US LHC Accel Proj Review 15-16 October 2003 Joseph Rasson LBNL Project Manager 1 LBNL Project Overview Joseph Rasson Jon Zbasnik Bill Elliott LBNL Presented.

Slides:



Advertisements
Similar presentations
24 Oct 2002 RFP Review1 DFBX Fabrication Activity at LBNL Jon Zbasnik LBNL.
Advertisements

1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Plans for 201-MHz Cavities Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 18, 2010.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
MICE Collaboration meeting at CERN March 28 – April 1, 2004 MICE Cooling Channel --- AFC Module work group report Wing Lau – Oxford.
Spectrometer Solenoid and RFCC Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
Cryo Capture Cavity II Progress Mike McGee April 6, 2005.
RF Cavity / Coupling Coil Module
NTOF11 Collaboration Meeting Non-Design Issues for the Mercury Jet Target P.T. Spampinato V.B. Graves T.A. Gabriel Princeton University April 29-30, 2005.
TD/MSD TORUS CMM PRODUCTION: OVERVIEW G. Velev Clas12 Torus CCM Production Readiness Review –Dec 4, 2013.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
LARG week 07/01 Paul Poffenberger University of Victoria Endcap Feedthrough Production at Victoria Status Summary.
TIS Review 13 Dec Bill Elliott IR ABSORBER STATUS1 Bill Elliott LBNL Presented at the TIS SAFETY REVIEW 13 Dec Berkeley,CA brookhaven - fermilab.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Collaboration Meeting at JLab, Virginia February 28, 2011.
ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
1 LHC-DFBX DFBX Production Readiness Review Project Overview Joseph Rasson LBNL October 2002, LBNL Brookhaven - Fermilab - Berkeley US LHC ACCELERATOR.
1 LHC-DFBX Shipping Specification Steve Virostek LBNL Presented at the DFBX RFP Review October 2002, LBNL Brookhaven - Fermilab - Berkeley US LHC.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
Key Design Issues and Recent Reviews Tom Peterson, Fermilab DFBX PRR, October 23, 2002 US LHC ACCELERATOR PROJECT brookhaven - fermilab - berkeley.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
1 LHC-DFBX Fabrication Oversight Plan Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab.
ATLAS Endcap Signal Feedthrough Project Status Report Pin carrier Procurement Summary Feedthrough Production QA/QC Shipment to CERN Reception Tests at.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #28 Sofia, Bulgaria.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Americas Cavity Specification C.M. Ginsburg (Fermilab) On behalf of the Fermilab cavity crew October 20, 2010.
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
MICE RF Coupling Coil Magnets Update Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory October 6, 2010 Sofia, Bulgaria.
HL-LHC Crab Cavity Review Debriefing Comments from LARP June 30, 2014.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
CMS Upgrade Workshop, FNAL, Oct 28-30, O.Prokofiev Update ME4/2 Chambers and Tooling A construction of new ME4/2 prototype at CERN Factory tooling,
DOE-QRT Review 12 Feb2004 Joseph Rasson LHC Project Update1 Joseph Rasson LBNL DOE LHC Quarterly Status Meeting at FNAL 12 February 2004 US LHC ACCELERATOR.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory Oxford, UK July 7, 2011 July 7, 2011.
Status of the Spanish contribution to CTF3 L. García-Tabarés, F. ToralCERN, 17/9/2006.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
MICE Coupling Coil Update Allan DeMello Lawrence Berkeley National Laboratory Illinois Institute of Technology June 17, 2013 June 17, 2013.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
Status of MICE RF for Step V’ (at LBNL) Derun Li Lawrence Berkeley National Laboratory December 6, 2014.
O. Kester, NuSTAR annual meeting, 27/02/2013
MUSE Task 5 Design and Construction of a Liquid Hydrogen Target.
MICE Coupling Coil Vacuum Vessel Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
Jan , 2008 LCLS Undulator Week Dean R. Walters 1 Vacuum Components Undulator System SH Lee, J Morgan, and D Walters.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
ELENA installation progress F. Butin / ELENA collaboration.
12 GeV Project Status Glenn R. Young 12 GeV Project Status
SPF MAG Quarterly Report – Feb 2015
Roadmap for triplet cryostats
Crab Cavities Contribution from the U.S.
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
LARP Phase II Secondary Collimator RC1
MLC Schedule Plan Proven in-house expertise and infrastructure for fabrication, assembly, and testing cryomodules Confident in our technical expertise.
Teleconference ACS – FREIA 31st October 2017
Support Structure Fabrication
2K CB FDR Overview:  Agenda, Charge, Review Process
Teleconference ACS – FREIA 20th February 2018
LARP Rotatable Collimators for LHC Phase II Collimation
Missile Defense Agency EVM Update
Teleconference ACS – FREIA 19th June 2017
UPPSALA UNIVERSITY_GERSEMI PROJECT
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 1 LBNL Project Overview Joseph Rasson Jon Zbasnik Bill Elliott LBNL Presented at the US LHC Accelerator Project DOE Review October 2003 FNAL brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 2 Outline  TAS-TAN Absorption  DFBX Large Cryogenic Procurement  DFBX Government Furnished Material LBNL Fabricated CERN Supplied Fermilab Fabricated  Fabrication Schedule  Fabrication Risk Analysis  Budget/Schedule Variances  Summary  Action Items from February, 03 Review

