THEMIS MISSION PDROVERVIEW- 1 UCB, November 12, 2003 1. UCB/Swales should identify an individual that will assume responsibility for magnetic cleanliness.

Slides:



Advertisements
Similar presentations
Chapter 7: Key Process Areas for Level 2: Repeatable - Arvind Kabir Yateesh.
Advertisements

GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
Quality evaluation and improvement for Internal Audit
ISO Standard is based on the management model of plan – do - check – act. Today we all be discussing the elements of the standard that deal with.
Speed of Sound Team BalloonWorks. Table of Contents Mission Goal and Objectives Science and Technical Backgrounds Mission Requirements Payload Design.
THEMIS INSTRUMENT PER 1 UCB, May, 2005 EMC / Mag Instrument Test Plan & Results Michael Ludlam University of California - Berkeley.
GoetzFIELDS iPDR – I&T SPP/FIELDS Integration and Test Preliminary Design Review Keith Goetz University of Minnesota 1.
Magnetic Field Instrument for the BepiColombo Planetary Orbiter
Authorization and Inspection of Cyclotron Facilities Inspections.
20a - 1 NASA’s Goddard Space Flight Center Attitude Control System (ACS) Eric Holmes, Code 591 Joe Garrick, Code 595 Jim Simpson, Code 596 NASA/GSFC August.
NASA’s Goddard Space Flight Center Systems Engineering Mike Pryzby Swales Aerospace August 16-17, 2005.
THEMIS SRR Requirement Overview - 1 UCB, 07/08/2003 REQUIREMENT DEVELOPMENT OVERVIEW Ellen R. Taylor Mission Systems Engineer Space Science Laboratory.
MERMAG-M/MGF MGF-OS MGF-IS MAST-MGF MAST-SC PWI-SC Credit : RISH, Kyoto Univ.
THEMIS Instrument CDR(1) UCB, April 19 & 20, 2004 Mission Assurance Critical Design Review Ron Jackson University of California - Berkeley.
MPEREMC 1 UCB, June 23, 2006 THEMIS MISSION PRE-ENVIRONMENTAL REVIEW Probe 2 EMC Test Results David Curtis University of California - Berkeley.
THEMIS peer Instrument CDR 1 CETP, Paris, April 8, 2004 THEMIS Mission Status at Peer UCB Instrument Critical Design Review UCB, April 19/20, 2004 Vassilis.
DINO PDR 23 October 2015 DINO Systems Team Jeff Parker Anthony Lowrey.
1 Directed by: Dr. PJ Benfield and Dr. Matt Turner Mentor : Miss Doreen Forsythe.
THEMIS Mission PDR/CAR 1 UCB, November 12-14, 2003 Search Coil Magnetometer (SCM) Mission PDR/CAR Alain Roux CETP-Velizy Co-i: O.Le Contel Technical Manager:
MPSRAlignments - 1 UCB, Oct 26, 2006 THEMIS PROBE MISSION PRE-SHIP REVIEW Alignments Paul Turin LME University of California - Berkeley.
THEMIS FGM CDR Peer ReviewBerlin, April 6, 2004 THEMIS FGM Engineering Peer Review SC Integration and Test Ellen Taylor University of California - Berkeley.
THEMIS FGM CDR Peer ReviewBerlin, April 6, UCB/Swales should identify an individual that will assume responsibility for magnetic cleanliness on.
THEMIS Instrument FM2/FM3 PERFGM 1 Teleconference 8/30/2005 THEMIS Instrument FM2/3 Pre-Environmental Review Fluxgate Magnetometer (FGM) Dr Ellen Taylor.
THEMIS Mission PDR/CAR 1 UCB, November 12-14, 2003 Instrument Integration & Test Dr. Ellen Taylor University of California - Berkeley.
Dispensary and Administration Site Information Presentation.
THEMIS MISSION PDRMAG BOOM- 1 UCB, November, 2003 Magnetometer Booms (MAGS) Mission Preliminary Design Review Hari Dharan Space Sciences Laboratory University.
24b - 1 NASA’s Goddard Space Flight Center LRO Safety Dave Bogart Code 302 August 16-17, 2005.
THEMIS SUITE PRE-ENVIRONMENTAL REVIEW 1 UCB May 2, 2005 THEMIS Pre-Environmental Review Instrument Verification Overview Ellen Taylor University of California.
THEMIS IDPU PDR I&T REQUIREMENTS- 1 UCB, October 16, 2003 I&T REQUIREMENTS Ellen Taylor University of California - Berkeley.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
THEMIS INSTRUMENT CDR Peer ReviewSYSTEM- 1 UCB, April 19, 2004 TITLE: Test Flow RFA CODE: UCB-10 REQUESTED BY: Preble SPECIFIC REQUEST: We recommend that.
THEMIS MISSION PDROVERVIEW- 1 UCB, November 12, 2003 THEMIS MISSION SYSTEM OVERVIEW Dr. Ellen Taylor University of California - Berkeley.
