Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.

Slides:



Advertisements
Similar presentations
Carrier Pre-Select Meeting BT Systems Interface Roadmap
Advertisements

Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
Interconnect Policy & Contract HL SAN + 1 Month (Max), unless extension requested by Operator,and agreed by BT, due to insufficient.
11 Ofcom Consumer Switching final statement Next steps for BT Bev Bytheway-Jackson WBC Product Manager 10 th February 2014.
Title Consult 21 Mike Reed - Openreach Name 21 st February 2006.
For discussion purposes. No implementation assurances 1 Consult 21 Interconnect & Portfolio Working Group NGN Interconnect - PSTN Emulation Blended Rate.
This update is a BT perspective of Working Group status including input from the Co-Chair call of 7 th September Nigel Scott 13 th Sept 05 Consult21 -
Software projects Management & Development Alireza Saebi
Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
©OTA O TA Office of the Telecommunications Adjudicator 1 11/10/20041 High Level Review and Status of Activities under the Telecommunications Adjudicator.
For discussion purposes. No implementation assurances 1 Consult 21 Interconnect Working Group NGN Interconnect - PSTN Emulation Technical Consultation.
Standard Contract Forum 24 April Customer Suite, BT Centre, London.
STEERING BOARD Market sector representation ~ Debating Policy ~ Escalation of Issues ~ Agreement on when formal Consultation is required Engagement between.
I&P: Contracts Clinic 24/02/06 1 Minutes Table Derivation & Application of Overflow The focus of the presentation is on principles: How it works how we.
Standard Contract Forum 26 September Customer Suite, BT Centre, London.
Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
Deakin Richard Tan Head, Information Technology Services Division DEAKIN UNIVERSITY 14 th October 2003.
Operation of vDLE concept Revised C&W proposal. Background C&W continue to believe that in the “virtualised” situation CPs should pay connection & rental.
Rationale for the changes Proposals for change were consulted on through ‘Raising expectations: Enabling the system to deliver’ White Paper published in.
The public information campaign to communicate about the process of migration to BT’s next generation network Version 11 – 24 September 2007 Information.
Anthony Stephens 21CN Customer Engagement 1 21CN High Level Consultation Plan The following plan provides a four month view of key consultation themes.
Consult21 IMWG Pre-Migration Scheduling Consultation Summary & Approach The purpose of this presentation is to share the summary and.
MIGRATION PROPOSAL: CONSULTATION FRAMEWORK Dave D’Arcy This Presentation provides a generic view of feedback received from Communications Providers during.
Becoming a Great Project Manager Gini Courter Annette Marquis TRIAD Consulting.
Equal Access: Space, Power & Common Infrastructure – LLU and 21C Gary Williamson Openreach LLU Business Improvement Manager January 2006 Queries to
Business unit (for internal use only) / url (for external use) Implementation & Migration Programme Plans This presentation covers: Consultation Plan –
Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
Director Industry Development Jo Upward FORWARD LOOKING STATEMENTS – CAUTION ADVISED Certain statements in this presentation are forward-looking and.
Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
21CN Legacy Interconnection Working Group 17 th December 2004 Auditorium City Place, Gatwick.
DELIVERING BT’S 21 ST CENTURY NETWORK INDUSTRY WORKING GROUP ON MSAN ACCESS & INTERCONNECTION 22 October 2004.
IMPLEMENTATION & MIGRATION WORKING GROUP PROVISIONING EXPERTS MEETING Wednesday 1st March 2006.
Interconnect Policy & Contract
Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
UK Link Programme Dashboard Report Change Overview Board: 13/05/2014 Critical HLD activities complete enabling entry into Detailed Design Detailed Design.
Basic principles of possible new international legal framework in energy Feygin V.I. Principal Director, Institute for Energy and Finance.
1 EBC Workshop Introduction and Welcome.
Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
Pathfinder update webcall 15 th May 2009 Welcome to the BT's 21CN programme is subject to consultation and further development. Dates and other details.
Portfolio Committee on Appropriations Quarter 1 Expenditure and Performance 24 August 2012 The Presidency Department of Performance Monitoring and Evaluation.
March 30, 2012 Wholesale Generation Interconnection Process Photovoltaic Program Power Purchase Agreements Request for Offers.
Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
Implementation & Migration Working Group 18 th January 2006 Kevin Young Interconnect & Numbering Services The information in this presentation relates.
1 FRIACO OFTEL INTERNET FORUM - 11 December 2000 Geoff Brighton JanWillem van den Bos.
The implementation programme for the 2008 SNA and supporting statistics UNECE special session on National Accounts for economies in transition Geneva,
Consult 21 Interconnect Working Group 7 Nov 2005 Ian Self Virtual Interconnect Capacity Product Outline The information in this presentation relates to.
Interconnect Policy & Contract
Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
The SaTH Foundation Trust Programme Deborah Shaw March 29th 2007.
Consult 21 Update - Agenda Consult21 Steering Board Remit Membership Detail Recent and Future Meetings Programme Plans Nigel.
The public information campaign to communicate about the process of migration to BT’s next generation network Version 14 – 03 November 2008 Information.
Consult21 Consult21 Working Group – Broadband and LLU 3rd Meeting 19 April :00 – 14:00 WELCOME.
1 DLE to NGS Migration: Contracts Clinic 24 th February 2006 The information in this presentation relates to plans currently under development and subject.
Welcome Learning for Living and Working in London 12 May 2008 Neil Roberts London West LSC.
Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject.
Information in this presentation is subject to change NEXT GENERATION BROADBAND UPDATE Thursday 3 April 2008 Delivered over BT’s 21 st Century Network.
Consult21 Systems & Process Working Group 19th October 2005 Welcome.
CPS LOCAL EXCHANGE CALLS BT WHOLESALE UPDATE 2 SEPTEMBER 2004 TIM HOWSON PRODUCT DEVELOPMENT MANAGER The information in this presentation.
1 The information contained in this Presentation is confidential information as per your terms and conditions with British Telecommunications plc (BT).
Pathfinder Working Group BT Centre Showcase, Registration: 9.45 am Start time: am.
1 EBC Conference Introduction and Welcome.
ILC 2007 Global Design Effort 1 Planning Damping Rings Activities in the Engineering Design Phase Andy Wolski Cockcroft Institute/University of Liverpool.
Broadband and LLU Working Group 18 January Broadband and LLU Working Group Membership BT Industry representatives Terms of Reference To ensure a.
12 September Billing Meeting Summary. Objectives Review of EBC concepts Establish how EBC will be calculated for the following BT terminating BT Originating.
Grid Code Review Panel 16th August 2017
Standards and Assessment
Cutover & Implementation Aggregated Programme RAG
Overall Project RAG Status:
Presentation transcript:

Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject to change. 1 Migration Provisioning Plan Management The purpose of this presentation is to outline to Communications Providers BT’s view of:  how the transition to an 18 month process will be handled from an operational perspective (slides 2 & 3) through provision of an example BT 21CN implementation programme for CP Interconnect migration from closing DLEs to NGSs  the milestones which BT believes it should be tracking with Industry at the Implementation & Migration Working Group at an Industry level (slides 4 & 5) Additionally this presentation informs Communication Providers on the system BT is developing to support this process (slide 6) Ron Riches

Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject to change. 2 21CN CP Interconnect Migration: Example Implementation Programme The purpose of the example (slide 3) is to show how we may reach the required standard 18 month migration timeline and quarterly SAN issuing Tranches as soon as is practically possible. In the example illustrated, this point will be reached at Tranche 5 After this point, SANs will be issued quarterly, in January, April, July and October with each SAN issued covering a 3 month period of the DLE to MSAN programme When reviewing this example, communication providers are asked to note:  Tranche 1 will cover 4 months to align with the Pathfinder timescales proposed in the Migration proposal (issued 21/10/05)  Tranche 2 will then cover 1 month to align the quarterly SAN issuing programme  Each box equates to a one month time period  Any variation in phase length in the timeline (from those in the standard 18 month timeline) is explained on the right hand side of each Tranche

Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject to change. 3 21CN CP Interconnect Migration: Example Implementation Programme

Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject to change. 4 21CN CP Interconnect Migration: Example Implementation Programme Milestones ADMINISTRATION PHASE MILESTONES: HLSAN : The production by BT, and the issuing to the impacted CPs, of the HLSANs (High Level SAN) for those DLEs closing within the Migration Tranche. DSAN : The production by BT, and the issuing to the impacted CPs, of the DSANs (Detailed SAN) for those DLEs closing within the Migration Tranche. Technical Negotiations : Based on the DSANs issued, bi-lateral technical negotiations between the CP and their BT Technical Account Manager (TAM), leading to an agreement on the DLE to NGS traffic and physical transfer method(s) to be used for each CP route and E1 connected to the closing DLE. Cost Negotiations : Bi-lateral negotiations between the CP and their BT Commercial Manager (CM), based on the agreed DLE to NGS transfer method(s) to be used for each CP route and E1 connected to the closing DLE, leading to an agreement on any CP's SAN related costs. ACOs : The production and issuing of an ACO (Advanced Capacity Order) to BT, by either the CP or BT, for the transfer of the CP's traffic and physical interconnect to the NGS from the DLE, based on the method(s) agreed during the joint negotiations. PREPARATION PHASE MILESTONES: Orders : The production and the issuing of an order, by either the CP or BT, for the transfer of the CP's traffic and physical interconnect to the NGS from the DLE, based on the method(s) agreed during the joint negotiations. RFT : Orders placed will be progressed by BT up to Ready For Test (RFT) status

Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject to change. 5 21CN CP Interconnect Migration: Example Implementation Programme Milestones PREPARATION PHASE MILESTONES (CONT): Review: A joint BT TAM and CP review of the transfer method(s) and capacities agreed during the SAN negotiations. TRANCHE ALIGNMENT TIME: No activities are planned to take place in the period. It is required to align the SAN issuing quarterly Tranches with the DLE to MSAN programme months. TRANSFER PHASE MILESTONES: Traffic & Physical Transfer: DLE to NGS : The transfer of the CP's traffic and physical interconnect to the NGS from the closing DLE, together with any agreed post transfer testing. STABILITY PHASE: No Activities: No closing DLE to NGS CP Interconnect Migration activities are allowed to take place within this phase NETWORK FREEZE PHASE: Absolutely No Activities: Absolutely no closing DLE to NGS CP Interconnect Migration activities are allowed to take place within this phase. DLE TO MSAN PHASE: End Users Transfer - DLE To MSAN: The transfer, by BT, of end users from the closing DLE's concentrators to 21CN MSANs.

Consult21 Information is subject to change and is for discussion purposes only. Any dates/timings are the current anticipated timescales and may be subject to change. 6 21CN CP Interconnect Migration: MIME High Level Overview MIME is an internal BT system under development to manage a number of Transfer Engineering related activities - but primarily Interconnect Migration Key workflow management areas supported are :  Tracking overall programme progress  Scheduling of an individual's tasks  Tracking of task achievement & overall migration progress  Task & assignment jeopardy management  Cost tracking Key automation areas supported are :  HLSAN & DSAN production & issuing  TAM & CM to CP interaction  Shadow ACO & Order production  Interaction to existing BT OSS  Route & E1 provision & recovery  Route & routing data provision