Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Power Supply System John Joseph LBNL Spectrometer Solenoid Test Plan Review Feb 17 th 2012.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
Project Update for the Muon Ionization Cooling Experiment (RAL) Mark Palmer Fermilab December 15, 2014.
G2P Target installation and Beyond. Schedule Pivot before.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
SS and AFC Control Systems Brian Martlew 21 st Sept 2011.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
Electrical Installation CM39 Andy Gallagher & Ian Mullacrane.
Spectrometer Solenoid Update Steve Gourlay Steve Virostek Lawrence Berkeley National Lab Steve Gourlay Steve Virostek Lawrence Berkeley National Lab MICE.
Vacuum and cryogenic systems in R5.2 for MICE Presentation to the MICE/ISIS Operations meeting on 16/03/2015.
Electrical & Control CM40 Daresbury Laboratory. CM40 Electrical Infrastructure Update RRM2 Latest Latest on Installation Progress Rack Allocations Racks.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
MICE - UK Project Progress Roy Preece 30 th April 2013.
MICE Decay Solenoid Quench Detector Trevor Hartnett Daresbury Laboratory.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Control and Monitoring System / EPICS Pete Owens Daresbury Laboratory.
Magnet quench during a training run Successfully trained to peak currents and operationally tested Thermal performance requirements met 3D magnetic bore.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
MOM Report Galina Vankova RAL, MICE Video Conference.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
February 17-18, 2010 R&D ERL Bob Lambiase R&D ERL Power Supplies Bob Lambiase February 17-18, 2010 Power Supplies.
Electrical & Control Power Supplies Trevor Hartnett.
Overview of Tracker Interlocks Designed to protect tracker equipment, in particular the VLPC cassettes, from damage due to failure in part of the tracker.
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
1 Mice Collaboration Meeting CM28 Bankya Palace Spa Hotel, Sofia, Bulgaria 3 rd -8 th Oct 2010 Daresbury Laboratory Spectrometer Report Authors : Ian Mullacrane.
Project Managers Report CM40 Collaboration Board – Rome Roy Preece 28 th October 2014.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
MICE Power Supply System John Joseph LBNL Spectrometer Solenoid Controls & Monitoring Review Dec 11 th 2012.
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
1 Mice Collaboration Meeting CM27 STFC Rutherford Appleton Laboratory, UK 7 th -10 th July 2010 Daresbury Laboratory Electrical Infrastructure Report Authors.
Status of the MICE Construction Project Resource Loaded Schedule Review 29 th April 2014 Roy Preece.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
MICE Project Progress Update Power Converters Rack housing MQ1 to MQ3 magnet power converters –Marshalling for all other quadrupole & dipole units –Houses.
A Gallagher Oct 2015 Electrical Integration MPB October 2015.
UK Project Plan (Finance & Risk) Alan Grant STFC DL RLSR 5 th April 2016.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
MICE Spectrometer Solenoids Step IV running. MICE Spectrometer Solenoids Remember: Both magnets met the full specification at the vendor and were fully.
ELENA installation progress F. Butin / ELENA collaboration.
MICE Spectrometer Solenoids Step IV running
S A Griffiths CM42 June 2015 Electrical & Control.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
Electrical Configuration and System Protection
S. Feher MICE Magnet Readiness Review RAL, June 28th, 2016
MICE RF System Power Supplies, Control and Monitoring Status report
Status of the MICE Construction Project
Electrical & Control.
MICE CM31 Schedule summary
LV Safe Powering from UPS to Clients
Focus Coil Quench Detector
Presentation transcript:

Electrical Integration CM38 Steve Griffiths & Ian Mullacrane

S A Griffiths & I D Mullacrane CM38 Feb 2014 Contents Decay Solenoid Power Supply replacement QD System Upgrade Rack Room 2 Infrastructure AC Electrical Distribution UPS System Cooling Channel Control racks Cooling Channel Power Supply racks FC and SS QD Systems Compressor and Vacuum rack Diffuser and Tracker Control rack 2

S A Griffiths & I D Mullacrane CM38 Feb 2014 Decay Solenoid Power Supply & QD System Upgrade 3 Existing PSI Power Supply & QD System in MICE Hall Existing Power Supply is electrically noisy and unreliable. Causing QD system to trip at currents below 150A. New Power Supply from FuG was procured and delivered in Sept Failure of a Solenoid - current lead has delayed the installation. Power Supply installation and commissioning is planned for April A new DL QD system has been installed and final commissioning is planned for March The DL QD system has been operated with existing Power Supply up to 150A. A Quench Data Logger system will be constructed to monitor the Solenoid during initial operations.

S A Griffiths & I D Mullacrane CM38 Feb 2014 Decay Solenoid Power Supply Replacement 4 FuG - Superconducting Magnet Power Supply - 10V, 1000A FuG - Superconducting Magnet Power Supply - 8V, 1000A Discharge Resistors Rectifier & Smoothing Capacitors Transistor Bank for Output Regulation Main DC contactor

S A Griffiths & I D Mullacrane CM38 Feb 2014 Quench Detection System Upgrade 5 Existing system contains obsolete components. Combines the reliable PSI philosophy with a modern modular design. Tripping points are set at 20mV for most of the voltage taps except for channel 4 which is set at 40mV. The Voltage taps from the magnet are arranged in sets of three with overlap along the length of the solenoid. Not all of the voltage taps are used. DL Quench Detection System

S A Griffiths & I D Mullacrane CM38 Feb 2014 Rack Room 2 – Step IV Equipment Layout 6 Room infrastructure progressing well, handover planned for cable management installation in March Proposed extended MCR? Allocation and position of racks and equipment for Step IV agreed and finalised. QD & QP system for SS – layout / position to be confirmed.

