Undulator Orientation & Electron Beam Spacing Should the undulator frames be toward the central aisle or the tunnel walls? What is the optimum spacing.

Slides:



Advertisements
Similar presentations
Beam-plug and shielding studies related to HCAL and M2 Robert Paluch, Burkhard Schmidt November 25,
Advertisements

HOB 2013 Body Mechanics The back you save can be your own.
ICRA Panel System Installation Instructions
CMS ZDC Crane Emergency Payload Removal Procedures This document proposes the viability of using a portable hydraulic actuator Hand crane (Davit crane)
MODULE TRANSPORT CLIC Module Working Group 27 September 2010 Keith Kershaw CERN EN-HE.
Spiral Stairs Assembly Instruction By Laser Dollhouse Designs
Answer each of these with your first instinct to the answer. You will have limited time to submit an answer. There will be a bit of discussion after most.
Positron Source Update Jim Clarke Deepa Angal-Kalinin James Jones Norbert Collomb At Daresbury Laboratory and Cockroft Institute 21/07/2009.
XFEL Undulator Efforts at DESY and Thoughts on LCLS-II H.-D. Nuhn June 30, 2010.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
Robert Ruland Installation Alignment -Magnetic Measurements – Fiducialization April 7-8, 2005 FAC Meeting 1 Installation Alignment,
TAGGER MAGNET DESIGN Presented by Tim Whitlatch Hall D Tagger Magnet Design Review July 10,
Sector 13 Canted Undulator Upgrade Hutch Modification Requirements.
Conceptual Design Review Senior Design
Super-B Factory Workshop January 19-22, 2004 Super-B IR design M. Sullivan 1 Interaction Region Design for a Super-B Factory M. Sullivan for the Super-B.
Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center LCLS Undulator Physics.
Robert Ruland MMF Layout, Workflow October 14, 2004 MMF Review 1 MMF Layout, Workflow Robert Ruland Magnetic Measurements Facility.
Sector 13 Canted Undulator Upgrade Hutch Modification Requirements ( )
Zachary Wolf Undulator Oct 12, LCLS Undulator Tuning Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko,
1 Telecom Cabling Ladder racks systems and relay racks Ladder racks systems and relay racks.
By:Sierra Fluker Cindy Williams Gloria Gordon.  First, adjust the height of the seat so that the work surface is elbow high.  Place feet on the floor.
Tagger and Vacuum Chamber Design. Outline. Design considerations. Stresses and deformations. Mechanical assembly.
DELTA Quadrant Tuning Y. Levashov, E. Reese. 2 Tolerances for prototype quadrant tuning Magnet center deviations from a nominal center line < ± 50  m.
MICE Magnetic Field Mitigation Review Potential impact on ISIS of MICE Stray Magnetic Fields 24 th September 2013 Martin Hughes.
SoLID EC Update Zhiwen Zhao 2012/05/22. Beam test update Coverage for PVDIS Road map.
Global Design Effort - CFS LCWS CONVENTIONAL FACILITIES AND SITING GROUP Parallel Session Overview A. Enomoto, V. Kuchler, J. Osborne.
FUNCTIONAL SPECIFICATION Dorothea Pfeiffer Dennis Haasler GIF++ User Meeting
Magnetic Shielding Issues Roy Preece STFC - RAL. Overview Issues Items in harms way – Step IV Step IV mitigation plan –Racks –Compressors Current / Future.
1. Two long straight wires carry identical currents in opposite directions, as shown. At the point labeled A, is the direction of the magnetic field left,
Magnetic Shielding Roy Preece. Issues Cooling channel initially designed without return yolks. Current North and South shielding walls designed to encapsulate.
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
BEPCII Prealignment Installation Survey and Alignment Accelerator Center of IHEP Xiaolong Wang
Magnetic Mitigation - Contents l Magnetic Mitigation General l West Wall Compressors l Rack Room 2 l Magnetic Shielding Yoke Jason Tarrant – Integration.
Thickness of the Kamaboko Tunnel Shield Wall under Different Assumptions Ewan Paterson Technical Board June 23,
Andrew Moss ASTeC CM32 9t h February 2012 RAL MICE RF System.
GIF in EHN1- layout, construction and schedule Adrian Fabich, EN-MEF-LE GIF users meeting, 12 th February 2014.
Option – 5m Undulators What is the optimum length for an LCLS undulator?  XFEL is using 5m undulator segments.  Is this optimum?  What are the advantages.
Integrated Radiation Measurement and Radiation Protection of BES Ⅲ Zhang Qingjiang, Wu protection group, accelerator center, IHEP,
Update for muon studies Helmut Vincke. Additional dump calculations Two options were studied: Option 1: beam is bend by 2 degree towards soil and beam.
Lau and Niels, NA62 TD meeting, 17 March Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10.
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
CM25 Engineering 1 4 Nov 2009 DIFFUSER Carousel (~50kg) Driven by air motors – 3 separate ‘actions’ 1.Carousel rotation 2.“30 degree rotation’’ Transfers.
G.Barber Mice Tracker Mechanical Progress Tracker Mechanical Progress Contents:- Station Space Frame Station Layout Light Guide Map Connectors Patch.
LER Workshop, October 11, 2006LER & Transfer Line Lattice Design - J.A. Johnstone1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Introduction The.
Primary beam production: progress - Extraction from LSS2 - Switching from TT20 at 100 GeV B.Goddard F.Velotti, A.Parfenova, R.Steerenberg, K.Cornelis,
Spreaders & Recombiners Beam Transport Michael Bevins May 30, GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation.
CLIC MODULE TRANSPORT AND INSTALLATION Keith Kershaw CES, 8 October 2008.
Contents Jason Tarrant STFC Aim of Presentation to show: l Problem of compressors located at south shield wall l Description of compressor layout and services.
Shielding review for temporary spectrometer for RUBICON experiment, ATF beamline #2 K. Kusche, M. Fedurin RSC meeting, Jan 20, 2015.
Catherine LeCocq, SLAC Alignment Plan for the LCLS Undulator IWAA 2006,1 Alignment Plan for the LCLS Undulator Catherine.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Mu2e Mu2e Remote Handling Review Comparisons: Costs, Risks & Maintainability Ryan Schultz Deputy L3 Manager Target Station 3/3/2015.
Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer Review of ESS Accelerator Conventional Facility Design.
LCLS-II Project Overview David Schultz LCLS-II Deputy Project Director March 19, 2012.
This material is based upon work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC Michigan State.
Implication of gamma-gamma on 14mr tunnels discussion (questions for discussion with WG-C and WG-A) Valery Telnov Budker INP IRENG07, Sept.19, 2007, SLAC.
1 Target Station Design Dan Wilcox February 2012.
VELO-installation meeting CERN, January 17, 2006
Things to Know About Push Back Pallet Racking System
Potential Use of PEP-II Magnets by Project X
LST Module Installation
Electron Beam Setup for Bubble Chamber
HRS at small angles for e+/ e- pair for APEX
SPEAR Summer/Fall Downtime Alignment Schedule
Extract from today’s talk given to DCB
Text Reference: Chapter 32.1 through 32.2
Undulator Alignment Plan
Undulator Alternatives
Some of the Points Raised During my JLAB Visit
Presentation transcript:

