XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010 DEVELOPMENT AND EVALUATION OF SCENARIOS FOR INTEGRATED SOLID WASTE MANAGEMENT SYSTEMS IN SELECTED REGIONS IN BULGARIA T. LOLOS, G. TAVOULARIS, B. LYKAS, C. TSOMPANIDIS, G. LOLOS & R. SIMEONOVA
GENERAL OBJECTIVE: Support the preparation of a sound project pipeline for the environmental sector as a prerequisite for the absorption of funds available for the environmental sector and the improvement of the environmental infrastructure of the country according to EU standards. SPECIFIC OBJECTIVES Update the regional waste management systems according to EU legislation; Prepare solid feasibility studies (preliminary designs, CBA study procurement plan); Prepare detailed designs and tender documents ; Construct viable waste management projects. LEVSKIVELIKO TARNOVOBOROVOVARNA XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Development of waste management scenarios and assumptions Main objectives for the development of the Investment Programs for the necessary infrastructures: ensure compliance with the national and EU legislation; ensure affordable long term project planning and optimal utilisation of EU funds; define a long-term, cost-efficient, waste management investment plan. contribute to the national commitments and compliance of the infrastructures with the National Waste Management Programme XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Current situation of waste management in Bulgaria Landfilling of waste - most of the landfill sites do not fulfil the specifications of the Landfill Directive; Closing and rehabilitation of non-conforming sites is still pending; Waste recycling, treatment and disposal facilities will be implemented in 23 regions; Mandatory targets for 50% municipal waste recycling by XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Current situation regarding waste collection and disposal in the assessed regions Transportation takes place by both modern vehicles and older skip carrying trucks; Waste management operations are performed by private or municipal owned companies; Waste is disposed in local, unprotected municipal landfills and have their permit officially prolonged until end of 2009 or until the new regional landfills are constructed No sealing works or other pollution abatement technical works were envisaged for the current disposal sites; Pollution risks of varying levels were identified; Both municipal and Construction & Demolition (inert) waste is accepted for disposal; Many of the sites are neighboring to a surface water aquifer, with direct discharge of leachate. The municipal dumpsites will be closed, covered with an impermeable layer and rehabilitated, following a detailed design study. ! XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
ParameterVeliko TarnovoVarnaLevskiBorovo Total average income per cap, € Expenditures on waste management, €/t 44,745,932,729,6 Expenditures in waste collection - transportation 62%67%68%51% Expenditures in landfilling 9%16%12% Waste tax / cap, € 20,213,54,94,5 Population Waste generation, t/y Selected Economical-Social Parameters of Studied Regions XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Scenario 1Scenario 2Scenario 3 Collection of residuals1 bin for mixed waste 2 bins(for mixed and organic waste) (in Varna) Collection of recyclables - From the Recovery Organisations - From Civic Amenity Sites (Aksakovo and Beloslav) - From the Recovery Organisations - From Civic Amenity Sites (Aksakovo and Beloslav) Collection of bio-waste- 85% Green waste from parks and households - Organic from CAS (Aksakovo and Beloslav) - 85% Green waste from parks and households - Separate collection through bio-bins in selected points (markets, restaurants, etc) and households (in Varna) - Organic from CAS (Aksakovo and Beloslav) Collection of hazardous household In landfill siteIn Civic Amenity Sites and in landfill site In Civic Amenity Sites and in landfill site Home –compostingNoYes, 4% of BDW Transfer StationNo Sorting Station (MRF)No TreatmentComposting of green waste (open system) Existing MBT Plant. Recovery of i) recyclables and/or RDF and ii) Compost-like output Composting of green waste (open system) Existing MBT Plant. Recovery of i) recyclables and/or RDF and ii) Compost-like output Composting of green waste (open system) Existing MBT Plant. Recovery of i) recyclables and/or RDF and ii) Compost-like output Treatment of C&DC&D waste recycling facility Landfill site“Vaglen” Closure of dumpsitesIn situ rehabilitation or waste transport to a compliant landfill, according to legislation XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010 Overview of Alternative Options for WMS in Varna Region
