New Bangkok International Airport Progress Information & Schedule Analysis KOICA(NESDB) FOR Air traffic Control Tower
INFORMATION OF NBIA’S CONTROL TOWER & NAVAIDS ● IMPLEMENTING AGENCY : Aeronautical Radio of Thailand Ltd. ( other government agencies) ● INVESTMENT BUDGET : 2,307 Million Baht ● SCOPE OF WORK ( including Design, Manufacture, Installation, Test & Commissioning Duration ) 1. Construction of ATC Complex : ~ Provision of surveillance system : ~ Provision of navigation aids : ~ Provision of aeronautical radio system 5. Provision of communications network : ~ Provision of flight data 7. Provision of airline services equipment 8. Air traffic operation and communications ● PROGRESS STATUS : Under bidding process as of Jun. 2003
Air Navigation System of IIA ATCT TRACON ASR/MSSR TVOR/DME LLZ/DME GP TDWR LLWAS
Meteorological Radar of IIA Surveillance Radar of IIA Surveillance Radar of IIA In case of NBIA Implementation by Aeronautical Radio of Thailand Ltd. Design & Construction & Test :Jun.2003~Jun.2005 In case of NBIA Implementation by Department of Meteorology Design & Construction & Test :Jan.2003~Jun.2005
Control Tower of IIA H = M CONSTRUCTION PERIOD INSTRUMENT & EQUIPMENT INSTALLATION PERIOD ~ ( 28 MONTHS) MAJOR FACILITIES & TEST ~ ( 8 MONTHS) - Structural Stability for Strong Earthquake : install. Of HMD - Structural Stability for Strong Earthquake : install. Of HMD - Perfect Stormproof Test for Violent Breeze at 60m/s - Perfect Stormproof Test for Violent Breeze at 60m/s
Duration CONSTRUCTION : 28 MONTHS DESIGN & BIDDING : 16 MONTHS Opening Date EQUIP INSTALL. & TEST : 8 MONTHS AIRPORT OPERATION READINESS : 6 MONTHS Incheon International Airport Control Tower Outcome 42 MONTHS Progress
Incheon International Airport Control Tower Outcome
Incheon International Airport Control Tower Outcome
Incheon International Airport Control Tower Outcome
Duration CONSTRUCTION : 28 MONTHS DESIGN & BIDDING : 16 MONTHS Opening Date EQUIP INSTALL. & TEST : 8 MONTHS AIRPORT OPERATION READINESS : 6 MONTHS Incheon International Airport Control Tower Outcome 42 MONTHS Progress
COMPARISON BETWEEN NBIA AND OTHERS MIDWAY Pre-cast DESCRIPTION NBIA INCHEONO’HARE Height (meter) Period Duration (150f) 78(260f) 94.10~ ~ ~’ Const.Method Reinforced 26 months 130 ‘03.5~’05.6 N/A AIR TRAFFIC CONTROL (ATC) TOWER
‘2000 IIA OPEN AIRPORT: 29 MAR AIR TRAFFIC CONTROL TOWER SCHEDULE COMPARISION BETWEEN NBIA AND IIA NBIA OPEN AIRPORT: 29 SEP EQP. INSTALL. & TEST CONSTRUCTION AIRPORT OPERATION READINESS DESIGN & AWARD AIRPORT OPERATION READINESS EQP. INSTALL. & TEST DESIGN & CONSTR. TENDER & AWARD (NOV. 02 ~ SEP 05) 20 MONTHS 6 MONTHS 3 MONTHS 16 MONTHS 28 MONTHS 8 MONTHS 6 MONTHS 36 MONTHS 26 MONTHS
THE ROLE OF CONTROL TOWER ● The control tower as the most important facility for air control is equipped with communication intelligence systems. ● All sorts of facilities such as control facilities play the most significant role for the safety of aircraft and passengers ● Without ATCT functions, we can’t do start up and commissioning the whole NBIA integrated system as airport operational readiness ● ATCT progress delay impacts directly opening date of NBIA