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 3 IR ABSORBER OVERVIEW-TAS The TAS consists of three major assemblies: Copper Clamshells Vacuum Beam Tube Alignment/support System

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 4 TAS Alignment Test Complete Mar, 03

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 5 First TAS Bakeout and Vacuum Leak Test Complete May, 03

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 6 Four TAS Assemblies are Completed and Ready to Ship Jul, 03

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 7 Subcontracted Shipping to HAAS Industries Jul, 03

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 8 TAS Beam Tube Final Pressure Test at Port of Oakland 10 Jul, 03

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 9 TAS Bagged and Sealed at Port of Oakland 24 Jul, 03

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 10 TAS Crated at Port of Oakland 30 Jul, 00

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 11 Four TAS Containerized and Shipped 30 Jul, 03

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 12 TAS Summary  TAS arrived at CERN on 19 Sep, 03  Passed visual inspection of crates and shock watches  TAS Acceptance Specification is in the approval process  TAS design, travelers and engineering safety files are being prepared to be uploaded to CERN EDMS  Now ready for acceptance tests at CERN

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 13 IR Absorber Overview - TAN The TAN consists of three major assemblies; 1.Absorber box 2.Beam tube, 15 ft long 3.Steel shielding and marble headstone 33 Tons total weight Absorber Box (includes the Beam Tube) Steel Shielding Beam Tube

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 14 Vacuum Chamber E-Beam Weld at Sciaky in Chicago Land Sciaky developed E-beam weld procedures, tooling and fixturing Completed weld test samples Total of 9 welds per tube Four beam tubes welded and vacuum leak checked at Sciaky

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 15 First TAN Beam Tube Arrived at LBNL 8 Jul, 03

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 16 TAN Beam Tube Weld Check with Boroscope

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 17 First TAN Bakeout and Vacuum Leak Test 26 Jul, 03  Two beam tubes passed initial vacuum leak test and proceeded to bakeout and final vacuum leak test in Bldg 60  Two TAN assemblies are completed and ready to ship to CERN

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 18 E-Beam Weld Issues  The remaining two beam tubes had a leak rate of~5x10 -7 atm cc/sec He at the same weld location  One of the leaky beam tubes had a porosity leak rate of ~ 2x10 -7 atm cc/sec He  Leaky beam tubes shipped back to Sciaky for repair  Sciaky’s large E-beam weld machine has been down for 3 weeks  We are in communication with Sciaky and expect to get schedule priority once the E-beam weld machine is back on line  In the meantime, we issued labor work stoppage at LBNL until we receive the remaining two beam tubes  It takes 2.5 weeks per beam tube for UHV cleaning, vacuum leak test and bakeout

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 19 TAN Summary TAN alignment and jack motion tests were completed Bakeout system has been assembled and is ready to go Two TAN assemblies are completed and ready to ship to CERN Remaining two beam tubes need weld repair at Sciaky and should be shipped to LBNL by 22 Oct, 03 TAN is behind schedule. Expected new shipping date is 15 Dec, 03 Required date at CERN is Jul, 04

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 20 Cryogenic Distribution Boxes, DFBX