S A Griffiths & I D Mullacrane CM38 Feb 2014 Rack Room 2 – Infrastructure 7 New Door Access Cable Management from Hall Cable Management under stairs Cable Access into RR2

S A Griffiths & I D Mullacrane CM38 Feb 2014 Rack Room 2 – AC Electrical Distribution 8 Main AC Supply for Critical Loads via UPS Main AC Supply for General Distribution Lighting replaced and main AC feeder installed 208V Transformer

S A Griffiths & I D Mullacrane CM38 Feb 2014 AC Distribution for RR2 up to Step VI 9 AC Distribution separated into Critical systems and General distribution All Critical systems are fed via the 30KVA UPS with 1 hour autonomy. General distribution includes DC magnet power supplies, A/C conditioning and lighting. Critical systems includes instrumentation, controls system and cooling water for SS energy absorbers 208V Transformer Main Hall Board

S A Griffiths & I D Mullacrane CM38 Feb 2014 Rack Room 2 – UPS Inverter and Batteries 10 UPS for Critical Loads Riello UPS – Sentry unit 3 Phase - Double Conversion Technology As the total load will be significantly lower than 30KVA the autonomy will be >1hour

S A Griffiths & I D Mullacrane CM38 Feb 2014 Rack Room 2 – Cooling Channel Racks Step IV 11 FC & SS Power Supplies, Instrumentation and Control Racks Racks allocated up to Step VI

S A Griffiths & I D Mullacrane CM38 Feb 2014 Cooling Channel Rack Configuration 12 All 7 Cooling Channel Control & PSU racks to be located in RR2 are designed and assembled as far as possible. RR2 installation is scheduled for May Cooling Channel Control Rack Spectrometer #1&2 Control & Instrumentation Rack FC Control & Instrumentation Rack FC Power Supply Rack Spectrometer #1 Power Supply Rack Spectrometer #2 Power Supply Rack Spectrometer #1&2 Discharge Circuit Rack BlisterFrontBack

Focus Coil & Spectrometer Solenoid Control Racks 13 These 3 racks have been designed, assembled and partially commissioned. Awaiting procurement / delivery of instrumentation to fully populate. Spare

Focus Coil & Spectrometer Solenoid Control Racks 14 Racks viewed from rear Cooling Channel Control – VME crates, CANBUS modules, ADC, DAC and serial interfaces. FC & SS Control - He level gauges, temperature indicators / controllers, pressure indicators and interfacing.

Focus Coil & Spectrometer Solenoid PSU Racks 15 These 4 racks are all designed. Assembly is completed apart from SS#2 PSU rack.

Focus Coil & Spectrometer Solenoid PSU Racks 16 Assembly and commissioning can only be completed after procurement / delivery of instrumentation (SS#2 PSU rack requires DC contactors). Racks are partially commissioned. FC PSU Rack-Front FC PSU Rack-RearSS PSU Rack-Rear SS PSU Rack-Front

Spectrometer Solenoid Energy Absorber Rack 17 Upstream SS energy absorber have been upgraded and thermally tested. Cooling water circuits have been modified and flow indication added. Downstream SS energy absorbers will be delivered once Solenoid training complete. (May 2014) Energy Absorber Rack-Rear with and without DC Cables Items Required

S A Griffiths & I D Mullacrane CM38 Feb 2014 Instrumentation required for FC & SS Racks 18 Racks will be populated once testing of the Spectrometer Solenoids is complete. Availability of FC instrumentation depends on training schedule. There are still power supplies and instrumentation to be procured for Step IV for both FC and SS. A list is being compiled of the remaining items for the SS, funding needs to be agreed for these and DC magnet / controls cables. Control & Instrumentation racks operational at WANG and RAL R9

S A Griffiths & I D Mullacrane CM38 Feb 2014 Rack Room 2 – QD & QP Systems 19 3 Racks allocated for the QD & QP systems for FC, SS & RFCC SS QD & QP System FC QD & QP System All Step IV systems fully installed and commissioned by Nov 2014

S A Griffiths & I D Mullacrane CM38 Feb 2014 Quench Detection & Protection Racks 20 SS QD / QP System rack FC QD / QP System rack RFCC QD / QP System rack The location of the FC QD systems is agreed. (for all 3 focus coils) Tests are being conducted to ensure reliable operation with 36m voltage tap cable lengths. Two FC QD systems are assembled and tested. One system is currently being used for training the FCs. The location for SS QD systems is being discussed. A second SS QD system is to be assembled, tested and installed before Nov Integration of the data logging for both systems needs to be finalised.

Diffuser and Tracker Control Rack 21 The rack design is being developed with the work package managers. The rack will be assembled ready for population with equipment by Summer 2014.

S A Griffiths & I D Mullacrane CM38 Feb 2014 Compressor & Vacuum Control Rack 22 The control system requirements for the compressors are agreed and the rack physically assembled. The vacuum control and instrumentation have been reviewed and equipment ordered. Control philosophy needs to be finalised with Vacuum specialists

S A Griffiths & I D Mullacrane CM38 Feb 2014 Summary Project Plan for Step IV Electrical & Controls is fully developed and linked to the master plan. Resource priorities are focused on the Step IV milestones and this may affect other work packages such as RF systems. Electrical & Control requirements for Step IV are progressing well. Installation & commissioning is dependent on key milestones such as installation of South PRY, FC and downstream SS. Peak resource loading will occur between July and November 2014 and will need to be carefully co- ordinated. 23

Questions? CM38 Steve Griffiths & Ian Mullacrane Acknowledgements Chris White Trevor Hartnett John Webb Andy Gallagher 24