THEMIS INSTRUMENT PDROVERVIEW- 1 UCB, October 15, 2003 THEMIS SYSTEM OVERVIEW Dr. Vassilis Angelopoulos, Science Overview Dr. Ellen Taylor, Mission and.
SWGTemplate- 1 UCB, Nov 15/16, 2006 THEMIS SCIENCE WORKING TEAM MEETING Search Coil Magnetometer (SCM) team Co-i: A. Roux, O. Le Contel Technical Manager(*):
Dec 1, FIELDS Top Level Requirements Review S. Harris (UCB)
SWT Overview 1 UCB, Nov15/16, 2006 THEMIS SCIENCE WORKING TEAM MEETING Mission Overview Peter R. Harvey Project Manager University of California - Berkeley.
FM1 Instrument Suite Pre-Ship Review (PSR)INT- 1 UCB September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) INTEGRATION AND TEST PLANS Jeremy.
THEMIS MISSION PDRINSTRUMENT OVERVIEW- 1 UCB, November, 2003 THEMIS INSTRUMENT PAYLOAD SYSTEM OVERVIEW Dr. Ellen Taylor University of California - Berkeley.
FM2 PPEREMC 1 UCB, March 16, 2006 THEMIS PROBE FM2 PRE-ENVIRONMENTAL REVIEW EMC Test Dave Curtis System Engineer University of California - Berkeley.
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
FM2/FM3 PSR FM4/FM5 PERSCM - 1UCB, November 10, 2005 THEMIS FM2/FM3 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) THEMIS FM4/FM5 INSTRUMENT SUITE PRE- ENVIRONMENTAL.
ITAR Restricted Data 1THEMIS Mission CDR 6/18/04 System Safety Overview WBS Element Tim Keepers (301)
THEMIS Instrument PDRMission Assurance- 1 UCB, October 15-16, 2003 THEMIS Mission Assurance Preliminary Design Review Ron Jackson University of California.
Characteristics of remote sensing satellites. Satellites generally vary in their architecture Usually remote sensing satellites are having two plateforms.
TRIO-CINEMA 1 UCB, 2/08/2010 Integration and Test Program Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley.
MPEREnvironmental Test OverviewUCB, June 23, 2006 THEMIS MISSION PRE-ENVIRONMENTAL REVIEW Environmental Test Overview and Logistics Rick Sterling University.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct 2, 2001 Darren Marsh1 I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist.
THEMIS MRRSystems - 1 GSFC, Jan 5, 2007 Systems Engineering.
THEMIS SRR Mission Requirements - 1 UCB July MISSION REQUIREMENTS Ellen R. Taylor Mission Systems Engineer Space Science Laboratory University.
FM1 Instrument Suite PSRSCM - 1UCB, September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) SEARCH COIL MAGNETOMETER (SCM) Michael Ludlam.
IDPU F1 Test Review FGM Fluxgate Magnetometer Michael Ludlam University of California - Berkeley.
FM4/FM5 IPSRSYS - 1 UCB, May 5, 2006 THEMIS INSTRUMENT SUITE FM4/FM5 PRE-SHIP REVIEW SYSTEM OVERVIEW Ellen Taylor University of California - Berkeley.
THEMIS Mission PDR/CAR 1 UCB, November 12-14, 2003 Instrument Design Fluxgate Magnetometer (FGM) Werner Magnes Institut fuer Weltraumforschung (IWF) Austrian.
EMC issues for cabling and racks layout design. (Belle II – Grounding) F.Arteche.
1 Auditing Your Fusion Center Privacy Policy. 22 Recommendations to the program resulting in improvements Updates to privacy documentation Informal discussions.
THEMIS MISSION PDROVERVIEW- 1 UCB, November 12, 2003 THEMIS MISSION SYSTEM OVERVIEW Dr. Ellen Taylor University of California - Berkeley.
Power Philip Luers NASA/GSFC Code 561 August 16-17, 2005.
Program Management Agenda
Solar Probe Plus FIELDS MEP iPSR SOC Marc Pulupa April 10, 2017
CINEMA System Engineering
Agenda. Solar Probe Plus FIELDS Main Electronics Package iPER Agenda Feb 2, 2017.
Search Coil Magnetometer (SCM) CDR/Peer review CETP-Velizy
Solar Probe Plus – FIELDS Verification Instrument mini-PER (V5)
THEMIS Mission Assurance
THEMIS INSTRUMENT SUITE
Science Requirements The FGM shall measure DC and low frequency perturbations of the magnetic field  see performance requirements The FGM shall measure.
Boom Electronics Board (BEB)
Solar Probe Plus FIELDS Instrument PSR - MEP Introduction
Instrument PDR Summary of Objectives
Presentation transcript:

THEMIS MISSION PDROVERVIEW- 1 UCB, November 12, UCB/Swales should identify an individual that will assume responsibility for magnetic cleanliness on the project. Bi-weekly magnetic telecons of the Magnetics Control Board are conducted between UCB, UCLA and Swales. UCB magnetic czar designee (Michael Ludlam) responsible for tracking issues, developing plans, filtering guidelines and budgeting requirements to the instruments and bus The MSE (Ellen Taylor) acts as the single point of contact for all communications UCLA is charged with an advisory role to the program, and the responsibility to conduct parts testing, modeling and training as needed. 2. a) Review the magnetic cleanliness requirement; Magnetics Control Board has reviewed the magnetic requirements as originally stated during the SRR and in Revision A of the MRD (thm_sys_001a_MRD). As a result, the DC magnetic noise requirement (M-31a) was relaxed from 1nT as stated at the SRR to 5nT with the understanding that the offset can be measured on the ground and on- orbit in the solar wind. The 5nT level is commensurate with ACS requirements (1deg at 300nT provides a good orbit arc for modeling) and, if measured, meets the Level 1 science req. In addition to the absolute DC offset, THEMIS mission objectives are also concerned with DC drifts (from Level 1 requirements, 1nT absolute knowledge and stability of 0.2nT over 12 hours is required). Therefore, a DC stability requirement was added. FGM PDR Peer Review RFA #1

THEMIS MISSION PDROVERVIEW- 2 UCB, November 12, b) Develop a magnetic cleanliness plan to meet the requirements set by the project; A Magnetics Contamination Control Plan has been developed and reviewed (thm_sys_002c_Magnetics Cleanliness). 2. c) Obtain concurrence of the relevant flight hardware developers on the plan; The Magnetics Contamination Control Plan is a controlling, signed document between UCB and Swales Requirements and guidelines detailed in the Plan have been used to develop the magnetic field emission requirements detailed in Probe Bus flight hardware specs. 2. d) Reviewed spacecraft systems level design for traditional sources of stray fields (solar array, current loops, grounding, latch valves, batteries, etc.); Specific aspects of the system design, including traditional sources of stray fields such as solar array layout and battery cell layout are reviewed and discussed during the bi-weekly mag telecons with the Magnetic Control Board. When adherence to requirements is threatened (e.g., loop current strength) or guidelines are violated by standard practices (e.g., small magnetic components within subsystems), the Magnetic Control Board provides evaluation, technical workaround, or exemption if deemed appropriate. In the case of exemption the offender is recorded and tracked to ensure proper mitigation (e.g., offending loop not operational during science, or magnetic component degaussing and characterization). FGM PDR Peer Review RFA #1