Undulator Orientation & Electron Beam Spacing Should the undulator frames be toward the central aisle or the tunnel walls? What is the optimum spacing between the electron beams in the two undulators? Slide 1Orientation & Spacing Undulators, M. Rowen,

Orientation of Undulators The issue is whether to face the undulators frame side to the wall, initial plan, or frame to the center aisle, alternate plan. Slide 2Orientation & Spacing Undulators, M. Rowen, Frame towards aisle Electron beam at 3.0m separation Frame towards walls Electron beam at 2.5m separation

Pros for Frames Toward Aisle: Undulator vacuum chamber can be installed and aligned before the undulator is installed. Undulator can be removed independently; no other components need to be removed.  Undulator can be removed without breaking vacuum. Easy access to the undulator mechanical parts for maintenance. Reduces the need to access the wall aisle. Greater beam separation at the electron dump and FEE areas.  Can also increase separation of electron beam with frames toward the aisle. Slide 3 Orientation & Spacing Undulators, M. Rowen,

Cons for Frames to Aisle - Alignment Alignment is a major problem with the frames toward the aisle. Would require twice as many setups, i.e. twice the labor and result in slightly reduced vertical positioning accuracy.  Initial alignment will take two crews instead of one. Doubling the cost of the initial alignment. The crossbar will limit the geometry of the fiducials on the undulator jaw. The accuracy of the roll measurement of the roll will the decreased.  Mapping the position of undulators will require three times more setups due to the limited field of view.  Taking measurements of the vacuum chamber once the undulator is installed might be impossible. This depends on the final position of the crossbar of the undulator support and the spacing of the two undulators.  If the vacuum chamber is aligned beforehand we will have an additional leveling step. Slide 4Orientation & Spacing Undulators, M. Rowen,