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 21 DFBX Fabrication and Integration Plan  Major cryogenic procurement scope included: Fabrication of components for 8 DFBXs Integration of GFM components (very extensive list) System assembly and test Crating and shipping to CERN  Developed a detailed fabrication and procurement/RFP strategy  Provided the subcontractor with detailed design to reduce fabrication uncertainties  Generated over 800 engineering drawings, 18 engineering and safety notes and 9 interface specifications  Had continuous communication with the potential vendors to facilitate technology transfer and to solicit design input prior to releasing the RFP

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 22 DFBX Procurement Status  RFP was released 17 Nov, 02 to PHPK and MTM  Two strong technical proposals were received 4 Feb, 03  An intense proposal review process and work scope adjustment ensued to lower bids  Released a request for BAFO on 3 Mar 03, two bids were received on 12 Mar, 03, and awarded a $2.3 M contract to MTM on 22 Mar, 03  Received excellent support from LBNL’s Procurement Department to meet our tight schedule constraints  Fabrication activities are progressing very smoothly and are ahead of schedule and on budget

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 23 Fabrication Oversight Activities  Approximately 2 FTEs are dedicated to fabrication oversight activities  Change Control Procedures are in place and are followed closely  Weekly teleconference meetings and almost weekly visits to MTM Review progress and assist in resolving fabrication issues Insure that DFBX is given the appropriate scheduling priority Supervise the transfer of GFM to the vendor Witness critical assembly processes and inspection tests Manage change control process  FNAL is providing valuable oversight support Tom Peterson is at MTM almost every week Oscar Lira inspects material/parts prior to paying invoices

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 24 DFBX Fabrication Progress  MTM fabrication approach: buy and fabricate parts for all eight DFBXs simultaneously  Subcontracted thermal shield fabrication  Material for all parts have been purchased  Great progress on machining of all common parts  All LHe vessels machining is near completion  Machining of the vacuum vessel has started  Two assembly fixtures have been designed and readied for assembly  Images of the fabrication progress can be viewed at:

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 25 Eight LHe Vessels Nearly Completed

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 26 Vacuum Vessel Formed Top Plates

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 27 VV Top Plate on the G&L Machine

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 28 Quadrupole Diagnostic Assemblies

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 29 Two Assembly Fixtures Completed

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 30 GFM Fabrication Bus Duct/Lambda Plate MQX1 to power quads & correctors 4 main leads, 24 corrector leads 8 assemblies required MBX1 to power D1 dipoles 2 main leads 4 assemblies required

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 31 MQX1 Fabrication Status (Oct 15)  Seven MQX1 Completed  No. 8 MQX1 Ready for Electrical Test  No. 9 MQX1 Ready for Weld Closeout  Plan to ship to MTM by end of Oct 03 85% Completed

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 32 Beam Tube Fabrication Status  All pieces machined for 8 assemblies  2 Assemblies are completed  All 8 assemblies plan to ship to MTM by end of Nov, 03 Complete Beam Tube Assemblies 60% Completed

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 33 HTS Leads  ~$730k procurement with Pirelli, UK  All 40 leads shipped to Fermilab  Fermilab test rate averages 4 leads per month  Testing status as of Oct 15: 12 leads are cold tested and suitable for use 4 leads are cold tested and must be repaired (wiring problems) 7 leads need repair before they can be tested (external leaks in elec. connector) 17 leads remain to be checked & cold tested Pirelli’s engineer will visit Fermilab in Nov, 03 to assess repair tasks No schedule impact is foreseen

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 34 Vapor Cooled Lead Status  ~$727k procurement contract with AMI  Shipment is in eight sets, each consisting of: 1 each 120 A, 10 Lead Assembly 2 each 600 A, 6 Lead Assembly 1 each 600A, 2 Lead Assembly  One Set received at MT&M Aug 29, 03  Expected near-term shipping to MTM Sets 2 & 3 on Oct 17, 2003 Sets 4 & 5 on Oct 31, 2003  No schedule problems are foreseen 120A, 10 Lead

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 35 LBNL-Provided Bellows  LBNL is providing 6 inch bellows to MTM Spec was changed to provide perforations in outer 2 plies of cryogenic bellows $35k contract was awarded to American BOA Award Date 5/5/ Each Type I (with perforations) 45 Each Type II (without perforations)  All 45 Type II’s and 45 Type I’s are at MTM  The balance of Type I will be be shipped to MTM in early Nov, 03

