Examining the project ( seminar ). What is this chapter about? Gathering and analysing information for decision making in projects: – What has happened.

Slides:



Advertisements
Similar presentations
Estimating, scheduling and budgeting
Advertisements

Chapter 3 Managing the Information Systems Project
3-1 © Prentice Hall, 2004 Chapter 3: Managing the Object-Oriented Information Systems Project Object-Oriented Systems Analysis and Design Joey F. George,
Project Management 6e..
Analysing the AoA network Project Management. Total Project Time The minimum time in which the project can be completed. Calculation: forward pass Forward.
Copyright © 2012 Pearson Education, Inc. Publishing as Prentice Hall 3.1.
Project Management Lecture Developing the Project Plan.
BSBPMG503A Manage Project Time 6.5 Develop Schedule The process of analysing activity sequences, durations, resource requirements and schedule constraints.
Importance of Project Schedules
Project Management Outline of Chapters 1-6. Chapter 1 – Project Management Concepts Definition of a project and its attributes Key constraints within.
Project Management Students should be able to: 1.Discuss the importance of project management for firms. 2.Define the key project management concepts.
Project Time Management
Chapter 3: The Project Management Process Groups
1 SWE Introduction to Software Engineering Lecture 11 - Requirements Engineering Processes.
©Ian Sommerville 2000Software Engineering, 6th edition. Chapter 4 Slide 1 Chapter 4 Project Management.
Copyright 2002 Prentice-Hall, Inc. Managing the Information Systems Project 3.1 Chapter 3.
Computer System Analysis
Chapter 3 : Managing the Information Systems Project.
Copyright © 2009 Pearson Education, Inc. Publishing as Prentice Hall Essentials of Systems Analysis and Design Fourth Edition Joseph S. Valacich Joey F.
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Essentials of Systems Analysis and Design Fourth Edition Joseph S. Valacich Joey F.
Edward B. Farkas, Managing Director, Project Management Practice
Copyright © 2014 McGraw-Hill Higher Education. All rights reserved. CHAPTER 15 Project Management McGraw-Hill/Irwin.
Appendix A Project Management: Process, Techniques, and Tools.
Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management.
Planning the project Project Management (lecture).
1 Chapter 5 Project management. 2 Project management : Is Organizing, planning and scheduling software projects.
“How to fail in project management without really trying” –J. K
BIS 360 – Lecture Two Ch. 3: Managing the IS Project.
1 L U N D S U N I V E R S I T E T P rojektledning och Projektmetodik.
Software Engineering Saeed Akhtar The University of Lahore Lecture 8 Originally shared for: mashhoood.webs.com.
Scheduling Resources and Costs CHAPTER EIGHT Student Version Copyright © 2011 by The McGraw-Hill Companies, Inc. All rights reserved. McGraw-Hill/Irwin.
©Ian Sommerville 2000Software Engineering, 6th edition. Chapter 4 Slide 1 Project management l Organising, planning and scheduling software projects.
Objectives 4 Understand the basic concepts of project planning and control 4 Explain PERT and Timeline (Gantt) charts.
1IT Project Management, Third Edition Chapter 6 Chapter 6: Project Time Management.
Project Life Cycle.
Requirements Capture. Four Steps of requirements capture List candidate requirements Understand system context Capture functional requirements Capture.
Chapter 3 Project Management Chapter 3 Project Management Organising, planning and scheduling software projects.
© 2014 Pearson Education, Inc., Upper Saddle River, NJ. All rights reserved. This material is protected by Copyright and written permission should be obtained.
Scheduling Resources and Cost
Resource analysis Project management (lecture + seminar)
Project Management Project Planning. PLANNING IN PROJECT ENVIRONMENT Establishing a predetermined course of action within a forecasted environment WHY.
12/2/2015 2:45 AM 1 PROJECT TIME PLANNING Process and Bar Chart Technique.
Initiation and Planning for Success Sridhar Seshagiri Rao, PMP Innova Solutions Inc. Santa Clara, CA. April 9 th 2004.
Copyright 2002 Prentice-Hall, Inc. Chapter 3 Managing the Information Systems Project 3.1 Modern Systems Analysis and Design.
Information Systems System Analysis 421 Chapter 3 Managing the Information Systems Project.
‘Crashing’ – reducing task durations by increased costs ( lecture )
Microsoft Project 2010 ® Tutorial 1: Planning a Project.
Resource analysis 1 Project management (seminar).
SOFTWARE PROJECT MANAGEMENT
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
P3 Business Analysis. 2 Section F: Project Management F1.The nature of projects F2. Building the Business Case F4. Planning,monitoring and controlling.
IT-301 Project Management I: Unit 4: Cost Management.
Develop Schedule is the Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule.
Project Time Management Based on PMBOK 5 th Edition Abdelrahman Sheta, PMP,ITIL 1PMP - Project Time Managementfacebook.com/Sheta.Page.
303KM, Introduction to Project Management1 Chapter 1: Introduction to Project Management.
Project management. Software project management ■It is the discipline of planning, organizing and managing resources to bring about the successful completion.
Project Management Planning and Scheduling. “Failing to plan is planning to fail” by J. Hinze, Construction Planning and Scheduling Planning: “what” is.
Examining the project (lecture).
Plan Schedule Management
Analysing the AoA network
PMIS Initiating a Project Application of Project Management Processes Project Charter Stakeholder Analysis and Stakeholder Register 2. Planning.
CIS 210 Systems Analysis and Development
Project Management (lecture)
Project management (seminar)
Examining the project.
Examining the project (seminar).
Project Management (lecture)
University of Debrecen Mongolian University of Life Sciences
Chapter 2: Building a System
Presentation transcript:

Examining the project ( seminar )

What is this chapter about? Gathering and analysing information for decision making in projects: – What has happened – What is happening – What should have happened – What should be happening Process of gathering information: monitoring & controlling

Time related processes Concerned with the activities in the project plan: –Determination of logical interactions –Estimation of durations –Schedules and key event schedules (with identification of critical activities) Focus of control is on the future. If not, it will degenerates into a recording system Consistent unit of time throughout the plan (with the exemption of different levels of detail).

Cost related processes Goal: to complete the project within the financial budget, including forecasting and managing costs. Estimation of activity costs for the budget-plan are based on: –Man-hours –Labor-rates (wage etc.) –Material costs –Service costs –Set-up charges –Rental charges –Overheads Cost control is based on the budget Cost control is the principal means of control (esp. for the customer)

Resource related processes Aim: to plan the use and control of resources. Resources: anything (any input) that is required. Availability of resources means constraints for the project. Resource planning: –Summation (aggregation) for each period –Scheduling activities with resource needs –Coming only after the scheduling of activities by logical interactions Resource control: monitor the usage of resources and report any deviations to the plan

Planning project duration Network techniques: a formal and explicit statement of policy, and also a communication tool 1.Work Breakdown Structure (WBS) 1.Logical sequencing the project 2.More grouping logic can be used (depending on the project-context): 1.Physical 2.Functional 3.Cost-centre etc. 2.Assign the durations to the tasks and task groups Use iterative refining of the duration estimations 3.Examination of the plan: ‘there is always a better way’ Project network techniques identifies the critical activities to focus the examinations on. Duration reduction always costs resources.

Reducing total project time (TPT) Systematic approach: 1.Critical activities subjected to the questioning technique (if there is a quicker way) 2.Can we modify the network logic to overlap or parallel activities? 3.Is it acceptably possible to increase the risk taken? 4.Can any resources moved or can the costs of increased resources be tolerated?

The questioning method Backround is work-study Systematic questioning: the same questions on the same (rigid) way Two kinds of activities: – ‘do’ activities: tasks advancing the project in themselves – ‘ancillary’ activities: supporting ‘do’ activities

Questions to be asked when reducing the project time ? Purpose Place Sequence Person Means Overlapping Risk Trade-off Cost

Reduction by overlapping activities Activities following each other, depending on the interrelationships can be overlapped or paralleled. 1 st day actvity ‘A’ actvity ‘B’ Original sequence Overlapping activities actvity ‘A’ actvity ‘B’ actvity ‘A’ actvity ‘B’ actvity name 2 nd day3 rd day4 th day5 th day actvity ‘B’ Parallel activities actvity ‘A’ actvity ‘B’ actvity ‘A’ actvity ‘B’

Reduction by increased risk Reducing activities like: – Testing – Checking – Proving Risk of failure will increase

Reduction by the transference of resources Trading-off resources: moving resources from non-critical activities to critical ones.

Reduction by increased cost („cost slope concept” or „crashing”) Increasing activity cost to reduce its duration. Cost-slope: cost of reducing duration time by unit time. We need network diagrams to do crashing.

Dangers of the cost-slope concept It is difficult to find reliable figures for the changes in cost resulting from changes in duration times. Cost/time relations are frequently not constant nor simple Not all resources are freely convertible to cost (problem of availability)

Reducing cost by increasing time Non-critical activities can be increased in time without extending the duration of the whole project (they have float time). In this case cost savings are the only effect.

Relationship between time and labour employed There is a minimum time below it is impossible to reduce duration.

The final network The network after reduction will be different than the one before: – Logic and connections changed between activities – Duration times altered – New critical path A test is needed to uncover illogicalities and to match the new activity schedule to the resource availabilities

Reading Textbook chapter 8

Thank you for listening