Waste Management Scenario 2 - VARNA XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Waste Management Scenario 3 - VARNA XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Mass Balance of selected Waste Management System (Scenario 1) in Varna Option 1 has been ranked as the best among the three and selected, satisfying all set criteria: Mixed waste is treated in the PPP Mechanical-Biological Treatment Plant; Packaging waste recovery is promoted by the Recovery Organizations; Home composting of biodegradable waste is promoted in rural areas of the region. Green Waste is separately collected and composted in the Composting Facility within the Regional Waste Management Centre
Total Biodegradable waste in tons Quantity of biodegradable waste allowed for landfilling relative to 1995 BDW quantity Year National Target - BDW allowed to landfill TARGET ACHIEVEMENT - BDW landfilled Scenario 1Scenario 2 Scenario 3 tons/year% of 1995 BDW quantitytons/year% % % % ,00% ,67% ,67% % ,00% ,65% ,65% % ,55% ,12% ,12% YearRegional targetScenario 1Scenario 2Scenario ,17%59,1359, ,37%59,5259, ,00%60,0660,54 XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010 National Target Achievement for Biodegradable Waste Allowance to Landfill – VARNA REGION Regional Targets and Target Achievement for the Recycling of Municipal Waste
Preliminary Investment Cost for Alternative Waste Management Scenarios– VARNA REGION XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Overview of Alternative Options for WMS in Veliko Tarnovo Region Scenario 1Scenario 2Scenario 3 Collection of residuals1 bin for mixed waste2 bins(for mixed and organic waste)1 bin for mixed waste Collection of recyclables- From the Recovery Organisations - From Civic Amenity Sites (one in each municipality) - From the Recovery Organisations Collection of bio-waste- 85% Green waste from parks and households - Organic from CAS - 85% Green waste from parks and households - Separate collection through bio-bins in selected points (markets, restaurants, etc) and households - 100% Green waste from parks and households Collection of hazardous household In Civic Amenity Sites and in landfill site In landfill site Home –compostingYes, 30% of rural BDW Transfer StationNo Sorting Station (MRF)NoYesYes, included in MBT TreatmentComposting of bio-waste (open system) Composting of bio-waste (open or closed system) MBT Plant. Recovery of i) recyclables and/or RDF and ii) Compost-like output Landfill site“Sheremetya” Closure of dumpsitesIn situ rehabilitation or waste transport to a compliant landfill, according to legislation The described options are consistent with the core principles of waste hierarchy, the producer responsibility, the polluter pays and eventually the central target Europe to become a “recycling society”. ! XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Waste Management Scenario 1 – VELIKO TARNOVO XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Waste Management Scenario 2 – VELIKO TARNOVO XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Mass Balance of selected Waste Management System (Scenario 3) in Veliko Tarnovo Option 3 has been ranked as the best among the three and selected, satisfying all set criteria: Mixed waste is treated in a Mechanical-Biological Treatment Plant with the recovery of recyclables, secondary fuel RDF, stabilised organic matter and residues; Packaging waste recovery is promoted by the Recovery Organizations; Home composting of biodegradable waste is promoted in rural areas of the region. XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Comparison of Scenarios’ National and Regional Target Achievement VELIKO TARNOVO YearNational targetRegional targetScenario 1Scenario 2Scenario ,00%14,42%38,5149,3151, ,00%34,36%38,7849,6652, ,00% 38,8549,4652,60 XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Total Biodegradable waste in tons Quantity of biodegradable waste allowed for landfilling relative to 1995 BDW quantity Year National Target - BDW allowed to landfillTARGET ACHIEVEMENT - BDW landfilled tons/year % of 1995 BDW quantity Scenario 1Scenario 2 Scenario 3 tons/year% % % % ,15% ,24% ,99% % ,16% ,01% ,71% % ,99% ,71% ,92% National Target Achievement for Biodegradable Waste Allowance to Landfill Veliko Tarnovo Region XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Scenarios’ Economic Evaluation with Dynamic Prime Cost (DPC) Indicator Considered Parameters: Investment Cost Operational & Maintenance Cost Lifetime of Proposed Solution Ecological Effect (Waste Collection &Treatment) DPC - index of discounted (present) value of all costs at real prices divided by the discounted quantity of waste and thus suitable for comparing