THEMIS MISSION PDROVERVIEW- 3 UCB, November 12, e) Maintain grassroots magnetics budget verified by some benchtop measurements; and UCB is maintaining the THEMIS magnetics budget. This budget is currently in spreadsheet form to track main offenders, materials, component testing and results. It is in the process of being ported to a DC tracking tool from JPL that UCLA is familiar with. 2. f) Verify that magnetic cleanliness requirements are met. THEMIS’s test and verification philosophy is commensurate with: early guidelines dissemination and training of personnel, main offenders recognition and risk mitigation, clear requirements specification and understanding across the program, specifications of magnetically clean parts and subsystems across the entire system. 3. At least one spacecraft should undergo magnetic mapping at a large coil facility where any stray fields can be characterized (spacecraft on/off, perm/de-perm) to establish compliance with +/- 1nT specification and provide basis for dealing with any non- compliance. Based on recommendations from this Peer Review, the THEMIS team is planning on testing P1 during environmental testing at GSFC. This test will ensure that the magnetic cleanliness contamination specifications have been met at a system-level, validating the analysis and component testing performed throughout the program. FGM PDR Peer Review RFA #1

THEMIS MISSION PDROVERVIEW- 4 UCB, November 12, 2003 REQUIREMENTDESIGN MRD Magnetics Requirements From THEMIS Magnetics Contamination Control Plan: Figure 2-1: FGM and SCM sensitivity at the sensor location (1m and 2m respectively). Ordinate is frequency measured in Hz. Abscissa is amplitude spectral density in nanoTeslas per root Hz. Figure 2-2: AC magnetic noise level requirement (solid curves) and goal (dashed curves) at 1m from the spacecraft. Ordinate is frequency in Hz. Abscissa is amplitude spectral density in nanoTeslas per root Hz. M-30: AC magnetic noise radiated by the Probe and other instruments shall not exceed the following levels at 1 meter from the Probe: <30pT/sqrt(Hz) at 1Hz; <1pT/sqrt(Hz) at 10Hz; <0.1pT/sqrt(Hz) at 1kHz; and <0.1pT/sqrt(Hz) in range 1-10kHz Compliance. Magnetic requirements, guidelines and verification plan provided in THM-SYS-002 Magnetics Contamination Control Plan.

THEMIS MISSION PDROVERVIEW- 5 UCB, November 12, 2003 REQUIREMENTDESIGN M-31a: DC magnetic field generated by the Probe and other instruments shall not exceed 5nT at 2 meters from the Probe (location of FGM). M-31b: DC magnetic field generated by the Probe subsystems and other instruments shall be stable to <0.1nT at 2 meters from the Probe (location of FGM) Compliance. Magnetic requirements, budget, guidelines and verification plan provided in THM- SYS-002 Magnetics Contamination Control Plan. M-32. All THEMIS elements shall comply with the Magnetics Cleanliness standard described in the THEMIS Magnetics Contamination Control Plan. Compliance. THM-SYS-002 Magnetics Contamination Control Plan in review. Verification Matrix to be completed. Magnetics Requirements

THEMIS MISSION PDROVERVIEW- 6 UCB, November 12, 2003 Magnetics Control Board Established (Michael Ludlam, UCB; Vassilis Angelopoulos, UCB; Ellen Taylor, UCB; Tom Ajluni, SA; Ginger Robinson, SA; David Jeyasunder, SA; Bob Snare, UCLA; Chris Russell, UCLA; Joe Means, UCLA ) Bi-weekly meetings held to coordinate all relevant activities Main Offenders List and Preliminary Magnetics Budget Established Budgeting was based on a survey of THEMIS components and identifying the main offenders listed below in decreasing order for each group: Special considerations and activities to be taken (testing, modeling, analysis) for each of these major offenders are described in Magnetic Contamination Control Plan Magnetic Verification and Test planning in progress Added P1 EMC/EMI/MAG Verification and Calibration Test Mag Cleanliness Program Hard Perm FieldsLatch valves, Thruster valves, Tanks, Motors, SST magnets Soft Perm FieldsMu metal shielding, welding Stray FieldsSolar panels, Current loops (power cables), Battery, RF components AC FieldsSolar panels, Power converters