Kitty Chan UC Berkeley architect Chad S. Green Stanford University Yuning Wang Stanford University engineer contractor owner Robert Alvarado Mission: To work together as AEC in creating a meaningful space for the users in 2010.
Site The site is at Central University in Los Angeles, California University of San Francisco is picked as the reference site.
Site Layout
Vision for 2010 Students and Faculty interfacing with computers in their daily functions in the department.
Design Alternates SQUARE TOWERS ZIGZAG SUNDIAL
Design Review – Construction Slanted columns difficult to install; precast members easier Masts expensive, difficult to install; expensive to excavate basement More connections due to zigzag shape; irregular formwork needed Economic design; good constructibility
Design Review – Engineer Torsion issues; long spans; no place to fit shear walls Long cantilever; low redundancy; large point load above auditorium Rigid & symmetric; issues with torsion Good lateral support; unchallenging design
Design Review – Architect Relates to religion, nature, and spatial Good interiors, interaction space Interesting exterior, atrium Uninteresting exterior, poor circulation
Preferred Alternate SUNDIAL
Exterior View morningnoonafternoon
Elevation Using surrounding context to define the building Reading the building from the inside East ElevationSouth Elevation
Basement Viewing the Mechanical Room Seeing the structure of the auditorium
Basement (cont’d)
1 st Floor Dual Usage –Auditorium –Hallway
1 st Floor (cont’d)
2 nd Floor Hallways as telescope
2 nd Floor (cont’d) BeforeAfter
3 rd Floor Faculty & Student Offices
3 rd Floor (cont’d)
Program Requirements Program Design
Program Requirements (cont’d)
Natural Ventilation Using the wind for natural ventilation for the building Cone serving as a greenhouse on the exterior layer
Solar Power Los Angeles Weather Solar Power for Daytime Electrical Use Skylights for Natural Lighting
Interaction with Architectural Program First Floor Auditorium Large Classroom
Interaction with Architectural Program Second Floor Small Classroom Computer Room
Interaction with Architectural Program Office Space Third Floor
Interaction with Architectural Program
Iterations – A E C Beams Floor Slabs Hanging from Beams A E A C E A C
Iterations – A&C Discussion on how HVAC will run through the building Location of Utility Floor –Top vs. Bottom
Iterations – A&E Dome Structure Layout Changed to Fit Architectural Program
Iterations – A&E Slanted Walls Caused Columns to Be Moved In
Northridge Earthquake 1994 6.7 magnitude 9,000 injured; 51 fatalities $44 billion in damages (costliest in US history) 29,000 buildings yellow- or red-tagged Steel SMRF experienced unexpected cracks
PHMRF System BENEFITS: Faster delivery time Increased safety Structure retains value
Typical Structural Members Floor Slabs: 8X20 Double Tee 50’ max span 2” topping Beams: 24X20 L-Beam 24X32 Inverted T-Beam 30’ max span Columns: 12X12 Interior 24X24 Exterior/Moment max M = 525 k-ft
Computer Analysis Earthquake Design – Weight of Structure, W = 4100 k Base Shear, V = 472 k Story Shear, Fx = 118 k Max Deflection = 1” Max M = 572 k-ft Max P = 486 k Max M = 852 k-ft Max P = 652 k
Computer Analysis Earthquake Design – Weight of Structure, W = 4100 k Base Shear, V = 472 k Story Shear, Fx = 118 k Max Deflection = 1” Max M = 572 k-ft Max P = 486 k Max M = 852 k-ft Max P = 652 k
Structural Details Steel Reinforcing in Dome Floor Slabs & Elevator Core Six #14 Bars 18” spacing Develop. Length = 72”
Structural Details Cantilever of Precast Double Tee Slabs
Structural Details Span of the Dome Structure 18” 20’
Foundation Sandy Soil Likely Low Water Table Earthquake and Liquefaction Max Column Axial Load = 486k Soil Bearing Capacity = 4ksf Footing Area = 120 sqft Footing = 11’ X 11’ Max Uplift Force = 118k
Load Paths
Construction Cost Total Cost –Present Value: $4,270,936 –2010 Value: $5,663,944 –3% over budget Structural System: $582,959 –72% over budget Site Work Exterior Structural System
Construction Schedule Mon. Sept. 6, 2010 Fri. May. 11, 2011 Jan. 31, 2011
Resource Usage in Erection
Construction Equipment Terrain Crane, 40 ton Backhoe Loader, 48 H. P. Dump Truck, 16 ton F. E. Loader T. M. 2.5 C.Y. Truck Gas Engine Vibrator Gas Welding Machine
Construction Sequence Cone is cast-in-place Construct cone first I. II.
Cone Construction
MEP Layout Solar Energy system –Saves energy costs during life cycle –Issue of heat loss Utility floor –Solves floor height problem –Saves life cycle cost of further expansion –Structural system + Wall: about $280,000 Horizontal Distribution
Structural System Evaluation Largely Precast Concrete –Saving labor –Few shear walls –Shipping cost: approximately $80,000 –Lead time: detail shop drawing, pre-casting –Re-stressing cables over life cycle Slanted columns in Cone
Team Interaction Whiteboard Sketches NetMeeting Videoconferencing Discussion Forum
Team Process Most iterations triggered by A C improved on being more vocal early on in design decisions E and C more reactionary than A A attempted to design with E and C in mind Although E and C were able to appreciate the goals of A and integrate well with one another, not yet able to think and design in A’s terms
Thank You Mentors!! Thank you to all mentors for their invaluable support and time investment in the PBL program and Central Team 2000! Robert Alvarado, CM Salter Assoc Scott Dennis, NBT John Hoeppner, Dillingham Builders Ron Hoyle, Pankow Builders Shilin Jiang, KL&A Greg Luth, KL&A Chuck Madewell, Habitat Bob Tatum, Stanford
Central University – Los Angeles, CA