Packages – by CAM

27 E. Bong 27 XCS Final Instrument Design Review Engineering Status April 21, 2009 P3 Files & Total Activities – by CAM

28 E. Bong 28 XCS Final Instrument Design Review Engineering Status April 21, 2009 P3 Files Milestones – by WBS L2

29 E. Bong 29 XCS Final Instrument Design Review Engineering Status April 21, 2009 Procurements and Dollars – WBS

30 E. Bong 30 XCS Final Instrument Design Review Engineering Status April 21, 2009 Labor/Non-labor Split – WBS 1.4