PHENIX WEEKLY PLANNING 11/30/06 Don Lynch. 11/16/06 Weekly Planning Meeting 2 PHENIX END OF SHUTDOWN PARTY Celebrating the successful installation of.

Slides:



Advertisements
Similar presentations
PHENIX WEEKLY PLANNING 2/8/2007 Don Lynch. 2/8/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress Pink.
Advertisements

PHENIX WEEKLY PLANNING 1/4/2007 Don Lynch. 1/4/207 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 2/15/2007 Don Lynch. 2/15/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress All.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
6/6/ PHENIX WEEKLY PLANNING 6/6/2013 Don Lynch Note: No PHENIX planning meeting this week due to end of run party. Feel free to discuss safety and.
1 1/13/2011 PHENIX WEEKLY PLANNING 1/13/2011 Don Lynch No Meeting Today Due to snow shortened work week, today’s planning meeting has been cancelled. Slides.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
5/9/ PHENIX WEEKLY PLANNING 5/9/2013 Don Lynch.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 10/05/06 Don Lynch. 10/05/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
12/26/2013-1/2/ PHENIX WEEKLY PLANNING Dec. 26, Jan. 2, 2014 Don Lynch.
12/5/ PHENIX WEEKLY PLANNING Dec. 5, 2013 Don Lynch.
PHENIX PLANNING Technical Support Plan for 2006 Don Lynch (updated 3/24/06)
PHENIX WEEKLY PLANNING 3/8/2007 Don Lynch. 3/8/207 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Continues…. All Up Commissioning In Progress.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
1/9/ PHENIX WEEKLY PLANNING Jan. 9, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
PHENIX WEEKLY PLANNING 10/11/2007 Don Lynch. 10/11/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 PHENIX WEEKLY PLANNING December 3, 2015 Carter Biggs.
Technical Support /1/08 PHENIX WEEKLY PLANNING 5/1/2008 Don Lynch.
PHENIX WEEKLY PLANNING 6/29/06 Don Lynch. 6/29/2006 Weekly Planning Meeting 2 This Week TOF W tests continue, modification decisions made? New HV connector.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
PHENIX WEEKLY PLANNING 3/09/06 Don Lynch. BLM Test BLM Test Installation He Bags.
PHENIX WEEKLY PLANNING 12/6/2007 Don Lynch. 12/6/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
PHENIX WEEKLY PLANNING 3/23/06 Don Lynch. MPC Electronics MPC rack installed without cards. Cards to be installed As available and as access time is available.
9/27/20121 PHENIX WEEKLY PLANNING 9/27/2012 Don Lynch.
1 PHENIX WEEKLY PLANNING January 21, 2016 Carter Biggs.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 10/20/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
1 12/30/2010 PHENIX WEEKLY PLANNING 12/30/2010 Don Lynch.
PHENIX WEEKLY PLANNING 10/18/2007 Don Lynch. 10/18/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
3/20/ PHENIX WEEKLY PLANNING March 20, 2014 Don Lynch.
12/6/20121 PHENIX WEEKLY PLANNING 12/6/12 Don Lynch.
PHENIX WEEKLY PLANNING 10/12/06 Don Lynch. 10/12/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
1/26/20121 PHENIX WEEKLY PLANNING 1/26/2012 Don Lynch.
PHENIX WEEKLY PLANNING 11/15/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going11/30.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
5/24/20121 PHENIX WEEKLY PLANNING 5/24/2012 Don Lynch.
12/19/ PHENIX WEEKLY PLANNING Dec. 19, 2013 Don Lynch.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
12/20/20121 PHENIX WEEKLY PLANNING 12/20/12 Don Lynch.
Preparations for Run 6 Don Lynch February 13, 2006.
SPHENIX MECHANICAL D. Lynch September 11, AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.
PHENIX WEEKLY PLANNING 10/26/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
PHENIX WEEKLY PLANNING 5/3/2007 Don Lynch. 5/3/2007 Weekly Planning Meeting 2 Schedule HyTec CM vibration modes test5/23/07 End of Run Party 6/29/07 Next.
5/30/20131 PHENIX WEEKLY PLANNING 5/30/2013 Don Lynch.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
3/7/20131 PHENIX WEEKLY PLANNING 3/7/2013 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
2/27/ PHENIX WEEKLY PLANNING Feb. 27, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 11/8/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish Elec. Cooling Water upgrade(CA) (under.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
PHENIX WEEKLY PLANNING 3/30/06 Don Lynch. This Week MPC air flow started BLM source test HBD transparency monitor hutch work and cable tray 1 st MPC Card.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 8/24/06 Don Lynch. 8/24/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameDurationStart_DateFinish_Date PHENIX Shutdown.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
PHENIX WEEKLY PLANNING 2/16/06 Don Lynch. Prep for Run 6 Completed.
Presentation transcript:

PHENIX WEEKLY PLANNING 11/30/06 Don Lynch

11/16/06 Weekly Planning Meeting 2 PHENIX END OF SHUTDOWN PARTY Celebrating the successful installation of the HBD, TOF.W, MPC.N, RXNP detectors and the completion of shutdown work Brought to you by the HBD, TOF.W, MPC.N, and RXNP detectors

11/16/06 Weekly Planning Meeting 3 New Gas Systems HBD and TOF W gas flow control systems are done. HBD gas monitoring system installation ongoing

11/16/06 Weekly Planning Meeting 4 Still Needed for Approval to Operate: Where will fan(s) be mounted? – CM base “cubby hole” fan model and specs to be forwarded to Safety Written design and operation description and– To be forwarded to Safety Order for 5 blowers & drivers (4 +1 spare) is in the works HBD (Hadron Blow Drier) Electronics Cooling Blower requirements: 5 cfm (142 5 in WC (1245 Pa) Order in Process, Finally ! Rec. ~ 2 weeks ? Supposedly partially shipped 11/27 no parts rec’d yet

11/16/06 Weekly Planning Meeting 5 Tools Needed –1/2’’ and 3/4’’ black electrical tape –Scissors –Scalpel –RTV –Plastic cable ties (long and short) –Isopropyl alcohol –Kim wipes –Optical grease –Small hex screw driver –Gloves for RTV RXNP Bad PMT replacement proposal

11/16/06 Weekly Planning Meeting 6 Label new PMT with tape Unconnect old PMT HV and signal cables Cut cable ties Remove RTV from prism cover gap with scalpel Unscrew prism cover and remove from PMT Remove black electrical tape connecting PMT and prism Detach PMT from prism Clean prism face with alcohol and wipes RXNP Bad PMT replacement proposal

11/16/06 Weekly Planning Meeting 7 Apply grease to prism and attach PMT Tape PMT to prism with black electrical tape (taping involves several steps to ensure light tightness, difficult to perform with one person) Attach prism cover and screw back on RTV prism cover gap Place PMT back on end of arm and secure with plastic ties RXNP Bad PMT replacement proposal

11/16/06 Weekly Planning Meeting 8 OTHER THINGS Test for light tightness anywhere along the way? Recommend dry run on bench top with spare parts RXNP Bad PMT replacement proposal

11/16/06 Weekly Planning Meeting 9 RXNP Bad PMT replacement proposal Problems with Proposed repairs 1. Only 1 person safely can workon the lift table 2. 3 rd PMT from top is most difficult to replace. All 6 fiber bundles pass in front of this PMT. 3. The mounting rings on the PMT's are staggered to fit. 4th PMT would need to be dismounted in order to remove the 3rd PMT. 4. All of the steps Eric has outlined in his slides above would need to be done on the lift table. 5. Proximity to HBD east detector, cables and gas lines which are delicate.