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 36 CERN-Supplied Hardware  LHC-PMO is actively supporting our effort in getting CERN’s commitment to provide GFM hardware  Thermometry Items: need date Nov, 03 All thermometers are at LBNL  36 long Cernox and 8 short Cernox “Pipe Elements” to connect thermometers are partially on hand  Electrical Signal Connectors: need date Feb, 04 CERN is ready to send connectors  LHe Level Sensors: need date Jan, 04 CERN has recently agreed to supply the sensors. Will to place order with supplier  Taylor Hobson tooling balls and target holders: needed date Mar, 04 CERN is ready to ship directly to MTM

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 37 Magnet Instrumentation Conduits at Fermilab  Magnet Instrumentation conduits will be fabricated at Fermilab  Prototyping is complete, material is procured and assembly started  Should ship to MTM in Dec, 03

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 38 DFBX Shipping Schedule  MTM is slightly ahead of their own schedule….  Built in schedule contingency to complete first box  GFM delivery to MTM is on schedule  Shipping date of last box is achievable but tight

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 39 DFBX Fabrication Schedule (GFM) MilestoneCompletion Date Ship GFM from LBNLNov, 03 Ship GFM from FNALDec, HTS Lead from PirelliAll shipped to FNAL Test and Repair HTS Leads Apr, 04 Ship Vapor Cooled Leads from AMIDec, 03 Ship 6” Bellows from BOAOct, 03 Ship CERN Supplied MaterialDec, 03 (need to confirm Liq. level sensor)

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 40 DFBX Fabrication Schedule (MTM) MilestoneCompletion Date Complete Machining of 8 LHe VesselsOct, 03 Complete Machining 2 Top Plates Oct, 03 Receive TP Copper Shield from SubOct, 03 (3 weeks behind schedule) MLI FabricationDec, 03 DFBX-G Top Plate/LHe Vessel AssyJan, 04 DFBX-G Complete Piping Assembly Jan, 04 Insert Power Leads and Complete Elec AssyFeb, 04 DFBX-G Assy CompleteMar, 04 DFBX-G Test Complete & Ready to ShipApr, 04 DFBX-D Ready to ShipJun, 04 DFBX-A Ready to ShipSep, 04 DFBX-H Ready to ShipNov, 04 DFBX-E Ready to ShipJan, 05 DFBX-F Ready to ShipMar, 05 DFBX-B Ready to ShipMay, 05 DFBX-C Ready to ShipJul, 05

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 41 Project Risk Analysis and Impact Absorbers: TAS – No Risk TAN – damage to one beam tube: 2.5 mos. sched. slip & $45k cost increase DEFBX: DFBX-G assembly problems: 2 mos. schedule delay & $50k cost increase DFBX-G test problems: 1 mo. schedule delay & no cost increase 7 DFBXs assembly/test problems: 4 mos. delay & $100k cost increase DFBX Total Impact: 7 months schedule delay and $150k cost increase (Jim, we need to talk about this and see how you would like it to be presented)

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 42 The LBNL CV to end Aug 03 is k, the SV is k (Overheads broken out)

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 43 The LBNL CV to end Aug 03 is k, the SV is k (Overheads rolled into tasks)

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 44 Status of LBNL CVAC in ASk$ (Overheads broken out)

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 45 Status of LBNL CVAC in ASk$ (Overheads rolled into tasks)

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 46 The LBNL CV to end Aug 03 TBD

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 47 Status of LBNL CVAC in ASk$ (EAC based on Jul-03 ETC adjusted for Jul & Aug ACWP) TBD

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 48 Summary  DFBX

US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 49 Recommendations from February 2003 Review 1.Continue aggressive pursue of the feedbox contract 2.Provide technical support to the vendor after award to maintain the schedule (and vendor efficiency) 3.As currently planned, deliver the GFE (GFM) this FY 4.Finalize DFBX acceptance criterion with CERN by end of April-03 5.Identify and obtain PMO and Lab management buy in, prior to issuing award, for two or three fundamentally full-time cryogenically experienced individuals to aggressively deal with DFBX procurement tracking activities for project duration