ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012.

Slides:



Advertisements
Similar presentations
New Radiation Safety Interlock System for the SPring-8 Accelerator Complex C. Saji, M. Toko, T. Matsushita, R. Furuta, H. Hanaki, S. Hashimoto 1), Y. Hashimoto,
Advertisements

Neutrinos from Stored Muons STORM Target Station Conceptual Design 15-April-2013 Kris Anderson Fermilab/Accelerator Division/Mechanical Support Department.
Main Injector Gap clearing kickers Phil Adamson (#) AEM 14th March 2011.
NuMI Target Pile Fan Repair Michael Andrews 3/15/10.
NuMI Radiation and Environmental Protection NBI th International workshop on Neutrino Beams and Instrumentation September 5-9, 2006 Mike Martens.
ANU Cooling Systems Karl Williams Fermilab Accelerator Division CD-2/3a DOE Review of NO A October 23-25, 2007.
1 Proton Upgrades at Fermilab Robert Zwaska Fermilab March 12, 2007 Midwest Accelerator Physics Collaboration Meeting Indiana University Cyclotron Facility.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
KICKOFF AS PRESENTED 6/17/11, SEE THIS WEEKS SCHEDULE FOP THE LATEST UPDATE Shutdown Shutdown ‘11.
NUMI NuMI Hot Handling Jim Hylen (FNAL) NBI02 March 13, 2002 Page 1 NuMI Target Hall Radioactive Component Handling NuMI Target Hall Utilizes Three Basic.
All Experimenters’ Meeting January 09, Accelerator Operation Summary Calendar Week # 51 NuMI Weekly Integrated Intensity 8.81E18 protons BNB Weekly.
A. Bross MTA RF WS August 22, Welcome MTA RF Workshop.
Sector 13 Canted Undulator Upgrade Hutch Modification Requirements ( )
Re-commissioning the Recycler Storage Ring at Fermilab Martin Murphy, Fermilab Presented August 10, 2012 at SLAC National Laboratory for the Workshop on.
The Tevatron Decommissioning Plans AEM 10/17/11 Paul C. Czarapata.
ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
NuMI Run II meeting Nov. 4, 2004 NuMI Target Hall Jim Hylen Page 1 NuMI Target Hall Status / Plan 8 slide introduction to target hall 9 slide list of status.
NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS Page 1 1 Infrastructure Review - W.B.S Water Systems Water Systems –Upstream.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
F MI High Power Operation and Future Plans Ioanis Kourbanis (presented by Bruce Brown) HB2008 August 25, 2008.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 1 Draft Schedule Beam off to Experiments 0000 Monday April 30 th Linac continues operations.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Proton Plan Director’s Review 8/15/06 Prebys 2006 Shutdown Eric Prebys, FNAL Accelerator Division.
All Experimenters’ Meeting November 03, 2014 Photo by Greg Vogel.
Ff NO A Accelerator Upgrades: Status Phil Adamson Fermilab
Accelerator Support and Maintenance Run 14. Maintenance Tomorrow AGS hrs CA Specific Jobs only. AGS hrs CA Specific Jobs only. RHIC.
NuMI NuMI Target Hall Air System Review Introduction July 30, 2003 Jim Hylen / FNAL Page 1 NuMI Target Hall Air System Review Introduction Air system for.
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Overlap of Project X and Beamline to DUSEL June 2, 2008.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
F NuMI Beamline Accelerator Advisory Committee Presentation May 10, 2006 Mike Martens Fermilab Beams Division.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
TD Help for Shutdown 2012 Preliminary, will be updated April 18, 2012.
Accelerator Issues Fermilab Antiproton Experiment Keith Gollwitzer Antiproton Source Department Accelerator Division Fermilab.
All Exp Mtg July 7, 2008 NuMI-MINOS Status Report – Laura Loiacono FAR DETECTOR: FD live time was 95.7% for cosmics last week (ROP7 problems reported at.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
Friday July 27, 2007 Page 1 Shutdown 2007 ES&H Enclosure Access  Linac Remains Operational until August 13 th  Booster RWP’s and enclosure access keys.
Proton Plan PMG 2/23/06 E Prebys 1 Proton Plan Status January Report Eric Prebys.
Main Injector Beam Position Monitor Upgrade: Status and Plans Rob Kutschke All Experimenters’ Meeting April 3, 2006 Beams-doc-2217-v3.
Status of the Accelerator Complex Keith Gollwitzer Antiproton Source Accelerator Division Fermilab 2009 Fermilab Users’ Meeting.
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.
July 15, 2013 Photo by Greg Vogel. Shutdown Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster.
All Experimenters’ Meeting September 23, Accelerator Operation Summary Calendar Week # 38 NuMI Weekly Integrated Intensity 4.57 E18 protons BNB.
August 2007 Booster RF Upgrades J.Reid Booster RF Upgrades West Gallery LCW modifications: – Headers in select locations to be upgraded by.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
All Experimenters’ Meeting November 25, 2013 Photo by Martin Murphy.
July 29, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Trying to.
Mike Andrews May 10, Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange.
All Exp Mtg May 5, 2008 NuMI-MINOS Status Report – Tingjun Yang FAR DETECTOR: 99.7% live time (wall clock) Everything was running pretty smooth NEAR DETECTOR:
March 7 th Shutdown Shutdown Begins: Monday morning, March 7 th :00 Beam OFF Safety System Testing 08:00 Rack out KRSS, switch MI house power to.
Mike Andrews August 30, Weeks 1-5 Activities Rad survey open to supervised access & re-core Install crane electronics & remove shield wall Retrieve.
09:00 Meeting Shutdown Update June 29 th 2015 Cons Gattuso AD Shutdown Manager.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
Muon Long Term Schedule August 15, µ Points to discuss What is the schedule What is the schedule Shutdown schedules Shutdown schedules How do we.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Maximum Credible Beam Loss in the Main Injector D. Capista January 26, 2012.
Friday 5/1/ meeting. I wish to lock in the power outage onTuesday 5/5/09 at the end of the 0930 lab scheduling meeting speak now or :
Mike Andrews August 17, Week 16 NuMI Activities Leak testing of DI bottles & Casks Complete all bottles & casks RAW Impulse line upgrade Finished.
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
Mike Andrews January 31, Weeks Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
News and brief overview of Beamline plans for the next few months
Hosting Orsay Walid KAABI
NuMI - Shutdown – Week 9 Horn 2 Repair – Successfully Tested the Repaired RAW Leak Drained and Refilled Horn 1 and 2 RAW Systems Changed Horn 2 DI Bottle.
J. Seeman Assistant Director for PPA/LCLS
Presentation transcript:

ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012

Accelerator and NuMI Upgrades April 30,2012 Cons Gattuso, AEM2 Recycler Ring, RR New injection line into RR New extraction line from RR New 53 MHz RF system Instrumentation Upgrades New abort kickers Decommissioning of pbar components Main Injector Two 53 MHz cavities Quad Power Supply Upgrade -Done Low Level RF System NuMI Change to medium energy beam configuration (new target, horn, configuration) Cooling & power supply upgrades

Big Picture 17 May 2010Cons Gattuso 3

NuMI Work Status Monday April 30 th –Horn and power supply test Ran System at the NoVA era sec rep rate successfully Tuesday May 1 st –Target Hall was repaired for Supervised Access…. Rad surveys done Crane electronics were installed Shielding wall removed Wednesday May 2 nd –RAW water system System drained Filter changed out DI Bottles removed 17 May 2010Cons Gattuso 4

NuMI Work Status Thursday May 3 nd –Drained glycol from TP chiller (900 Gallons) –Dehumidifier upgrade Disconnect cooling lines to dehumidifier coil box Started initial electrical work –Electrical work Install supplemental lighting and electrical services were added to add in the shutdown work. –Horn 2 work Started disconnecting Horn 2 RAW piping in Target Hall Removed strip line cage 17 May 2010Cons Gattuso 5

NuMI Plans For The Week Dehumidifier upgrade Re-pipe system Munters Coil & housing upgrades NOvA Cooling Coil Installation Work runs from 5/7 through 5/18 Provides additional cooling for TP and Chase air handling system Install new lighting & electrical service on top of and behind work cell Install Target Hall rail system Installation of the 3Q120 Quads at the Q113, Q114, & Q120 Transport and installation of Quads to retarget enclosure 17 May 2010Cons Gattuso 6

Main Injector Tunnel Work status Monday April 30 th –MI power supply tests Tuesday May 1 st –MI rad survey complete –Doors re-cored Thursday May 3 rd –A short tunnel access was complete to closes all RR and MI beam Valves Friday May 4 th - Monday May 7 th –Tunnel relamping 17 May 2010Cons Gattuso 7

This weeks plans Next week: Task specific accesses only Special approval will be needed for any tunnel before May 9th Monday, May 7 th Water Group accessing to layout MI-14 water work Wednesday, May 9 th Fire testing fire protection systems in MI/RR – NO ACCESS until completed (09:00 to 12:00) Accessing to clear MI-60 MVA Thursday, May 10 th Accessing to clear MI-60 MVA As Founds for 614 and injection region Power Supply isolation for MI-8 work Friday, May 11 th Staging equipment for following week General access begins Monday, May 14 th