Telescope Integration and Tests Tuesday Afternoon.

Slides:



Advertisements
Similar presentations
MMIRS 1 MMIRS MMT and Magellan Infrared Spectrograph Brian McLeod.
Advertisements

CMSC 2006 Orlando Active Alignment System for the LSST William J. Gressler LSST Project National Optical Astronomy Observatory (NOAO) Scott Sandwith New.
1 Second Safety Council Meeting Tucson, AZ April 10-11, 2014 Name of Meeting Location Date - Change in Slide Master The Dome Project Bill Gressler Telescope.
FLAO Alignment Procedures G. Brusa, S. Esposito FLAO system external review, Florence, 30/31 March 2009.
LBT AGW units Design Review Mar.2001 General Concept Performance specifications and goals The off-axis unit The mechanical support structure The control.
NGAO Instrumentation Overview September 2008 Updated Sean Adkins.
WFS Preliminary design phase report I V. Velur, J. Bell, A. Moore, C. Neyman Design Meeting (Team meeting #10) Sept 17 th, 2007.
NGAO Alignment Plan See KAON 719 P. Wizinowich. 2 Introduction KAON 719 is intended to define & describe the alignments that will need to be performed.
WBS & AO Controls Jason Chin, Don Gavel, Erik Johansson, Mark Reinig Design Meeting (Team meeting #10) Sept 17 th, 2007.
LIGO-G D partial ADVANCED LIGO1 Development Plan R&D including Design through Final Design Review »for all long lead or high risk subsystems »LIGO.
Project Plan The Development Plan The project plan is one of the first formal documents produced by the project team. It describes  How the project will.
P. Wizinowich & D. Le Mignant for Keck AO Team AOWG – June 6, 2002 Keck AO Overview to support summit tour.
Integration and Test 14 October 2008 Martin Nordby.
Status of IPBSM Improvement N. Terunuma, KEK 2012/July/13 ATF2 Weekly Meeting.
Integration and Alignment of Optical Subsystem Roy W. Esplin Dave McLain.
Control Software Integration German Schumacher T&S Software Lead.
M2 Status & Near Term Major Milestones C. Araujo/B. Gressler 1.
MCAO Adaptive Optics Module Mechanical Design Eric James.
Magellan F/5 System Status A.Szentgyorgyi/SAO/30 Apr 2005.
Monday Morning J. Sebag T&S Systems Engineer. Close Past… 2 M1M3 acceptance and transportation to storage Reviews and RFPs (Dome, Software, Coating Plant,
Presentation EddiCam consortium, FF, Madrid 13/06/2002 Eddington programmatic status Fully approved by SPC as part of ESA’s science program as project.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
Sandrine Thomas (T&S Project Scientist) & Telescope and Site Team.
Magellan F/5 System Status A.Szentgyorgyi/SAO/25 Sept 2004.
M1M3 Status & Near Future Milestones C.Araujo/ J. Sebag 1.
FLAO system test plan in solar tower S. Esposito, G. Brusa, L. Busoni FLAO system external review, Florence, 30/31 March 2009.
Magellan F/5 System Status A.Szentgyorgyi / Ann Arbor 25 Sept 2005.
RWA, 8/12/2006 Present Preliminary Production Plan All still preliminary, as we are re-establishing production. January 9 th,2007: –Delivery of 2 ring.
The Active Optics System S. Thomas and the AO team.
FELT 1 Study of the capability and configuration of a fixed mirror Extremely Large Telescope (FELT) Low cost path to large telescope Primary concern is.
Update on the GRINCH Detector SBS meeting, 21 Oct 2015 T. Averett, W&M JLab, NC A&T, JMU, Glasgow Timing-based gas Cherenkov detector PMT array-510 tubes.
Telescope Mount Assembly (TMA) Status and Schedule Design Contractor: Empresarios Agrupados (Madrid Spain) Fabricator: Asturfeito (Asturias, Spain) LSST.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
