KAGRA Roadmap and Progress Evaluation Assessment S.Miyoki  M.Ando 2012/7/30.

Slides:



Advertisements
Similar presentations
Project management.
Advertisements

Step by step guide.
LCGT Program Advisory Board (June , Kashiwa, Chiba) On behalf of LCGT special working group Masaki Ando (Department of Physics, Kyoto University)
©Ian Sommerville 2004Software Engineering, 7th edition. Chapter 5 Slide 1 Project management.
4. 2Object-Oriented Analysis and Design with the Unified Process Objectives  Explain the elements of project management and the responsibilities of a.
Chapter 5: Project Scope Management
Development and Quality Plans
The R&M Task Group mandate is to: Develop specific recommendations on how social housing project reporting and monitoring could be improved and made more.
 A project is “a unique endeavor to produce a set of deliverables within clearly specified time, cost and quality constraints”
Burst noise investigation for cryogenic GW detector TITECH NAOJ Daisuke TATSUMI 2nd Symposium ‐ New Development in Astrophysics through Multi-messenger.
(Facility) Support - LCGT Handy Man - The definition of “Support” is now under construction. Many missing-tasks will be delivered to the support group.
Software Engineering Chapter 15 Construction Leads to Initial Operational Capability Fall 2001.
SEO report _SAITO 1. Overall schedule of iKAGRA installation/commissioning change to Michelson Interferometer 2. Scheduling of daily works for installation.
4th Phase : 4th Phase : CONTROL Why is control necessary? Because:  People make mistakes  External factors can have impact on the project  Requirements,
OSF/ISD Project Portfolio Management Framework January 17, 2011.
Improvements to Service Provisioning Platform Deployment Process Master’s Thesis – Matti Jylhä Supervisor: Professor Jorma Jormakka.
Chapter 4 The Project. 2 Learning Objectives Third phase starts after a contract is drawn up and ends when the project objective is accomplished; final.
Cryo-payload Kazuhiro Yamamoto Institute for Cosmic Ray Research
Information Systems Development. Outline  Information System  Systems Development Project  Systems Development Life Cycle.
27/Aug./2015 KAGRA f2f meeting N. KIMURA High Energy Accelerator Research Organization, KEK Progress status of Cryogenic System at KAGRA site.
Takanori Sekiguchi ALPS Report, Dec. 26th, 2013 Prototype Test of Type-B 1 Takanori Sekiguchi KAGRA F2F MEETING Feb
ICT Standards and Guidelines The Structure of the Project Akram Najjar CNSI – Senior Consultant Director of InfoConsult.
Summary of Suspension Configurations Yuta Michimura Department of Physics, University of Tokyo March 18, 2015.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
Optical Levers Layout and Cabling Yuta Michimura, Yuya Kuwahara Ando Group Department of Physics, University of Tokyo November 19, 2015.
Configuration Management and Change Control Change is inevitable! So it has to be planned for and managed.
1 Project management. 2 Topics covered Management activities Project planning Project scheduling Risk management.
Mark McKinnon NSF Mid-Project Review May 11-12, Baseline Project Definition Mark McKinnon Project Manager.
Project management 1/30/2016ICS 413 – Software Engineering1.
Aug. 2, 2010 Proposal for Creating New Task Force - To Develop 7-year Scenario for LCGT - Ichiro Nakatani Project Manager, LCGT 1.
Vibration Isolation Subsystem KAGRA face to face meeting (31 July, 2012) R. Takahashi (ICRR), K. Yamamoto (ICRR), T. Uchiyama (ICRR), T. Sekiguchi (ICRR),
1 Kazuhiro Yamamoto Institute for Cosmic Ray Research The University of Tokyo KAGRA external review (Cryogenic payload) 18 April 2012.
1 Cryogenic payload is not a simple system. We need cryostat to test cryogenic payload performance. 1/4 cryostat will be prepared in Kashiwa campus. 1/4.
Development Project Management Jim Kowalkowski. Outline Planning and managing software development – Definitions – Organizing schedule and work (overall.
O. Kester, NuSTAR annual meeting, 27/02/2013
 Overview of Project management. ◦ Management. ◦ Project Management. ◦ Software Project Management. ◦ Project(Dimensions, Characteristics, Complexity,
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Overview of iLCGT & bLCGT Kazuaki Kuroda LCGT Collaboration F2f meeting 27 September, 2010.
Information Systems Development. Outline  Information System  Systems Development Project  Systems Development Life Cycle.
Performance test of KAGRA cryostat at site
CERN Construction Planning and Scheduling (LHC installation)
Main Interferometer Subsystem
KAGRA用防振装置の開発 VIII Configuration Sensors and Actuators
Performance test of KAGRA cryostat at site
Yuta Michimura Department of Physics, University of Tokyo
Systems Analysis and Design
Vibration Isolation Systems
Interferometer Design for bKAGRA Phase 1 and Beyond
Systems Analysis and Design
Interferometer Design for bKAGRA Phase 1 and Beyond
Interferometer Design for bKAGRA Phase 1 and Beyond
Interferometer Design for bKAGRA Phase 1 and Beyond
Interferometer Design for bKAGRA Phase 1 and Beyond
Commissioning Procedure for bKAGRA Phase 1 ( )
Commissioning Procedure for bKAGRA Phase 1 ( )
Commissioning Procedure for bKAGRA Phase 1
Commissioning Procedure for bKAGRA Phase 1
Commissioning Procedure for bKAGRA Phase 1 ( )
Yuta Michimura Department of Physics, University of Tokyo
Status of KAGRA Yuta Michimura on behalf of the KAGRA Collaboration
Commissioning Procedure for bKAGRA Phase 1
Status of KAGRA Yuta Michimura on behalf of the KAGRA Collaboration
Commissioning Procedure for bKAGRA Phase 1
Interferometer Design for bKAGRA Phase 1 and Beyond
Development of vibration isolation systems for LCGT VII
KAGRA – 3km Cryogenic Laser Interferometer
KAGRA ISC Electrical Components Layout
M. Kezunovic (P.I.) S. S. Luo D. Ristanovic Texas A&M University
Yuta Michimura Department of Physics, University of Tokyo
Presentation transcript:

KAGRA Roadmap and Progress Evaluation Assessment S.Miyoki  M.Ando 2012/7/30

Outline Introduction Updated KAGRA Roadmap KAGRA Progress Chart (KPC) as milestones according to bottom up plans KAGRA Progress Chart Evaluation Summary F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

Update Roadmap - Ando’s Ext.Rev Presentation- We Updated the KAGRA Roadmap. Mainly because of delay in the excavation schedule. It is regarded as a good chance to refine the schedule. Recent some budget status might require minor changes. Roadmap special working group was held chaired by M.Ando We made iteration between the project constraints and the bottom-up plans submitted from subgroups. Open discussions in the collaboration were done -> Finally, this recommendation was approved by EO. F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

KAGRA Roadmap (ic1) F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Tunnel Excavation(14/3) FPMI (15/12) Vacuum(15/3) DRMI (16/9) Type-A Cryo(16/9) RSE(17/8) Cryo-RSE(18/3) Tuning And Observation Sapphire Test mass preparation(16/3) b-KAGRAi-KAGRA Training for km-scale IFO. Sorting out the problems involved in KAGRA Short observation will be done Introduce Full Type-A SAS, Cryogenic and RSE Technique. Realize the targeted sensitivity and observation. 12 ic1 phase

Tunnel Excavation and FAL Construction F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Tunnel Excavation Power line, water line, air humidity conditioner, network installation Clean room construction North Direction Mozumi Tunnel GW Atotsu Tunnel From 12/5 From 12/6 till 14/3 GW Office (2012/08) 30 deg Y arm X arm

KAGRA Roadmap (ic2) F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Tunnel Excavation(2014/3) FPMI (2015/12) Vacuum(2015/3) DRMI (2016/9) Type-A Cryo(2016/9) RSE(2017/8) Cryo-RSE(2018/3) Tuning And Observation Sapphire Test mass preparation(16/3) b-KAGRAi-KAGRA 12 ic2 phase

Vacuum and Laser Stuff Installation 1 F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Both Arm and IY*, EY* installation Laser, MC*, IFI, IMM installation No Connection Parallel task Type-C Type-A Type-B Mozumi Tunnel GW Atotsu Tunnel EYC,EYV, EYT EXC,EXV, EXT IXC,IXV, IXT IYC,IYV MCE EYA IYA IXA VIS Types MCF IFI, IMM Laser EXA GW Office

Vacuum and Laser Stuff Installation 2 F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Mozumi Tunnel GW Atotsu Tunnel MCE MCF PRMMR2 MR3 IFI, IMM Type-C Type-A Type-B VIS Types EYC,EYV, EYT EXC,EXV, EXT IXC,IXV, IXT IYC,IYV EYA IYA IXA EXA Center part construction without SR* and OMC, OFI Type-A SAS test at Y End at room tmp Cryogenic test at X End Laser GW Office

KAGRA Roadmap (ic3) F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Tunnel Excavation(14/3) FPMI (15/12) Vacuum(15/3) DRMI (16/9) Type-A Cryo(16/9) RSE(17/8) Cryo-RSE(18/3) Tuning And Observation Sapphire Test mass preparation(16/3) b-KAGRAi-KAGRA 12 ic3 phase

iKAGRA Commissioning Mozumi Tunnel GW Atotsu Tunnel MCE MCF PRMMR2 MR3 Type-C Type-A Type-B VIS Types EYC,EYV, EYT EXC,EXV, EXT IXC,IXV, IXT IYC,IYV EYA IYA IXA EXA IFI, IMM Low Laser Power (15W ?) FPMI operation using Silica Mirrors in IXA, IYA, EYA, EXA. Short Commissioning ~ 1 month(15/12) Laser GW Office

