1 LHC-DFBX DFBX Production Readiness Review Project Overview Joseph Rasson LBNL 23-24 October 2002, LBNL Brookhaven - Fermilab - Berkeley US LHC ACCELERATOR.

Slides:



Advertisements
Similar presentations
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Advertisements

24 Oct 2002 RFP Review1 DFBX Fabrication Activity at LBNL Jon Zbasnik LBNL.
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Coupling Coil Test Facility Update Ruben Carcagno Fermilab September 20, 2012.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Video Conference 114 September 18, 2008.
-1- Wang, Li The 23rd MICE Collaboration Meeting to 17 HIT/CHINA WANG, Li Institute of Cryogenics and Superconductivity Technology.
128 April 2008 Spectrometer Solenoid Fabrication Update MICO Meeting 19 May 2008 S. Virostek, M. Zisman LBNL.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #129 February 25, 2010.
9 June 2006MICE CM-15 Fermilab1 Progress on the MICE Cooling Channel and Tracker Magnets since CM-14 Michael A. Green Lawrence Berkeley Laboratory.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
Spectrometer Solenoids and Coupling Coils Primary Activities and Risks Going Forward Spectrometer Solenoids Completion of SS#2 magnetic mapping Completion,
MEBT & RT CH Section Thomas Page Fermilab Accelerator Advisory Committee May 10 th – 12 th, 2006.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab Roy Preece Rutherford Appleton Lab October 28, 2011 MICE Collaboration Meeting.
TIS Review 13 Dec Bill Elliott IR ABSORBER STATUS1 Bill Elliott LBNL Presented at the TIS SAFETY REVIEW 13 Dec Berkeley,CA brookhaven - fermilab.
DFBX Thermo-Mechanical Review
From Research Prototype to Production
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
US LHC Accel Proj Review October 2003 Joseph Rasson LBNL Project Manager 1 LBNL Project Overview Joseph Rasson Jon Zbasnik Bill Elliott LBNL Presented.
1 LHC-DFBX Shipping Specification Steve Virostek LBNL Presented at the DFBX RFP Review October 2002, LBNL Brookhaven - Fermilab - Berkeley US LHC.
Type IV Cryomodule Proposal (T4CM) Don Mitchell, 16 JAN 2006.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
Key Design Issues and Recent Reviews Tom Peterson, Fermilab DFBX PRR, October 23, 2002 US LHC ACCELERATOR PROJECT brookhaven - fermilab - berkeley.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
January 4, 2007 Project Overview RHIC II Project Internal Cost Review Roberto Than Cryogenics Systems January 4, 2007.
1 LHC-DFBX Fabrication Oversight Plan Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab.
Brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Inner Triplet Review Q1, Q2, and Q3 Mechanics T. Nicol April 24-25, 2007.
Spectrometer Solenoid Update Steve Virostek Lawrence Berkeley National Lab MICE Collaboration Meeting #28 Sofia, Bulgaria.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
Endcap Signal Feedthrough Overview Endcap Signal Feedthroughs are constructed and tested in Victoria by Victoria and TRIUMF staff. Each feedthrough unit.
MICE Coupling Coil Testing at Fermilab All Experimenters Meeting Ruben Carcagno March 19, R. Carcagno - MICE CC Testing at Fermilab3/19/2012.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Spectrometer Solenoid Fabrication Status and Schedule RF Cavity / Coupling Coil Module Plan and Progress Steve Virostek Lawrence Berkeley National Lab.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
MICE Prototype Coupling Coil Fabrication Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM38 - Napa California February 25, 2014 February.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
The integration of 420 m detectors into the LHC
DOE-QRT Review 12 Feb2004 Joseph Rasson LHC Project Update1 Joseph Rasson LBNL DOE LHC Quarterly Status Meeting at FNAL 12 February 2004 US LHC ACCELERATOR.
LAT-PR GLAST LAT ProjectManufacturing Readiness Review, Oct. 12, 2005 LAT Test Stand Manufacturing Readiness Review 1.Introduction Bill Olson.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
Cryomodule Safety Approvals Jay Theilacker LCLS-II Production Cryomodule Final Design Review May 12-14, 2015.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
12 GeV Project Status Glenn R. Young 12 GeV Project Status
2K Cold Box FDR Introduction
Roadmap for triplet cryostats
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
Spectrometer Solenoid Update
Teleconference ACS – FREIA 31st October 2017
Spectrometer Solenoid Fabrication Status and Schedule
2K CB FDR Overview:  Agenda, Charge, Review Process
SNS PPU Helium Vessel Design and Assembly
SNS PPU Cryomodule Vacuum Vessel
SNS-PPU upgrades the existing accelerator structure
SC1R Cold Box PDR Assembly Sequence
JLAB CHL 2K COLD BOX REPLACEMENT
Presentation transcript:

