August 05, 2013
Startup 2013 Machine Status: Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster Main Injector Startup and Tuning
Power Outages PS3 Power Outage Oil Switch Replacement Impacts PS3, PW5, & PC3 Run on generator for ~1 week Connect generator Monday, July – 1000 Disconnect generator Friday, August
Power Failures Feeder 46B Wednesday, July Impact – Possible F0 ventilation system Fault located between P71 & F4 Further isolation and repairs necessary
Kautz Road SubStation Status MI backfed from Master SubStation ○ Using Feeder 45 for MI conventional power which is normally T85 on KRS We ordered 6+ new surge arrestors (4.7k each) from Hubbell and they were delivered on Friday, July 26 th Schedule: (Weather Dependent) ○ Monday, August 5 th replace T85 surge arrestors No machine impact (In Progress) ○ Tuesday, August 6 th replace T87 surge arrestors No beam during work 8-10 hours After replacement, test both T85 and T87 There will be a 20 minute MI conventional power outage to remove the backfeed, not scheduled.
MI Startup Activities (~1 Week) Turn on power supplies and establish ramps Establish 8 Gev beam Match MI8 line lattice with IPM Tune abort Gev Establish 120 Gev beam Smooth orbits up the ramp Tune abort 120 Gev High field Orbit smoothing (quad moves) (Have data for 1 st ) Requires tunnel access (2x8 hrs) Calibrate tune table MI8 line lattice matching (1 st of 2 passes complete) Dedicated beam study Extraction line tune up (NuMI) (Attempting extraction) Tune up for operation Deliver low intensity beam to NuMI beam line for target scans Estimated to take an additional week after MI is tuned up for operations
Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations ScheduleOperations Schedule Direct link to schedule -
We have removed all of the antiproton equipment, which comes to over 1,400 feet of beamline components. o Electron cooling removal o Stochastic Cooling tanks removal from the 200 and 100 tunnel locations o Decommissioned the two Recycler Pbar injection and extraction lines (~1,000 ft. of beam line components). o The A150 Beam line was decommissioned (~800 ft. of beam line) More than ~1.3 Million feet of cable have been pulled to support the new transfer lines and instrumentation upgrades. o ~500,000 feet was a complete replacement of the Recycler BPM system o ~700,000 feet of new cabling for instrument cabling o IPM’s, Toroid's, DCCT’s, Multiwires, Schottkies, o ~10,000 ft. of RF cabling o ~10,000 ft. of 500 MCM cable o ~12,000 ft. of 350 MCM cable o ~25,000 ft. of correction element cables o ~6,000 ft. of radiation damage cable o ~ 25,000 ft. of kicker system cables We have installed a new transfer lines; a new Injection line into the Recycler and a new transfer line out of the Recycler Ring into the Main Injector o New injection line spans from the MI-8 line Q848 location to the Recycler Q104 location o New extraction line spans from Recycler Q230 to Q308 in the MI
Approximately 590 tons of material has been moved o ~ 40 Tons of lead blankets were installed to reduce the radiation levels to reasonable levels such that work can be completed (~25 tons in the MI30 straight section, ~5 tons in the new injection line and ~10 tons in various other locations around the ring. o Installed 3 shielding walls ( 2 for MI-31 stub and 1 at the 304 tunnel location ~ 20 tons each) o ~490 Tons of magnets moved o 3 ILAM we moved/relocated o 6 3Q120 magnets were removed from the A150 line reworked and reinstalled in the NuMI beam line to replace existing magnets o 1 MI wide aperture Quad was relocated o 1 new Wide aperture C Magnet was installed in the MI abort line o ~40 20 inch Quads were removed from the RR30 Cooling insert o 3 ADCW were installed ( main vertical bend Magnets) o Entire Ecool Cooling section and return line were removed o inch Quads were installed in the RR 30 section o inch Quads were installed in the new RR extraction line o inch Quads were relocated/installed in the RR injection line o Removed/installed/relocated a total of 14 cavities o 2 old RR RF cavities/6 MI coalescing cavity/ 2 MI studies cavities/ 2 new MI RF cavities and 2 new RR cavities o ~30 tons of stands and misc. parts/components were removed and or installed
Keeping true the Recycler name, we are reusing ~70 percent of the instrumentation, ~30 percent of the vacuum components ~85 percent of the magnets A completely new 53 MHz RF cavity system was installed into the Recycler o 2 New RF cavities were installed a place holder for a third o Relocated and repurposed the 3 existing Recycler wideband RF cavities into a damper system. A complete rework of the Recycler Abort system to allow full turn proton abort along with gap clearing. 5 Gap clearing kicker and 2 new Full turn kickers were relocated from the Main Injector to the Recycler The RR30 straight section was rework from a cooling lattice back to a standard FODO lattice ~45 Recycler 20 inch quads were removed ~900 feet of beam pipe was removed and reworked for the new Lattice configuration New insert was prepped for 2.5 MHz RF cavity system to be installed in the Recycler region. Relocated radiation sensitive equipment from the MI/RR 30 straight section to minimize future radiation dose to equipment and Technicians. MI and RR Coasting Beam safety system MI and RR DCCT’s RR schotkies Installed 2 new 53 MHz in the MI Relocated 4 RF cavities to make room