Intended Learning Outcomes Define the principles of Line of Balance Demonstrate the application of LOB Understand the importance of LOB Understand the.

Slides:



Advertisements
Similar presentations
Project Management Skills for QOF leads Quality and Outcomes Framework Assessor Training.
Advertisements

Scheduling CTC-470.
Estimating, scheduling and budgeting
Project Management Process. Managing the Information Systems Project Focus of project management To ensure that information system projects meet customer.
© Tarek Hegazy – 1 Efficient Scheduling of Repetitive Projects Prof. Tarek Hegazy Computer-Aided Construction Project Management,
WOOD 492 MODELLING FOR DECISION SUPPORT Lecture 22 Network Problems.
Multimedia Specification Design and Production 2013 / Semester 1 / week 7 Lecturer: Dr. Nikos Gazepidis
 Chapter 6: Activity Planning – Part 1 NET481: Project Management Afnan Albahli.
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
Work Breakdown Structures. Purpose The WBS shows different levels within the product hierarchy. For Government program managers levels 1-3 are of prime.
Project Management: A Managerial Approach
1 9. S EQUENCING C ONSTRUCTION T ASKS Objective: To understand the problem of sequencing tasks in a manufacturing system, and the methods of finding optimal.
Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall 3.1.
Session 18 Modeling the Dynamic View: The Collaboration Diagram Written by Thomas A. Pender Published by Wiley Publishing, Inc. October 20, 2011 Presented.
Modern Systems Analysis and Design Third Edition
Copyright 2002 Prentice-Hall, Inc. Chapter 3 Managing the Information Systems Project 3.1 Modern Systems Analysis and Design Third Edition Jeffrey A. Hoffer.
Project Time Management
BAR CHART Paweł Bilski Piotr Mazur Paulina Wawryca.
Project Management and Scheduling
Copyright © Software Process Group 1 Software Process Group Microsoft Project Tutorial Steve Meyers
Resources Management Dr. Ahmed Elyamany.
Copyright © 2009 Pearson Education, Inc. Publishing as Prentice Hall Essentials of Systems Analysis and Design Fourth Edition Joseph S. Valacich Joey F.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Essentials of Systems Analysis and Design Fourth Edition Joseph S. Valacich Joey F.
Lesson №2. is the unique activity that has a beginning and an end time, aimed at achieving a predetermined result/goal, the creation of a specific, unique.
Appendix A Project Management: Process, Techniques, and Tools.
1 7. R EPETITIVE C ONSTRUCTION Objective: To understand how production and production rates are affected by repetition of tasks, and to learn how to plan.
© 2012 Cengage Learning. All Rights Reserved. This edition is intended for use outside of the U.S. only, with content that may be different from the U.S.
IT Project Management, Third Edition Chapter 6 1 Chapter 3: Project Time Management.
Copyright 2006 Prentice-Hall, Inc. Essentials of Systems Analysis and Design Third Edition Joseph S. Valacich Joey F. George Jeffrey A. Hoffer Chapter.
Project Management: A Managerial Approach
Linear Scheduling Method Definition A simple diagram to show location and time at which a certain crew will be working on a given operation.
Applying Stochastic Linear Scheduling Method to Pipeline Construction
Objectives 4 Understand the basic concepts of project planning and control 4 Explain PERT and Timeline (Gantt) charts.
1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management.
Problem Solving.
Scheduling CTC-415. Short Interval Scheduling Plan & manage day to day activities Focus on individual activities Goal Oriented to get activity done Two.
1 8. A DVANCED R ESOURCE M ANAGEMENT Objective: To develop new perspectives of space as resources, that will enable it to be more readily integrated with.
Resource analysis Project management (lecture + seminar)
PERT and CPM.
© 2008 Sterling Commerce. Confidential and Proprietary. How to Get Along with Project Using Microsoft Project so that it actually works for you, not against.
PROJECT MANAGEMENT Approaches By- Rahul Jain. Plan your work first…..then work your plan.
Information Systems System Analysis 421 Chapter 3 Managing the Information Systems Project.
Copyright © 2009 Pearson Education, Inc. Publishing as Prentice Hall Chapter 3 Managing the Information Systems Project 3.1.
© 2006 John Wiley and Sons, Inc. Project Management: A Managerial Approach Chapter 8 – Scheduling.
Microsoft Project 2010 ® Tutorial 1: Planning a Project.
Linear Scheduling Method Definition A simple diagram to show location and time at which a certain crew will be working on a given operation. Characteristics.
WBS Work Breakdown Structure © Unitec New Zealand.
1. WHAT IS A PROJECT? “A project is a problem scheduled for solution.” This definition forces us to recognize that projects are aimed at solving problems.
Asset accounting-29.pptx This course will give an overview of the following Workbreakdown Structure Network Project Builder Project Planning.
Unit 2 Time Management Prepared by: Prof. Seemaah Keddar.
Programming Taija Puolitaival, Department of Construction, Unitec 2014.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Chapter 7 Project Management and Event Implementation
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
PROJECT MANAGEMENT TOOLS AND TECHNIQUES SEMINAR December 2003.
Copyright 2002 Prentice-Hall, Inc. Chapter 3 Managing the Information Systems Project Modern Systems Analysis and Design Third Edition Jeffrey A. Hoffer.
CRITICAL PATH METHOD - PRECEDENCE DIAGRAMS - SANDEEP DIGAVALLI.
2nd Task of Your Project „All you have to decide, is what to do with the time that is given to you.“ J.R.R. Tollkin Prof. Dr. Christian Bleis 1 Interaktionskompetenz.
Activity Planning.
ENGINEERING MANAGEMENT (GE 404)
ENGINEERING MANAGEMENT (GE 404)
Basic Project Scheduling Line of Balance
THE HIERARCHY OF SCHEDULES
CEM 510 Construction Planning & Scheduling Dr Almohawis
Lecture 7 PROJECT SCHEDULING Ferdinand Fassa.
Modern Systems Analysis and Design Third Edition
LINEAR BALANCE METHOD & MATRIX SCHEDULE
Time Scheduling and Project management
CHAPTER ONE: RESOURCE ALLOCATION AND SCHEDULING
Modern Systems Analysis and Design Third Edition
Presentation transcript:

Intended Learning Outcomes Define the principles of Line of Balance Demonstrate the application of LOB Understand the importance of LOB Understand the process of applying LOB

Line of Balance (LOB) Definition A simple diagram to show location and time at which a certain crew will be working on a given operation. Focuses on balancing the time taken for individual activities by either re-distribution of resource or by reducing process waste.

Line of Balance (LOB) LOB is a Planning methodology to optimize resources used LOB is a Good Visual tool that lets us see if a construction program can be achieved with the minimum waiting time between tasks It is primarily used on projects that have repeated elements like Highways, Pipelines, High-rise buildings, hotel bedrooms, bridge etc.

Benefits of LOB Continuous resource use Less starts and stops Crews will spend less time and money on later units once they develop a learning momentum. Improve productivity by 20 % Save money and time Faster planning process Superior Visual control

Faster planning process Less tasks Less links Faster program creation Less time to understand & interpret Easy to try ‘what-if’ scenarios

Activity-based vs. Location-based Activity-based – 30 floors, 4 activities in each location = 120 activities – Formwork-reinforcement-pouring on the same floor = 60 links – Pouring – formwork next floor = 29 links – Pouring – finishes two floors below = 28 links – Internal links in finishes to prevent resource overlapping = 29 links – Total: 120 CPM activities, 266 links Location-based – 4 tasks flowing through locations – 4 links between activities – 4 links inside activities – Total: 4 tasks, 8 link

Activity-based Formwork Floor 1 Reinforcement Floor 1 Pouring Conc. Floor 1 Finishing Floor 1 Formwork Floor 2 Reinforcement Floor 2 Pouring Conc. Floor 2 Finishing Floor 2 Formwork Floor 3 Reinforcement Floor 3 Pouring Conc. Floor 3 Finishing Floor 3

Location-based Time Units

Superior project control Easy to interpret Clear uncomplicated displays Simple to manage Easy to monitor Effortless progress updates Effective control

LOB Calculations The objective of using LOB is to achieve a resource- balanced schedule by determining the suitable crew size and number of crews to employ in each repetitive activity. This is done such that: 1.the units are delivered with a rate that meets a pre- specified deadline 2.the logical CPM network of each unit is respected 3.crews’ work continuity is maintained. The analysis also involves determining the start and finish times of all activities in all units and the crews’ assignments.

Three diagrams are used in LOB 1. Production Diagram Shows the relationships of the activities for a single unit. 2. Objective Diagram Used to plot the planned or actual number of units produced vs. time. 3. Progress Diagram Shows the number of units for which the activity has completed.

Drawing the LOB Schedule Similar rates  parallel lines Different rates  lines not parallel Conflict points  at the last or first unit R= (n – 1)/(t f – t 0 ) Time Units n n n - 1 t0t0 tftf R tftf

LOB Calculations The CPM-LOB formulation involve: – Crew synchronization – Calculating resource needs – Drawing the LOB schedule

Crew Synchronization A simple relationship between the duration taken by a crew in one unit (D) and the number of crews (C) to employ in a repetitive activity Slope of the shaded triangle in becomes: R = 1 / (D / C) Then: C = D x R Crew 3 R Crew 1 Crew 2 R Time Units D/C

B Calculating Resource Needs Time Units n...21n...21 ADC n - 1 C(2) B(5) D(5)A(5) TF=3 Ri = (n – 1) / (TL - T1) + TFi Ci = Di x RiCai = Round Up (Ci)Rai = Cai / Di C(2) B(5) D(5)A(5) TF=3 CC

Example A BCDE N=61 units Required ; draw LOB at month 16 ActivityABCDE Production rate35531 No of crews

Example R = 1 / (D / C) D = C/R ActivityABCDE Production rate35531 No of crews Duration A B C D E Start 000

Example For A: R=3, t 0 =3, Time Units t f =3+(61-1)/3=23 For B: R=5, t 0 =6, t f =6+(61-1)/5=18 For C: RC=RB>RA, buffer from top t 0 =25-(61-1)/5=13 R=5, t f =23+2=25, B C For D: R=3, t 0 =13+3=16, t f =16+(61-1)/3=36 For D: R=1, t 0 =16+2=18, t f =18+(61-1)/1= DE A

Example Time Units For A: R=3, t 0 =3, 16=3+(x -1)/3, x=40 For B: R=5, t 0 =6, 16=6+(x -1)/5, x=51 For C: R=5, t 0 =13, 16=13+(x -1)/5, x=16 For D: R=3, t 0 =16, For E: x=0 A B C D E B CDE A 16=16+(x -1)/3, x=1 Progress Diagram Objective Diagram Actual Planned

Example B CDE A

QUESTIONS Contact: Dr. Ahmed Elyamany