Cons for Frames to Aisle – Beam Separation Requires wider x-ray beam spacing (3.0m – 3.1m)  With the present ( ) undulator frame layout the beams need to be 3.06m apart to maintain a 1.5m aisle.  Requires larger angle at switching magnet to switch between hard and soft x-ray undulators.  Paul Emma says he could do 3.1m if that is required.  May have some negative effect on the beam. Slide 5Orientation & Spacing Undulators, M. Rowen,

Cons for Frames to Aisle – Magnetic Measurement The large variable gap undulators will be much more labor intensive to remove to the MMF. in situ magnetic measurements to determine if there is degradation of the magnets is a possible approach.  No defined procedures for in situ measurements.  Need to set up a group to look at what can be done in this area. Will likely to require removal of undulator vacuum chamber.  This would be more straight forward if frames are toward the wall. Slide 6Orientation & Spacing Undulators, M. Rowen,

Vacuum Chamber Orientation Orientation of the vacuum chamber strong back effects alignment. Strong back to the frame would be better for alignment, but the chamber strong back would have to fit through the open undulator jaws.  It is not clear this can be done. Placing the strong back toward aisle will reduce area expose on lower jaw for roll alignment and access to only one surface of vacuum chamber for vertical position. Vacuum chamber orientation needs to be assessed. Slide 7Orientation & Spacing Undulators, M. Rowen,

Undulator Hall – 2.5M Spacing Slide 8Orientation & Spacing Undulators, M. Rowen,

Undulator Hall – 2.5M Spacing Slide 9Orientation & Spacing Undulators, M. Rowen, Access Through Undulator Line Rack behind Undulators Racks required only every 2 nd or 3 rd undulator depending on rack height.

Undulator Hall with Racks Under Quad stands Slide 10Orientation & Spacing Undulators, M. Rowen, Electronics Racks Pass Through Racks required only every 2 nd or 3 rd undulator.

Conclusion Undulator Orientation The undulators should be oriented with their frames toward the tunnel walls. This is driven by:  Improved configuration of alignment.  Better access for in situ magnetic measurements.  Does not require a change in electron beam separation. Slide 11Orientation & Spacing Undulators, M. Rowen,

Electron Beam Separation Is 2.5m the optimum electron beam separation?  Need to move undulators and other large items down central aisle way.  Need access to back side of undulators for access to electronics and maintenance.  Need to be able to search the undulator hall.  Need egress and access for emergencies. Clear space through electron beam dump. Space at down stream end front end. Space between hard and soft x-ray stations. Slide 12Orientation & Spacing Undulators, M. Rowen,

Effect on Electron Optics Should be able to increase separation between hard and soft x-ray lines to 2.75m without major changes to electron optics. Just move bend to bring beam back to parallel down stream a bit. By 3.0m need to increase angle of switching magnet, as there is not enough free z space. Need to confirm this with Paul Emma. Slide 13Orientation & Spacing Undulators, M. Rowen,

Dump Area Access between components in dump area is limited.  Stands need to be redesigned  Greater separation between electron beams would be beneficial. Slide 14Orientation & Spacing Undulators, M. Rowen,

Experimental Stations Assuming 2.75m electron beam separation can increase spacing between nearer soft x-ray station and hard x-ray lines from 2.64 to 2.89m. Slide 15Orientation & Spacing Undulators, M. Rowen,

Front End Spacing with 2.75m separation at down stream front end is still reasonable.  Possibly move south shielding wall out some. Slide 16Orientation & Spacing Undulators, M. Rowen, Shielding Front End EH2

Undulator Hall – 2.75M Spacing Slide 17Orientation & Spacing Undulators, M. Rowen,

Conclusions Increasing beam separation to 2.75m:  Improves access through dump area  Space at between hard and soft x-ray lines.  There a small benefit for alignment.  Need to confirm: No significant effect on electron beam. There are significant additional issues on fire safety and egress. No major changes with searches.  May need to keep tunnel side walls free of utilities. Slide 18Orientation & Spacing Undulators, M. Rowen,

Cables & Utilities Keep cable and conduits off the floor.  Eliminate this trip hazard.  Cables and conduits should drop from over head. For alignment clear lines of site must be maintained (see presentation C. LeCocq).  Cables and conduits drops must be limited to specific areas.  70cm below each wall monument must be kept clear for leveling fixtures (see presentation C. LeCocq). Possible run local cables to components along back of undulators. Slide 19Orientation & Spacing Undulators, M. Rowen,

Local Cable Runs Along Back of Undulators Slide 20Orientation & Spacing Undulators, M. Rowen, Cable Trays supported from floor for local cables from equipment to electronics racks Electronics Rack