different environmental solutions under Net Present Value terms DPC:Dynamic Prime Cost, KIt:Investment expenditures in year t, KEt:Operation & Maintenance costs in year t, EEt:waste collected and treated in year t, i: the discount rate, that was taken 6% per annum n:lifetime of an investment. XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Comparison – Investment Costs vs. Scenario Performance VELIKO TARNOVO REGION XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Dynamic prime Cost (Indicator for Cost Effectiveness) VELIKO TARNOVO REGION Scenario 1Scenario 2Scenario 3 Total Dynamic prime cost 162,94215,57214,19 Dynamic prime cost waste treated 39,6958,2974,57 Dynamic prime cost waste collected / transported 70,0273,5568,43 Dynamic prime cost waste landfilled 53,6861,0862,08 XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Veliko Tarnovo – Dynamic Prime Cost Scenario 1Scenario 2Scenario 3 Total Dynamic prime cost, €/t 67,284,788,4 Decision Making Factors Environmental Technical Social Financial Least cost Best overall performance after Multi-Criteria & Sensitivity Analysis XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
SCENARIO 1SCENARIO 2SCENARIO 3 Environmental objectives30% To ensure prudent use of land and other resources15%82,5084,75 Depletion of resources, such as water and energy30% Necessary landspace20% Diversion of biodegradable waste from landfill25% Rate of material recovery25% To reduce greenhouse gas emissions15% Greenhouse gases emitted100% To minimise adverse impacts on air quality and water25% Extent of odour problems20%80 90 Wastewater generation30%90 85 Generation of leachate during the landfilling of the residues50% To protect local amenity15%80 Extent of noise, litter and vermin problems100%80 5To conform with waste policy and legislation30%80,092,597,5 Diversion of biodegradable waste from landfill50% Recovery of packaging waste50% Implementation Objectives30% To ensure absorption of secondary products20% Maturity of market for secondary products (number of recycling companies, potential for compost use in agriculture etc100% To ensure public acceptance30% Level of public acceptance100% To ensure public participation30% Level of risk for the public not to participate efficiently in the system100% To implement optimum systems20% How proven the technologies used are, simplicity and flexibility of system, modular100% Financial Objectives40% To minimize costs of waste management100%9080 Costs of collection, management, disposal and material and energy revenues100%9080 Score 82,6180,0685,91 Veliko Tarnovo – Overall Performance of Alternative Options
Multi-criteria analysis – Veliko Tarnovo The diagram illustrates in linear form the scores of each alternative scenario. The X-axis is the EWF and hence each point determines the FWF as well. The performance of each scenario alters depending on the value of the EWF Option 3 is qualified as the preferred scenario for new waste management system and the further feasibility study is based on it Scenario 1Scenario 2Scenario 3 Environmental / technical performance 86,4689,15100,00 Financial performance 100,0089,00 XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Discussion- Conclusions A basic engineering design has taken place, consisting of: Technology selection; Pre-dimensioning of the facilities and calculation of necessary area; Investment, operational and unit costs for the entire lifetime of the waste management system were identified Calculation of Discounted Expenditures with the index of Dynamic Prime Cost as €/tn of waste Cost effectiveness of the three scenarios; Multi-criteria analysis evaluation of the three options, based on environmental, institutional and financial criteria. XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Regional recycling targets set: Sustainability, better public services and environmental protection through the proposed investments; Compliance with the National Waste Management Programme ; A long-term, cost-efficient, waste management development plan. XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Veliko Tarnovo Region, Sheremetya Site
Updated Investment Cost for Integrated Waste Management Center – VELIKO TARNOVO REGION XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010
Affordability of project at municipal level Payments do not exceed 1% of the monthly average income for households Levski: 172 BGN/tn waste or 90 BGN/household-y; Borovo: 198 BGN/tn waste or 85,6 BGN/household-y Veliko Tarnovo: 142 BGN/tn waste or 66,57 BGN/household-y; Varna: 123 BGN/tn waste or 94,65 BGN/household-y. XI International Symposium WASTE MANAGEMENT – ZAGREB 2010 Zagreb, Croatia, November 25th and 26th 2010