7 November 2003 Status of CNGS NBI presented by K. Elsener 1 Status of CNGS Konrad Elsener CERN – Accelerators+Beams Division.
Page 1HMI/AIA Science Meeting – February 13, 2006 HMI Instrument Status HM/AIA Science Meeting February 13, 2006 Barbara Fischer HMI Deputy Program Manager.
COSMO Large Coronagraph Preliminary Design Review
Taikan SUEHARA, IN2P3-KEK collaboration meeting on ATF2, Annecy, 2007/10/15 Shintake Monitor: Installation and Commissioning Schedule Taikan SUEHARA, The.
SPIE 2014 Montreal, Quebec, Canada June 22 nd - June 27 th, LSST Telescope and Site Status William J. Gressler Telescope and Site Manager J. Andrew,
FLAO_08 FLAO System Shipping Plan Document 646f010a Richard Demers, Guido Brusa, Armando Riccardi, Daniele Galieni FLAO system external review, Florence,
MMIRS Status A.Szentgyorgyi/SAO 30 April Imaging 7 x 7 arcmin FOV 0.2 arcsec pixels Y,J,H & K wavelength coverage Spectroscopy Multislit (4’ x 7’)
FourStar Status SAC Meeting 13mar2010 Persson, Murphy, Birk, Monson, Kelson, Uomoto.
MMIRS 1 Harvard-Smithsonian Center for Astrophysics Magellan SAC 9/05 MMIRS Status Upate Presented by A. Szentgyorgyi P.I. B. McLeod.
Report to the SSC Jan 10, Report to the SSC-Jan 10/02Page 2 Key Dates Nov 13-14/01Preship Review Jan 4/02Final review before disassembly Jan 7Start.
Fernanda G. Garcia, Steve Dixon, Andy Stefanik, Justin Tillman, John Voirin SBN Far Detector Installation & Integration.
Tim Abbott & Brenna Flaugher, CTIO Integration Meeting 1 The DECam Project Closeout, Action Items Hexapod Optical Lenses CCD Readout Filters Shutter 2008.
Content Lessons from writing proposals and work on PTDR How can this meeting help to remedy problems SCT AOB.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Commissioning Planning
LSST Commissioning Overview and Data Plan Charles (Chuck) Claver Beth Willman LSST System Scientist LSST Deputy Director SAC Meeting.
LSST External Communications Suzanne Jacoby, Andrew Gordon Communications Leads at LSST and SLAC August 17,
ComCam Hardware and Interfaces James Howard ComCam CAM LSST 2017 Project & Community Workshop 2017 Aug 15.
Camera Maintenance and Access
Agenda ComCam planning and scheduling (James & Jacques) CCS & CCS-TCS Interface (Tony) Software to use ComCam Software to get data out of ComCam (Mike)
Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J
Systems Engineering, Verification, and Commissioning for LSST George Z
ComCam Hardware and Interfaces James Howard ComCam CAM LSST 2017 Project & Community Workshop 2017 Aug 15.
LSST Commissioning Overview and Data Plan Charles (Chuck) Claver Beth Willman LSST System Scientist LSST Deputy Director SAC Meeting.
INSTALLATION SEQUENCE
LSST Commissioning Kevin Reil LSST Commissioning Camera Rep
Prime Focus Imaging Spectrograph Status
SCHEDULE Nov 1st - Assembly Table Complete
ETS For ACTR 9the April 2015 R.Tighe april 2011 april /04/2015
Chuck F Claver LSST System Scientist & Commissioning Lead
Camera to Top End Assembly Integration Travis Lange Camera I&T M. E
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
GLAST Large Area Telescope: Cost/Schedule Review September 1, 2005
Management Breakout: MREFC Budget Summary Victor L
Click to add title Planning for LSST Verification George Angeli LSST All Hands Meeting Tucson August 15, 2016.
Vendor Interactions Paul J. Lotz.
Instrument Overview Larry Springer HMI Program Manager
Presentation transcript:

Telescope Integration and Tests Tuesday Afternoon

2 Status: Document LTS-104 describes the Telescope integration and tests Plan This coming year, this plan will be reviewed and updated: -Using vendor schedule input -Include software development WBS 4-14

Integration sequence in phase with subsystems delivery Integration and Test Plan (LTS-104) describes the general strategy, includes the integration and test sequence and provides a summary for all major key activities. Three Major Phases: Phase 1 (P1): Heavy Construction Phase 2 (P2): Mirrors Coating and Integration Phase 3 (P3): Alignment Phase START END P1 P2 P3

Phase 1 Heavy Construction Summit Facility construction (lower enclosure, support building, platform lift, AT lower enclosure) Provide early access for Dome Installation (lower enclosure and pier ready) and Coating Plant installation Crane + Manpower to build Dome included in I&T WBS (supervisory from dome contractor). Mount and Coating Plant Installation on site included in contract. Dome Light/Wind Screen installation finalized after Mount installation for shutter door access Laser Tracker used during Integration 6 months 11 months P1 Mount Testing Milestones: Mount Acceptance Tests Refine positioning look-up tables First Pointing on Sky Refine TCS Pointing Model on sky with small alignment telescope 6 months Total: 1year 5months M1M3 Cell with Surrogate Mirror

Mount sections installed through the dome shutter doors using outside crane 1- Azimuth Track Integration2- Azimuth Bearing Installation3- Elevation Pier Installation 4- Center Section Integration 5- Top End Ring Integration Welded in place Az drives installed and Tested 1 st Elevation balance 6- Platform, Surrogate Mass Installation

M1M3 Cell Reception Sequence M1M3 Mirror CartM1M3 Cell Reception Cell Installed on CartM1M3 Surrogate Mirror From Integration and Test Plan (LTS-104)

Phase 2 Starts after end of heavy construction for safe handling of mirrors M2 Coating during Mount Testing (overlap with Phase 1) M2 is first installed on Telescope Mount M1M3 Mirror Reception and Integration in cell M1M3 coating and assembly (Mount locked at Zenith) Calibration Screen installed on Dome during M1M3 coating M1M3 integration on Telescope P2 3 months 2 months 1 month 3 months 2 months Total: 10 months

M1M3 Cell and M1M3 Mirror Assembly M1M3 Lifter Staging M1M3 Mirror Reception M1M3 Container Open M1M3 Mirror Installation in Cell M1M3 Cell Preparation M1M3 Cell under coating chamber

Phase 3 starts with M3 tests for 3-Mirror Telescope testing Repeat M3 Mirror System performance tests under full active control at zenith pointing (with interferometer) Install Integrating Structure with wavefront sensor (WFS) On-axis 3-Mirror Telescope Alignment (take advantage of diffraction-limited image on-axis by design) Perform Calibration Equipment Tests P3 Total: 8 months M3 Interferometer Shack-Hartmann WFS

Commissioning camera (ComCam) for initial off-axis alignment 1.3-Lenses FOV Corrector (2 lenses + dewar window) 2.40-arcmin Focal Plane Composed of one CCD raft (3x3 CCD Detectors) 3.Intra and Extra focal images used for Wavefront Analysis (on and off-axis) Filters Window 374 mm 309 mm Rotator Hexapod Camera Support Assembly with ComCam ComCam installed on Surrogate Mass

Integration Milestones with Dependence on Main Subsystems Delivery Dependent on following milestones: 1.Dome Ready for Installation 03 Jan 17 2.TMA Ready for Installation12 Jul 17 3.Support Facility ready for Coating Chamber 06 Oct 17 4.M1M3 arrives on site 24 Jan 18 5.M2 arrives on site 10 Apr 18 1.Dome Installation Finished (Ph1)19 Jun 17 2.Telescope Mount Installation Finished (Ph1) 03 Jan 18 3.Coating Chamber ready for use (Ph1) 18 May 18 4.Telescope Mount Testing Finished (Ph1)11 Jun 18 5.Major Exterior Handling Operations Complete (Ph1) 14 Dec 18 6.Telescope ready for 3-mirror testing (Ph2)25 Jan 19 7.T&S ATP Complete (Ph3)30 Sept 19

FDR Schedule in Primavera Team Equipment Activities Y3Y4Y5Y6 Rental