Topic 5.8 ( only HL ) IB Business & Management Project Management Mr L Greenbank 1.

Slides:



Advertisements
Similar presentations
Lecture Network Analysis
Advertisements

WBS: Lowest level OBS: Lowest level
Copyright 2006 – Biz/ed Critical Path Analysis.
PROJECT MANAGEMENT Network or Critical Path Analysis
Productive Efficiency
1 Lecture by Junaid Arshad Department of Engineering Management Abridged and adapted by A. M. Al-Araki, sept WBS: Lowest level OBS: Lowest level.
Having Fun with Gantt PERT &.
Network Analysis and Duration Estimating Kathy S. Schwaig.
Tutorial 2 Project Management Activity Charts (PERT Charts)
Manjari Akella Pranava Nagpal B-Tech(CSE) 4 th Year.
Welcome to your final year at school! Introductions.
5.8 Project Management Chapter 37 HL - Only.
Operations Management
Management & Development of Complex Projects Course Code - 706
Chapters 8, 9, and 10 Design Stage 1 Preconstruction Stage 2: Procurement Conceptual Planning Stage3: Construction Stage 4: Project Close-out.
Managing time ‘Time is nature’s way of stopping everything happening at once’ Hughes & Cotterell 2002 Production Process.
Module 5 – Networks and Decision Mathematics Chapter 24 – Directed Graphs.
15C Backward scanning and crashing
Project Time Management
1 B. SW Project planning & scheduling Recap from previous slide: It is important to decide on who is responsible for each activity. See Yeates & Cadle.
Scheduling CTC-415. Activity Network Development Network Models Activity on Node Precedence Diagram Method Activity on Arrow Network Characteristics Discrete.
George’s Bicycle Creating a Gantt Chart.
1 Planning Change. Planning for improved efficiency and effectiveness Utilise the resources in a better way Obtain additional resources that may help.
CRITICAL PATH ANALYSIS aka NETWORK PATH ANALYSIS DESIGNED to help managers who are planning complex projects that involve many interrelated tasks The idea.
PROJECT MANAGEMENT Syllabus Outcomes : Construct and interpret a network, identify the critical path, and calculate the free and total float. Evaluate.
MODULE 5: OPERATIONS MANAGEMENT UNIT 5.8 – PROJECT MANAGEMENT
A brief summary of Critical Path (or network) Analysis Critical Path Analysis is a way of planning complex projects. It allows one to find those parts.
IB Business and Management 5.8 Project Management (Critical Path Analysis)
O PERATIONAL S TRATEGIES O PERATIONAL S TRATEGIES : L EAN P RODUCTION “Do not wait; the time will never be just right” Napoleon Hill “The clock not the.
1 Project Planning, Scheduling and Control Project – a set of partially ordered, interrelated activities that must be completed to achieve a goal.
Software Project Management
Black Box Testing Techniques Chapter 7. Black Box Testing Techniques Prepared by: Kris C. Calpotura, CoE, MSME, MIT  Introduction Introduction  Equivalence.
Critical Path Analysis. Planning and Monitoring Tool.
PROJECT MANAGEMENT Approaches
11/02/09 Chapter 7-Project Planning 1 Elements of Project Planning  Divide project into tasks, tasks into subtasks, subtasks into...  Estimate duration.
PROJECT MANAGEMENT Approaches By- Rahul Jain. Plan your work first…..then work your plan.
Operational strategies Lean production. The adoption of techniques that help to reduce waste.
TK3333 Software Management Topic 6: Scheduling. Contents  Estimate the duration for each activity  Establish the estimated start time and required completion.
A2 Operations Management Critical Path Analysis. How long will it take? n Walls have decided to launch a new Magnum ice cream. Machine delivery will take.
Unit 2 Time Management Prepared by: Prof. Seemaah Keddar.
Critical Path Analysis - Worksheet
Project Management What are businesses trying to achieve by using Operations Management? (done on AS) EFFICIENCY.
Net work Analysis/Critical Path Analysis (L1) Learning Objective – Understand CPA Learning Outcomes - By the end of the lesson students should be able.
Critical Path Analysis. Starter – The Big Breakfast! On Saturday, I want to cook myself a big breakfast.I want to have some toast, scrambled eggs and.
PROJECT MANAGEMENT TOOLS AND TECHNIQUES SEMINAR December 2003.
Network planning models These project scheduling techniques model the project's activities and their relationships as a network. In the network, time flows.
First name ??? ist auf Englisch. Critical Path Analysis.
Lean Production: Critical Path Analysis 3.15 Lean Production Objectives; Understand the key requirements of critical path analysis (CPA) Understand the.
Copyright 2006 – Biz/ed Critical Path Analysis.
CRITICAL PATH METHOD - PRECEDENCE DIAGRAMS - SANDEEP DIGAVALLI.
Critical Path Analysis (CPA)
Critical Path Analysis
UNIT II Scheduling Procedures & Techniques FLOAT
Project Management: PERT/CPM
Critical Path Analysis
Critical Path Analysis (CPA)
Planar Graphs & Euler’s Formula
Analysing the AoA network
Welcome to your final year at school!
Critical Path Analysis
Critical Path Method Farrokh Alemi, Ph.D.
Activity on Node Approach to CPM Scheduling
Project Management (lecture)
Project Planning By Phaik San Liew.
CPA – Information Sheet
Project Management (lecture)
Critical Path Analysis
Critical Path Analysis
Have a think…! What process do you need to go through to make bread or redecorate your bedroom? Are there any activities that could be done at the same.
Presentation transcript:

Topic 5.8 ( only HL ) IB Business & Management Project Management Mr L Greenbank 1

Introduction Project Management: “The application of management techniques to the implementation of a project from start to finish.” Purpose of project management: – To achieve predetermined objectives of scope, quality, time and cost, to the equal satisfaction of those involved. Network Analysis – Most common tool used in project management. – Serves to improve the efficiency in the production process by systematically scheduling tasks and resources. – Will also set deadlines for all the different tasks to ensure smooth operations. – The diagram will help managers reduce productions costs. 2 HL

Network Analysis The ultimate purpose of network analysis is to identify the minimum amount of time needed to complete a project. Requires the various tasks to be planned in a logical and coherent way so that the different processes are completed with minimum delay and maximum efficiency. Critical Activities: “activities that cannot be delayed.” The process of network analysis, is also known as Critical Path Analysis (CPA). 3 HL

Critical Path Analysis (CPA) Critical Path Analysis (CPA) involves: 1. Identify all the operations required for the completion of a project. 2. Breaking down the project into separate jobs and tasks. 3. Determining how long each task will take. 4. Identifying all dependencies (“activities that cannot start until the completion of other jobs”). 5. Determining which tasks can take place concurrently to minimize production time. 6. Placing all operations in the right sequence and placing these on a network diagram. 4 HL

7. Determining Showing the earliest start time and the latest finishing time of each activity. 8. Identifying the critical path from the network diagram. [Critical Path: “the route which generates the minimum time needed to complete the whole project.”] Any hold-ups to the operations on the critical path of a network diagram will delay the completion of the project! 5 Continued… HL

Constructing Networks Key features shown in a CPA diagram: – Node – Shows the start and finish if each activity within the project. – Arrows – Are used to in a network diagram to show the duration of each activity or task. – EST (Earliest Start Time)– of each activity is shown in the top right-hand part of the node. Will depend on the duration of all previous activities. – LFT (Latest Finishing Time)– of each activity is shown in the bottom right- hand part of the node. Is the deadline for a particular activity to be completed so that the entire project can finish in minimal time. – Float – the difference between EST and LFT for each activity to identify any spare time that might exist. 6 HL

7 Continued… EST LFT Node Number Activity or task Duration of activity

8 HL Continued… A C B D E  Activities A and B can be started at the same time.  Activity C cannot be started until activity A is completed.  Activity D cannot be started until activity B is completed.  Once both activities C and D are completed (not necessarily at the same time), then activity E can start.

