Project Update Colorado Esplanade Project
Agenda Colorado Esplanade Project Overview Current Work
Overview
Overview 96 New Trees -71 Mexican Sycamores -13 Kentia Palms WYNDHAM 96 New Trees -71 Mexican Sycamores -13 Kentia Palms -12 Rainbow Eucalyptus 17 Trees Relocated 23 Trees Protected in Place 5.3 New Trees per 1Tree Removed Bring paver and pass around TONGVA PARK
Color Rendering of Proposed Project Colorado Esplanade Explain paver types, decking, string lights, and trees (type) Colorado Avenue Esplanade project will be complete before Expo begins carrying passengers
Color Rendering of Proposed Project Colorado Esplanade Explain paver types, decking, string lights, and trees (type) Festival lighting will be placed approximately every 25 feet. Outdoor furniture will be added.
Schedule Awarded Start Date Duration: 12 months January 27, 2015 March 16, 2015
Current Work
Current Work Placing structural soil along north sidewalk. Structural soil supports the sidewalk above it while encouraging root growth. Placing structural soil along north sidewalk.
Current Work Elements of the finished project: charcoal concrete The driveway at 1st Court (alley) and Colorado Avenue will feature the same concrete.
Current Work Elements of the finished project: pavers
Current Work Elements of the finished project: trees The 96 new trees will be watered with recycled via drip water systems.
Current Work Elements of the finished project: trees
Public Outreach Explanation and Way Finding
Public Outreach Print material
Phasing Northside Colorado Avenue Construction 2 WB traffic lanes will be maintained at all times PHASE A Southside Colorado Avenue Construction -2 WB traffic lanes will be maintained at all times -Main St will be realigned connecting to 2nd St -Lane closures and 1-way for <duration> PHASE B Discuss work on sidewalk, road… Before moving on to Phase B you will see pavers, trees, etc… things looking complete and tidy
Phase A Phase B WYNDAM Bring paver and pass around TONGVA PARK
Phase A Phase B WYNDAM Bring paver and pass around TONGVA PARK
Phase B Phase B will also have a pedestrian walkway and business access Bring paver and pass around
Merging 2nd Street and Main Street Moving of sewer siphon was first step in reconfiguring Main Street; some closures will be necessarily to complete the work.
Main Street Before and After Project
Intersection & Driveway Work Will be done at night during both phases
Public Outreach Visit businesses within 500-foot radius of project boundaries -Interview for business profiles -Leave project FAQs Distribute contact information -Email: ned@Celtis.com -Hotline: 310.374.7570
Q&A Colorado Esplanade