KAGRA Roadmap (bc1) F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Tunnel Excavation FPMI (15/12) Vacuum(15/3) DRMI (16/9) Type-A Cryo(16/9) RSE(17/8) Cryo-RSE(18/3) Tuning And Observation Sapphire Test mass preparation(16/3) b-KAGRAi-KAGRA 12 bc1 phase

bKAGRA Commissioning 1 F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Mozumi Tunnel GW Atotsu Tunnel MCE MCF PRMMR2 MR3 Type-C Type-A Type-B VIS Types EYC,EYV, EYT EXC,EXV, EXT IXC,IXV, IXT IYC,IYV EYA IYA IXA EXA IFI, IMM SR*, OMC, OFI are prepared. VIS upgrade to Type-B for core optics DRMI Operation using Silica Mirrors Full test of VIS Type-A + Cryo-Mirror SRM SR3 OFI OMC SR2 Laser GW Office

KAGRA Roadmap (bc2) F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Tunnel Excavation FPMI (15/12) Vacuum(15/3) DRMI (16/9) Type-A Cryo(16/9) RSE(17/8) Cryo-RSE(18/3) Tuning And Observation Sapphire Test mass preparation(16/3) b-KAGRAi-KAGRA 12 bc2 phase

bKAGRA Commissioning 2 F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Mozumi Tunnel GW Atotsu Tunnel MCE MCF PRMMR2 MR3 Type-C Type-A Type-B VIS Types EYC,EYV, EYT EXC,EXV, EXT IXC,IXV, IXT IYC,IYV EYA IYA IXA EXA IFI, IMM Sapphire mirrors suspended Type-A. RSE Operation (Sapphire mirrors at room temp.) SRM SR3 OFI OMC SR2 Laser GW Office

KAGRA Roadmap (bc3,4) F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Tunnel Excavation FPMI (15/12) Vacuum(15/3) DRMI (16/9) Type-A Cryo(16/9) RSE(17/8) Cryo-RSE(18/3) Tuning And Observation Sapphire Test mass preparation(16/3) b-KAGRA i-KAGRA 12 bc3,4 phase

bKAGRA Commissioning 3 F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Mozumi Tunnel GW Atotsu Tunnel MCE MCF PRMMR2 MR3 Type-C Type-A Type-B VIS Types EYC,EYV, EYT EXC,EXV, EXT IXC,IXV, IXT IYC,IYV EYA IYA IXA EXA IFI, IMM RSE Operation (at Cryo Temp.) IFO Tuning Observation SRM SR3 OFI OMC SR2 Laser GW Office

In the Last PAB Report … ‘We believe the project needs a more systematic technique for monitoring of status and plans, in effect, some version of a performance measurement system. … We recommend that some form of baseline planning and performance assessment be added to the project.’ -> A :Progress Evaluation System Introduction ‘A key element in this performance measurement system will be establishing an integrated schedule, built up from the individual subsystem schedules.’ -> A: Construct Master schedule and make detail schedule from each subgroup Bottom-up Plans. F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

Bottom-up Plan and Progress Evaluation System Schedule management system for quantitative evaluation of project progress was introduced. Progress evaluation is done by a ‘Milestone scheme’. Set ~10 milestones for each subsystem, picked up from a detailed schedule of each subsystem. Status for the milestones will be checked in regular “Chief” meetings. Required progress evaluation accuracy is ~20% resolution. The status will be open for all the collaborators. For this purposes, a software and network system : MS Project and Web server were prepared. F2F Meeting 2012/7/30~1 in ICRR, Kashiwa

KAGRA Progress Chat (KPC) based on bottom-up Plan KAGRA bottom up schedules of all subgroups are collected in one MS Project file. The mile stones and some important construction items, their anteroposterior relation and period are listed with respect to each subgroup. Time schedule consistency and anteroposterior relations between subgroups items are also specified. KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa

All KAGRA Progress Chart (KPC) KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa Subgroups Schedule for each milestones

Important Items and Anteroposterior relations in Subgroups KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa VAC milestones and some important Items and schedule. Detailed Progress schedule and Milestones

Anteroposterior relations bw Sub-Gs KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa VIS milestones and schedules CRY milestones and schedules

KPC progress sign for each item F2F Meeting 2012/7/30~1 in ICRR, Kashiwa Black lines in the bar shows progress rate.

Progress Evaluation and Action Each subgroup chief is requested to check the progress with this schedule for each item by himself in every chief meetings (every tweek weeks). If the chief encounters some problems that result in the delay of schedule, he is encouraged to consult with SEO. SEO should find any signs that show progress delay as soon as possible, and try to find reasons and problems with chiefs, and to show solutions. At the same time SEO should report to EO about KPC. KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa

Where we can find the KPC ? KAGRA External Review 2012/4/17~20 in ICRR, Kashiwa Schedule can be found in the “Chief meeting report page (pass required)” and the “Subgroup blog page (free access)” (in Japanese). Progress schedule link

Summary KAGRA Roadmap was refined and some minor re- refines might be expected because of budget status in the future. As detailed roadmap progress, KPC (KAGRA Progress Chart) was prepared by gathering milestone items (bottom-up plans) of subgroups. Chiefs are requested to update their progress status in KPC, while SEO members should check them, follow and report any troubles and delays for them to EO. F2F Meeting 2012/7/30~1 in ICRR, Kashiwa