Progress report on multi-OTR fabrication and schedule IFIC-SLAC Design and Hardware fabrication Realistic Optics and Beam Dynamics simulations Controls and Software analysis Outline
Design and Hardware Fabrication Design and Hardware Fabrication Finalize design shortening beam tubes until 300 mm overall length Purchase movers V/H movers, Pneumatic target inserter Focus adjustment X/Y camera positioner Purchase hardware control Two 8 channels stepper motor driver 12 channels digital control target actuator 12 ADC channels for read back of linear pots Purchase Optics Camera C-mount optics tubes 150 mm for each OTR Mitutoyo 10X long working distance microcope 90º C-mount mirror
Design and Hardware Fabrication Design and Hardware Fabrication OTR main fabrication OTR body and optical windows parts Fabricate and weld flanges on tubes and tubes to OTR body Fabricate and weld bellows and flanges Fabricate OTR moving system adaptors
Realistic Optics and Beam Dynamics Simulation Study of the possible locations space, better optics conditions Tracking studies the model should be completed adding all possible machine imperfections Modelisation of the OTR measurements Comparison with the multi-wire scanner measurements
Controls and Software Analysis Control needs Low-levels drivers for: CCD frame grabber, V/H movers, lens focus movers, OTR insertion actuator EPICS drivers and Data Base choose hardware controls with EPCIS module support High-level interface EDM, Flight Simulator… Hardware protection for: Target damage CCD radiation sensitive
Controls and Software Analysis Software analysis Can be done in any scripting/programming environment supported by EPICS CA (C, C++, Perl, Python, Matlab, TCL…) Output processed data to EPICS Process Variables when done Scripts/code should also be controlled via PVs 2D Gaussian filter, taking CCD image and generating beam matrix data Online Twiss/Emit calculations Upgrade FS EXT emittance minimisation application Beam finder and tracker Track interpolated beam position in OTR target locations using adjacent BPMs for faster OTR insertion Intermittent target insertions to check tracking Piggyback on the software planned for multi-wire system
Conclusions The tasks has been identified We are working on the schedule of the different phases: Design and Hardware fabrication (~4 months) Realistic Optics and Beam Dynamics simulations (~2 months) Controls and Software analysis (~4 months) We could give a realistic schedule mid-September 2009