1 LHC-DFBX DFBX Production Readiness Review Project Overview Joseph Rasson LBNL October 2002, LBNL Brookhaven - Fermilab - Berkeley US LHC ACCELERATOR PROJECT

2 Outline  Functional Flow Diagrams  Design Variants  DFBX Components  Engineering Activities Since May 02 Review  Technical Design Reviews  Design Change Summary  Acceptance Specifications and Travelers  Crating and Shipping Specifications  Project Schedule  Summary

3 DFBX Functional Flow Diagrams IR Cryogenic and Electrical Distribution Box IP1 & IP5 IP2 & IP8

4 Design Variants  Eight cryogenic distribution boxes  6 Slightly different designs with many common components  Major variation results from connection to either cold or warm dipole

5 DFBX Components Major subsystems:  Power leads: HTS & VC leads  Vacuum vessel  Cryogenic piping  LHe vessel  Thermal shield  Power lead chimneys  Instrumentation leads  Super insulation

6 DFBX Components (cont.) Other subsystems:  Jacketed beam tube  Bus duct assembly:  Busses  Lambda plate  Bus duct  Interconnect hardware  Alignment tools  Support jacks

7 Engineering Activities Since May 02 Review Enhanced the Engineering Team in the following areas:  Mechanical design  Daryl Oshatz is leading the mechanical design effort  Added more designers (2 FTEs}  Engineering analysis  Steve Virostek is responsible for structural analysis  Lambda Plate R&D  SUPERCON technician group headed by Roy Hannaford is supporting Jon Zbasnik’s effort  Vapor Cooled Lead  SUPERCON group supporting the mechanical design and layout  Ron Scanlan prepared the lead design specification document

8 Engineering Activities Since May 02 Review (cont.) Fermilab Engineering Support:  Cryogenic Engineering  Tom Peterson is providing cryogenic design oversight  Don Brown (cryogenic consultant) provided reviewed the design  Interface Specification  Phil Pfund is very active in supporting the interface specification effort  Kerry Ewald is generating mechanical interface drawings  High Temperature Superconducting (HTS) Lead Testing  Sandor Feher will head the HTS testing effort at FNAL

9 Engineering Activities Since May 02 Review (cont.) Fermilab Engineering Support (cont.):  Procurement Effort  Review procurement documents  Participated in interaction with vendors  Reviewed proposal evaluation effort  Acceptance Criteria  Provided thorough review of acceptance plan  Jim Strait is negotiating the acceptance criteria with CERN

10 Recent Technical Design Reviews

11 Design Change Summary More Robust Mechanical Design:  Thrust loads and Pipe support  Most of pipe thrust loads were eliminated by use of flex hoses  Bus duct and overflow tank support were modeled and redesigned  Magnet G-10 spiders are no longer load path components  QRL G-10 spiders were simplified and stiffened up  Pipe thermal contraction  Thermal contraction up to 1 inch is possible with flexhoses

12 Design Change Summary (cont.) More Robust Mechanical Design (cont.):  Helium tank support  Added invar rods for vertical support  Redesigned lateral and longitudinal supports  Modified access panel and rib thickness  Modified weld preps to conform to ASME Pressure Vessel Code  Completed a detailed FEA model  Pressure Vessel Safety Note written and approved by LBNL Safety Committee

13 Design Change Summary (cont.) More Robust Mechanical Design (cont.):  Optimized thermal shield design and cooling  Added trace cooling channels  Reduces wall thickness of all panels except top panel  Simplified the design by eliminating complex forming  Reduced number of vertical supports  Give vendor more flexibility in forming and attaching panels

14 Design Change Summary (cont.) Enhance Design for Manufacturability:  More relaxed tolerances  Design intent is conveyed and moved tight toleranced to top level assemblies  Maintained tolerances that are tied to interface specifications  Give vendor more flexibility to manufacture pipe assemblies  Vendor can select construction and fabrication method  Vendor can substitute for elbows, T’s and rearrange routing  Simplify welding and assembly process  Added weld rings to address warping during welding which allows vendor to meet the design intent

15 Design Change Summary (cont.) Bus Duct and Lambda Plate R&D:  Completed R&D effort  LBNL fabrication and test plan has been developed  Bus duct assemblies will available at the cryogenic system 2 months before the first pair is needed

16 Design Change Summary (cont.) Beam Tube:  Beam tube cooling jacket design complete  Cold to warm transition layout is underway (to be completed Nov 02)  Bore tubes to be shipped to LBNL (Jan 03)  LBNL to fabricate and test beam tube assemblies then ship them to cryogenic system fabricator  Beam tubes are scheduled to be delivered 3 months before the first beam tube is needed for installation