11/16/06 Weekly Planning Meeting 10 CM Lift Table Proposal: High and low limit switches to prevent over-travel hitting HBD mounting I-beams and lower cable trays. Upper limit switch cuts out power to lift allows power to lower Lower limit makes audible alert. No need to cut out control. ( Professional hand model? )

11/16/06 Weekly Planning Meeting 11 Subsystem Maintenance & Repairs EMCal West & East Done DC HV/LV patch panel upgrade & wire repair Done MPC South repaired BBC South & North repairs done MuTr grounding problems Fixed MuTr North and South HV/FEE troubleshooting ~ Done..Dry air distribution balancing done RICH light leak ~ PC HV module/cable maintenance done TEC upgrades done MuID survey DONE ! MuID commissioning next month after flammable gas is on

11/16/06 Weekly Planning Meeting 12 MuTr Dry Air Flow Distribution Upgrade MuTr South Flow Controls MuTr North Flow Controls

11/16/06 Weekly Planning Meeting 13 Infrastructure Work CAD/RHIC PHENIX infrastucture related mechanical and electrical support Roof leak repairs ? MuID survey Done Door Latch maintenance for security Requested Metals Dumpster Requested Run 7 prep support On-going

11/16/06 Weekly Planning Meeting 14 StartComplete TOF West, RXNP, MPC N Electronics Installation/Commissioningin progress12/30/06 HBD HBD preamp cooling system10/1/0612/15/06 (temporary LN2 system in-place) Electronics Installation/Commissioning11/1/0612/30/06 MuID surveyDone MuID commissioning 1/8/071/15/07 Remaining Schedule

11/16/06 Weekly Planning Meeting 15 Remaining Schedule (cont’d) StartComplete Pink Sheeting & Blue Sheeting Started30-Nov Move MMS full North 20-Nov21-Nov Rebuild Rolling door 29-Nov1-Dec Install beam pipe collar 26-Dec29-Dec Close rolling door 29-Dec Start Flammable Gas Flow 3-Jan All Up Commissioning 4-Jan26-Jan RHIC Cooldown Begins 2-Jan Beam in yellow ring 9-Jan Beam in blue ring 16-Jan RHIC beam conditioning 23-Jan Shutdown Concluded/Start of Physics Run 23-Jan

11/16/06 Weekly Planning Meeting 16 Looking Ahead What’s up for next year and beyond New CM Crane New Beam pipe design Muon RPC trigger design VTX/FVTX design NCC design MuTr upgrade ? Infrastructure improvements

11/16/06 Weekly Planning Meeting 17 SEU Test John Lajoie Iowa State Experimental Impact Statement The box dimensions are: 17” x 10” x 3.5”. The only services required by the box in order to function are AC power and a Cat5 cable connected to the USB interface. The FPGA devices will be programmed and monitored over an external USB connection, which is run over a USB -> Cat5 extender box. This extender has a maximum range of 150 feet of Cat5 cable, which should be sufficient to reach from the PHENIX IR to the rack room, where it will connect to a laptop containing the analysis and configuration software. (The laptop will require network access, and will comply fully with all BNL cybersecurity requirements.) Because SEU events are relatively rare, it would be best to expose the apparatus to as high a particle flux as possible. However, the box represents a substantial amount of material and it would be unacceptable to place the box within the acceptance of the central arms. Placement within one of the muon arms, near or on the central magnet pole, would be optimal.

11/16/06 Weekly Planning Meeting 18 SEU Test John Lajoie Iowa State Both boxes installed. Approval request sent to Yousef.

11/16/06 Weekly Planning Meeting 19 PHENIX Annual Safety Review Follow Up No major problems/no action items received from Yousef Provide as-built drawings and procedures for new gas systems (TOF W and HBD)- Rob finished drawings. Procedures in-progress Comprehensive review of PHENIX procedures, revise where necessary, retire where appropriate - Started

11/16/06 Weekly Planning Meeting 20 Next Week Complete Wall HBD, TOF W, RXNP, MPC N electronics commissioning PHENIX Procedure review Subsystem Commisioning Housekeeping

11/16/06 Weekly Planning Meeting 21 PHENIX END OF SHUTDOWN PARTY Celebrating the successful installation of the HBD, TOF.W, MPC.N, RXNP detectors and the completion of shutdown work Brought to you by the HBD, TOF.W, MPC.N, and RXNP detectors

11/16/06 Weekly Planning Meeting 22 Links for the weekly planning meeting slides, long term planning, pictures, videos and other technical info can be found on the web site: Where To Find PHENIX Technical Info