10-07-2003EE planning meeting Lucie Linssen 1 CERN EE regional centre and Dee assembly plans Dee assembly TA3, not for EE Supercrystal regional centre.

Slides:



Advertisements
Similar presentations
Design Items and Tasks for pol. 3 He Remain design items: Support structure Main support Tube/oven (90% complete) Temp. support in the target lab Target.
Advertisements

ECAL End Cap Schedule issues Justin Greenhalgh This presentation will be at under EE356.
CMS-UK Oversight Committee 17/5/04 D.J.A. Cockerill - RAL 1 The CMS ECAL Endcaps Crystal ECAL Endcap Calorimeter (EE) Preshower EE EE crystals.
CMS-UK Oversight Committee 18/11/03 D.J.A. Cockerill - RAL 1 The CMS ECAL Endcaps Crystal ECAL Endcap Calorimeter (EE) Preshower EE.
Lyon Gantry Status TEC meeting Dec D. Contardo Module production in Lyon Rigidifier test on R4 Frame tolerance effect on assembly plates Short term.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
EMCal Meeting CERN – July 2 nd 2007 LPSC Status 1 J-F Muraz LPSC Status LPSC Status.  Assembly Hall. - Removal starts and is in progress. - Main infrastructure.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
MM mechanical prototype Work progress at CERN MicroMegas General Meeting, CERN, 5-6 November
DATA PRESERVATION IN ALICE FEDERICO CARMINATI. MOTIVATION ALICE is a 150 M CHF investment by a large scientific community The ALICE data is unique and.
WP2: Detector development Summary G. Pugliese INFN - Politecnico of Bari.
G.Barber - Imperial College London - EE Workshop March EE Dee Assembly Contents:- Area Manipulator Future Plans.
TGC Big wheel Sector assembly plan Tatsuo Kawamoto ATLAS workshop 2005.
Status Brussels GANTRY Ê Assembly of R3 modules (36 modules) 4 precision of the modules 4 problems with DataBase (not adapted for single sensor modules)
J A Hill – EID RAL 1-2 September EE End Cap Mechanical Design ECAL EE End Cap Engineering CMS-UK Collaboration Meeting Brunel University September.
LAV construction status Matthew Moulson (Frascati) NA62 Photon-Veto Working Group Meeting CERN, 27 May 2009.
EE and SE Installation Wolfgang Funk - CERN CMS 11/9/ ) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.
Thoughts about the MQXF development plan P. Fessia Thanks to discussions within the MDT section (P. Ferracin, J. C. Perez, E. Todesco, P. Ferracin), L.
CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000 A.B.Lodge - RAL 1 ECAL End Cap High Voltage Cards and 2000 Electrical/Thermal Model. Progress on.
ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
G.Barber KEK Test Beam Update, Berkeley 9 Feb KEK Test Beam – Tracker Progress Contents:- Station Space Frame Light Guide Map Station Connectors.
ISOLDE: Status report building th ISCC meeting CERN, 22 October 2013 Maria Borge, Erwin Siesling.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
M. Gilchriese Sectors, Rings, Frame Assembly and Installation July 18.
MM detector construction One or several modules per sector considerations.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
Space, labs & testing equipment Paolo Petagna Meeting on CO 2 Cooling CERN 04 February 2015.
ECAL – EE Design Status Presentation 19/7/06 D.J.A. Cockerill - RAL 1 EE Design Status D Cockerill CERN 19 July 2006.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
Baby MIND coil modules assembly the aluminium folded strip solution 1 Alexey, Philippe, Gabriella, Helder, Herman Baby Mind Magnet CERN June.
BNL Role In ITK 1.Current R&D Roles 2.Proposed Production Role 3.Activities now until TDR (early 2017) 4.Resources and Infrastructure 5.Personnel 1 D.
CMS Experiment at the LHC, CERN Date Recorded: :21 CET Run/Event: / Candidate Collision Event Report from Belgium Michael Tytgat.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
ECOOL Meeting 03/26/10 1 Low-E cooler baseline decisions: 1.FNAL’s cooling section “as is” – with weak solenoids, correctors, etc. (to prevent over focusing.
Hybrid panel heated plate study Currently the curing of the ASIC glue for the hybrid panels are done at room temperature. This is a study to determine.
CERN adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of Production of support panels - Things to be settled.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
ATLAS Pixel Detector July 2003 SC Pixel Meeting N. Hartman LBNL 1 Pixel Support Tube WBS Santa Cruz Cost Workshop July 9, 2003.
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
Upgrade week Apr10 AB CMS assembly & lab areas: future External constraints : entire 3000m 2 CMS area in ISR destined for rad material treatment entire.
ECAL Plenary 27/2/07 D.J.A. Cockerill - RAL 1 Status of the CMS ECAL Endcaps ECAL Plenary, 27 Feb 2007 D Cockerill  VPTs  Electronics and Integration.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
CMS-UK Oversight Committee 17/11/06 D.J.A. Cockerill - RAL 1 The CMS Electromagnetic Calorimeter UK Responsibilities Procurement and testing of VPTs Design.
Progress on Stave assembly tooling Stephanie Yang (Oxford) WP4 meeting at Liverpool University, 13 th November 2014.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
Tracker cooling plant refurbishment Project status Revised plan Financial impact.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
Engineering Division Transition to Production E Anderssen.
Magnetized Beam LDRD: Design Tasks February 19, 2016.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
1.I interaction with VakuumPraha using basic drawings. We made a deal for 19'310 EUR + tax for two vacuum chambers plus the compensation system, we provide.
Kitakami Side AHCAL Assembly or anywhere in any detector.
Florian Buchsteiner (HEPHY Vienna)
Stator Plan & Schedule Chris Booth 2nd March 2009
Resource Loaded Schedule and Budget Profile
CSP 25th November 2010 Technical agreement number 3: overview
BSS Prep work at CERN and Acceptance of Parts
INSTALLATION SEQUENCE
Production and commissioning of the 2nd BGC
UK CMS Oversight Committee Mtg
Type 2 Supercrystal Type 1 Supercrystal
PROGRESS on EE VPTs, Dees D Cockerill
East Hall under construction
Polarized 3He target installation
Presentation transcript:

EE planning meeting Lucie Linssen 1 CERN EE regional centre and Dee assembly plans Dee assembly TA3, not for EE Supercrystal regional centre

EE planning meeting Lucie Linssen 2 Dee and Reg. Centre lab in B m2 for regional centre / 120 m2 for Dee lab Space is presently being emptied C. Detraz is working on plans for setting-up of walls, roof, electricity, water, etc Plan to finish the space (real estate part, not tooling) for February 2004 ~100 kCHF needed for this lab (real estate part)

EE planning meeting Lucie Linssen 3 Dee lab Our objectives for various Dee lab equipment: Supercrystal manipulator IC responsibility, valid DALMEC solution found Probably deliverable ~ February 2004 Equipment for Dee dry mount Tooling for gluing of cooling tubes Pressure test equipment of cooling tubes Tooling, if any, for mounting of back plate + ring flange Target date : February 2004

EE planning meeting Lucie Linssen 4 Dee lab Modified OPAL frames Drawings ready => ~November 2003 Price offers => January 2004 Frames ready => May 2004 Further Dee lab tooling needed Dee lab test equipment: RAL/Saclay responsibility Further jigs, storage infrastructure, etc, to be defined Target date ~August 2004

EE planning meeting Lucie Linssen 5 Production rate for Dee assembly Our objective is: Have the Dee lab ready for SC mounting from August 2004 onwards 2 Dee’s are placed at the same time: 1 Dee for SC mounting, 1 Dee for mechanics mounting Production rates: Mount 4 SC per day => 40 days per Dee Various mechanics/cooling mount => 30 working days Total 70 working days for Dee #1 ~60 working days for Dee 2,3,4 each (but partly in parallel) We assume that we receive ~10 SC early, to test the procedures

EE planning meeting Lucie Linssen 6 Objectives for regional centre Assembly of full and partial SC in the same Regional Centre lab Collaborate with RAL and Russian labs to set up the tooling Try to find solutions to do part of the assembly (like end-stops) prior to arrival of crystals Objective for production rate: 10 SC per week (mixed full/partial) (production rate 50% during first ~2 months) Objective to have Regional Centre ready for receiving the first crystals in ??? August 2004 ……….Depending on help from outside TA1 group Cruising speed ~4-6 months later

EE planning meeting Lucie Linssen 7 Manpower for production Regional centre manpower estimate Assembly: ~4 persons Supervision: 1 physicist + 1 technician Dee lab manpower estimate Assembly: ~3 persons Calibration system mount: persons from Saclay Supervision: 1 physicist + 1 technician Of the above: TA1 will provide 2 technicians (supervision)

EE planning meeting Lucie Linssen 8 What we need to meet objectives Sufficient financial funding for the various tasks 1 additional designer + Daniel Lacroix until end additional mechanical technician (Russia?) throughout 2004 (to help building tooling etc.) Manpower for “assembly” tasks (see previous slide) Physicists for Regional Centre and for setting-up test equipment Enough Crystals to build ~10 supercrystals at CERN in 2004 Caveat: Dry mount of major mechanics + Dummy Dee’s + Precabling + E0’ test beam need to be done during the same period