17 Design Change Summary (cont.) Current Lead Splice Procedures:  Current lead splice process developed and prototyped  Used the DFBX mock-up to demonstrate the process  Issued purchase orders to the vendors to: 1.Transfer the technology by training the vendors before the RFP is released 2.Assess vendors’ capabilities 3.By making the vendors comfortable with the process, we remove uncertainties that could lead to bids  Roy Hannaford visited the vendors with tools and fixtures to train them  Both vendors showed good capabilities as demonstrated by the samples they produced on their own

18 Status of Mechanical Interface Specifications  Fermilab is supporting the magnet mechanical interconnect hardware design effort  Not all interconnect hardware proposals have been accepted by CERN yet  Reviewing dipole as-built pipe positions (some are out of tolerance)  Pipe ends will be capped since pressure and vacuum leak tests will be repeated at CERN  Therefore pipes will be fabricated with capped long stubs  Pipe ends will be measured and cut during installation at CERN

19

20 Status of the fabrication drawing package  Detailed fabrication drawing package for DFBX-G and C are released  Top level configuration drawings for the other 5 variations are complete  Bill of Materials is complete  All remaining unique pipe drawings ready for release by end of November

21 High Temperature Super Conducting Leads (HTS)  A total of 40 lead assemblies (20 lead pairs) are required  Full current tests of the prototype pair were performed at CERN in Nov 2001  Authorized Pirelli to start production in May 2002  Cold test facility is under construction at Fermilab

22 High Temperature Super Conducting Leads (HTS) (cont.) HTS Production Schedule:  Pirelli’s initial production schedule slipped 1.5 months  Latest Pirelli schedule as of 21 Oct: 1 st 5 FNAL Dec nd 5 FNAL Jan rd 5 FNAL Feb th 5 FNAL Mar  Leads for first box will be delivered to the vendor at least 4 months before they are needed

23 Vapor Cooled Leads  VC Leads required 16 sets of 600A-3pair 8 sets of 600A-1pair 8 sets of 120A-5pair  Lead design layout was revised to provide more installation clearance  Eliminated Fisher connectors (high cost and long lead time)  Ron Scanlan prepared the performance/design Specification  Specification was reviewed by CERN and FNAL  Design reviewed by vendors in August

24 Vapor Cooled Leads (cont.) Procurement Schedule: Issue RFQ7 Oct Bidder responses8 Nov Place order10 Dec 2002 Deliver leads for DFBX-GApr nd LBNLMay rd 2003  Leads for DFBX-G will be delivered to the vendor 3 months before they are needed for installation

25 Acceptance Specification and Traveler status LBNL acceptance from vendor:  Defines the tests and measurements required to meet functional and interface specifications  Defines in process inspection points that give the vendor flexibility in selecting the manufacturing process and assembly sequence  Defines the set of travelers to be completed by the vendor  LBNL final acceptance takes place after pressure and vacuum leak tests are completed at CERN

26 Acceptance Specifications and Travelers (cont.) CERN acceptance from US-LHC is based on:  Approval of LBNL-vendor Acceptance Specification,mainly: oIn-process tests and inspection oFinal test/inspection prior to shipping oInspection and tests at CERN after shipping  Approval of power lead Acceptance Specifications  Approval of LBNL-manufactured components Inspection Specifications  Completing a series of electrical tests at CERN:  Hi pot and continuity tests of leads, bus duct and instrumentation conduits

27 Crating and Shipping Specification  Requirements based on FEA of shipping package with appropriate safety factors:  Maximum vertical shock acceleration transmitted to DFBX +/- 5.0 g  Maximum horizontal shock acceleration transmitted to DFBX +/- 2.0 g  Free drop from a height of 6 inches without transmitting more than the vertical shock limit of 5.0 g  Crating and shipping specification document has been distributed to the vendors for review by their shipping subcontractors  Vendors feel comfortable with taking on the crating shipping responsibility

28 Project Schedule  Additional schedule constraints:  US-LHC Accelerator Project Ends September 2005

29 Project Schedule (cont.) Schedule forecast  Based on the LOI production schedule provided by the manufacturers:  First DFBX Delivered 13 month ARO oMeets CERN requirement  Last (8th) DFBX Delivered months ARO oMeets DOE-LHC requirement  However, production schedule is aggressive  To meet schedule extensive oversight is required  Highlights the urgency to get process started

30 Summary  Design team was enhanced  Fermilab is playing an active role in supporting the design effort  Mechanical design is more robust and simpler to fabricate and assemble  Detailed fabrication drawing package being readied for the RFP  LBNL components will be ready 2-3 months before need dates  HTS production has started  VC leads RFQ is released and order will placed in Dec 02  Project is ready to start the RFP process  Meeting production schedule is a major challenge