To construct a network diagram, consider the following steps: 1. Identify all the tasks involved in the project. 2. Order these in the correct sequence. 3. Identify tasks that can take place at the same time. 4. Design the network. 5. Identify the critical path. 9 HL Continued…

Example: 10 HL Continued… ActivityDescriptionProceeded by Duration ASend out invitations and wait for replies -7 BResearch and book suitable venue based on numbers A2 CBook entertainment (music and awards ceremony) B5 DOrder drinks and cake for deliveryB7 ESet up hall and stage for partyC, D3

How to calculate: (IBID book pg ) – Free and Total Float – Dummy Activities 11 HL Continued… NOTES !!

DummyDefinition A dummy activity is an activity that uses no time or resources, but is included in a network to maintain the logic of the diagram and the relations between activities 12

Advantages of Network Analysis (CPA) A. Provides a visual representation of a problem, thus it is easier for some people to understand. B. As a decision-making tool, encourages forward planning. C. Helps managers consider different aspects of a particular project. D. Promoted operational efficiency by identifying the critical path (shortest time and free float) and customers will get timely delivery of their order. E. Help firms have better cash flow management by identifying when certain activities can start and how long tasks should last. F. Prove useful for stock management, thus reducing storage costs and expenses of holding stocks. G. Useful for a range of business issues and problems. Works well with JIT production systems. 13 HL

Limitations of Network Analysis (CPA) 14 HL A. The construction of a CPA doesn’t guarantee that everything will go according to plan (ex: motivation levels are not considered). B. Is useful only if the data used to construct the network is accurate and reliable. C. If necessary steps are missed in the CPA, the critical path identified will be invalid. D. Constructing a CPA for huge-scale projects can be very complex, highly challenging and time consuming (some software programs are provided to facilitate the process).

Tips for Completing a Critical Path Diagram Start by looking at whatever activities are preceded by nothing (or a dash sign). All of those activities will come off the first node. Always leave the activity lines open until you know where the line might need to connect to, i.e. do not connect it straight away to another node – leave it open until you know where to move the line to next Once an activity line is connected between two nodes (i.e. the node it has started from and the node it connected to) it cannot be used again. If you need to use that activity line to connect somewhere else on the diagram to start another activity, then use a dummy line 15

Tips for Completing a Critical Path Diagram A dummy line can go in any direction just like a normal activity line. Make sure you put the arrow though as to which direction it is going once you decide. Remember, all dummies have a duration of 0. Sometimes you may have designed the lines alphabetically but then the lines end up having to cross through each other (see Buffer to Buffer example from class). If they start crossing through each other, just go back and rearrange the lines and try them in a different order (e.g. D, E, F may need to be changed to D, F, E in order to not make any activity lines cross each other) 16

Tips for Completing a Critical Path Diagram The first and last nodes always have the same numbers in both their respective EST’s and LFT’s – i.e. 0 and 0 for node 1 and the final node may have numbers such as 18 and 18 When going forward and calculating the earliest starting times, always choose the highest number When going backwards and calculating the latest finishing times, always choose the lowest number The dummy line can come anywhere off the activity line 17

Tips for Completing a Critical Path Diagram When calculating total float, the formula is Latest Finishing Time of the second node – Duration – Earliest Starting Time of the First Node (between an activity line) When calculating free float, the formula is Earliest Starting Time of the Second Node – Duration – Earliest Starting Time of the First Node (between an activity line) Remember free float will only tell you how many days you can delay an activity to where it wont delay the following activity, whereas total float will tell you how many days you can delay an activity to where it will not delay the total completion time of the project. If an activity’s total float answer is 0 then it is a critical activity and should be included in your critical path A dummy can be included in a critical path 18