Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.

Slides:



Advertisements
Similar presentations
M.N Minard SPD cabling overview SPD cable chain & tray SPD cable chain & tray Motorisation PS/SPD Motorisation PS/SPD Work on PS Work on PS.
Advertisements

AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop.
Walls crates cables gas chambers electronics CERN adb.
Laboratoire de l’Accélérateur Linéaire (IN2P3-CNRS et Université Paris-Sud 11), Orsay, France Olivier Callot 21 September 2005 Calorimeter Configuration.
LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation.
Yu. Guz 18/12/20061 HCAL commissioning: status and plans Yu. Guz, IHEP, Protvino Outline 1. current status of HCAL a)CW+PM b)signal cables c)LED monitoring.
Preparation of SPD Cabling Calo comissioning meeting – 19th July 2006 – CERN I.Status of cables II.Cable reels III.Labelling IV.Cabling inside a VFE box.
HCAL Fall meeting Oct 11 to 13, 2004 HF assembly, commissioning and integration Ianos schmidt The University of Iowa.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester July 8, 2013.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Laboratoire d’Annecy-le-vieux de Physique des Particules, France Cyril Drancourt Tuesday 16 September 2003 Optical link in Calorimeter DAQ: Link FEE(CROC)
1 Status of the calorimeter PMT’s time alignment LHCb CALO meeting Anatoli Konoplyannikov /ITEP/ Introduction Development status of the PMT time.
DVCS-2 Assembly & Installation Charles Hyde DVCS Collaboration Meeting 18 December 2009 Clermont-Ferrand.
Dec. 19, 2006TELL1 commissioning for Calorimeters 1 TELL1 commissioning for calorimeters ■ Reminder ■ TELL1 status ■ ECS for TELL1- PVSS panels ■ Firmware.
Calo Piquet Training Session - Xvc1 DCS and DSS Cuvée 2015 – RUN2 Xavier Vilasís-Cardona.
Test beam setup: status report 31/03/2009 M. Alfonsi (CERN)
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
E.Guschin (INR,Moscow) 17 July 2007 CALO commissioning group meeting CERN Status of PS/SPD LED system.
PS VFE & PS/SPD FE Electronics Status and Plans 21 November 2007 LPC Clermont.
04ABR07Calo Commissioning Meeting - Xvc1 Power Supplies Xavier Vilasis-Cardona.
DSS  Informal review Tuesday 24 th October 10:00 Room , organized by Laurent Roy.  Subsystems will not be allowed to run overnight or at weekends.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
SPD cabling issues I.Cable status II.Cabling inside VFE box III.Cable through chains (Gael) IV.Data spare cables V.Control bundles VI.Information for cabling.
CALO Commissioning Plans Pascal Perret LPC Clermont 17 March 2008.
PS VFE & PS/SPD FE Electronics Status and Plans 20 February 2008 LPC Clermont.
S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
PS VFE & PS/SPD FE Electronics Status and Plans 16 January 2008 LPC Clermont.
1 Calorimeters LED control LHCb CALO meeting Anatoli Konoplyannikov /ITEP/ Status of the calorimeters LV power supply and ECS control Status of.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
SB 1 Cables from PP to calorimeters Cabling being done by ITEP-Moscow and IAP-Bucarest team Summary for cables/connectors list, rack wizard.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
Yu. Guz 21/04/20061 Database usage by calorimeters Yu. Guz IHEP Protvino.
S.MonteilPS/SPD COMMISSIONING1 OUTLINE 1)STATUS SUMMARY. 2)PLANS AND OPERATIONS FOR THE NEXT MONTH. 3)CONCLUSION. COMMISSIONING MEETING – NOVEMBER 2007.
26/May/2008Calor LHCb Preshower(PS) and Scintillating pad detector (SPD): commissioning, calibration, and monitoring Eduardo Picatoste Universitat.
Extended Pid in PHENIX (assembly and integration ) 7/28/03 CDR review 07/28/2003, presented by E.Kistenev.
SPD VFE installation and commissioning (status and plans) I.Summary of VFE installation II.Stand alone VFE test: noise & offset III.Stand alone test: LED.
Tile HCAL status Felix Sefkow CALICE Technical Board Review April 19, 2007.
1 PS cabling status and planning Overview Rustem DZHELYADIN (CERN&IHEP, Protvino) PS-Cabling: what has been done : 1.PS/C top cable tray (3days)installed.
SPD VFE installation and commissioning (status and plans) I.Status of VFE test at Barcelona II.First commissioning experience at CERN (15 th -16 th March)
S.MonteilPS/SPD COMMISSIONING1 OUTLINE 1)PROGRESS REPORT. 2)PLANS. 3)CONCLUSION. COMMISSIONING MEETING – JUNE 2008.
Installation of the T600 at Fermilab CSN2, September 22,
14 February 2007 G. Bohner, R. Bonnefoy, M. Crouau, P. Jacquet, C. Lacan, J. Lecoq, S. Monteil, P. Perret, G. Reinmuth, K. Suchorski LPC Clermont PS Very-Front-End.
1 Status of Validation Board, Selection Board and L0DU Patrick Robbe, LAL Orsay, 19 Dec 2006.
SPHENIX MECHANICAL D. Lynch September 11, AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.
1 ECAL/PRS quality check with LED system Outline  Introduction, how to use LED time scan data for a detector quality check;  Last collected data of the.
Calorimeter global commissioning: progress and plans Patrick Robbe, LAL Orsay & CERN, 25 jun 2008.
1 ECS CALO LED Control System CALO Piquet Training Session Anatoli Konoplyannikov /ITEP/ Outline  Introduction  Calorimeter ECS LED monitoring.
Piquet report Pascal, Yuri, Valentin, Tengiz, Miriam Calorimeter meeting 16 March 2011.
1 hcal installation and commissioning status pawel de barbaro, vitali smirnov, june 11, 2007.
CALO News Pascal Perret LPC Clermont 23 October 2011.
SPHENIX Mechanical Don Lynch & Rich Ruggiero April 10, 2014.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
E.Guschin (INR,Moscow) 26 February 2008PS/SPD commissioning meeting CERN PS/SPD LED monitoring system status Tuning of SPD ‘C’ side: We concentrated our.
30/March/2009SPD commissioning activities1 SPD status (1)Electronics tests (2)Control/clock cables problem (3)Plans Calo commissioning activities meeting.
CALO News Pascal Perret LPC Clermont 22 January 2012.
20OCT2009Calo Piquet Training Session - Xvc1 ECS Overview Piquet Training Session Cuvée 2009 Xavier Vilasis.
E.Gushchin,S.Filippov(INR,Moscow) 16 April 2008Calo commissioning meeting CERN PS/SPD LED monitoring system status General status LED signal is used for.
DCal-ALICE integration and installation plan and status A. Tauro.
21 November 2003Jacques Lefrancois1 HOSTING ELECTRONICS AND CONNECTIVITY Role of calorimeter system: Level 0 trigger +  reconstruction +e/  id. Level.
1 04 April 2007 L. Roy Detector Safety System for infrastructure - General fire detection (barracks, cavern) - Sniffer system (smoke detection above the.
23MAY07Xvc - Calo ECS Working Group1 Calo FSM hierarchy and structure Xvc.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
1 Calorimeter LED & LV - HV control systems LHCb CALO meeting Anatoli Konoplyannikov /ITEP/ Outline Status of the calorimeters LV & MV power supplies.
Update on ‘Real estate’ for Level-0
CMS Area Working Group Meeting
LHC Experimental Vacuum Systems Status October ‘07
Presentation transcript:

Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006

Overall Planning  Overall infrastructure  Installation C-side: Priority.  Installation A-side  Commissioning before beams  Commissioning with beams 2007 and … Many tasks have no date or length attached to them. In particular A-side installation. We will learn more about duration of VFE-FE cabling tasks with PS Top cabling. Links have to be established carefully.

Specific issues PS/SPD  PS needs 25 more trigger cables installed on detector. Access.  PS and SPD need light tightening with Kevlar/Al foils(?). Access. During SPD/PS cooling work?  Request to check light tightness before VFE installation.  PS/SPD cable tray material not long enough. Welding? Delay?  Before VFE-FE cabling: Lower SPD/Guidance, alignment, cooling, RICH 2 platform for cable reel storage.  Is presence of racks on ECAL platform compatible with VFE-FE cabling? Yes, maybe move ECAL from time to time.  LED control drivers under development. Start manufacturing: January  Need to design and build mechanical support for radioactive source spectrometer for checking SPD/PRS in situ.  Detector access for cooling installation?  Cooling circuits and distribution from Main to detector: Who? When? How long? Manifold location?

PS/SPD cabling sequence  Sequence: C-side PS TOP, PS BOT, SPD TOP, SPD BOT, then A-side  Receive cable tray material: end of September.  Assemble into required lengths.  Connect to distribution cooling pipes before( or during) installation.  Install fixture (“potence”) for supporting PS cable chain.  Install water retaining trough and racks on ECAL platform.  Install ECAL gallery.  PS cooling installation requires: PS closed, and ECAL and (maybe) HCAL open. for access to PS.  If HCAL needs to be moved, this operation must wait end of ECAL cable (PMT end) repairs.  Install “passerelle” between two ECAL arrays for access to PS. (Muon group design). Approval by safety. Also ladders or scaffolding for bottom boxes.  Install cooling inside SM boxes.  Install distribution to these boxes along TOP and BOT, maybe already connected to cable trays or after cable tray installation.  Install lateral distribution TOP to BOT connecting pipe.  Test for leaks with gas system.  SPD cooling installation requires: SPD open, and PS, ECAL closed. Cooling installation: 1 week per half detector after infrastructure in place.

 RICH2 platform installation.  Cable reels must be ready by then.  Chariot and rails for PS cable chain installed.  Pull cables from TOP PS to storage 1 on RICH platform.  Install Cable chain for PS.  TOP PS cables through cable chain to storage 2.  BOT PS cables to storage 1.  Then, through cable chain to storage 2.  Move cable chain.  Storage 2 to ECAL platform.  Repeat for SPD.

Specific ECAL/HCAL issues  ADC cables repairs finished ~end of September/beg. October.  ECAL PMT end repairs CRYO side finished end of September. Extra person as of mid-September. A-side?  HCAL radioactive source safety approval and commissioning.  HCAL integrators, Pin diode/LED blocks installation.  ECAL racks need water leak testing before installation. Pressure? Flow? Little info available from Wiener.  Installation of remaining back planes for A-side end of September.  Sequence: PS cable chain support, Retaining “bac”, racks, gallery.  Do we install available FE cards in 156 or on platform?  Schedule of testing of FE on platform: Interference with VFE-FE cabling?  Should we start testing with racks on A-side while C-side is being cabled?  Temporary power and cooling availability on platform?  Any need for a PC ?  When do we need CRACK?  TELL1 availability for CRACK? Firmware?  Suggestion: Form a little group to plan the CRACK and TELL1 tests.

Debugging, testing  ECS control of electronics, HV, etc….  Data bases: Calo specific and configuration. Later conditions.  DAQ: TELL1 firmware.  Beyond TELL1? Farm? Software ?

Cabling  Cables patch panel to fixed point, fixed point to platforms. Procedure? Manpower?  Connectors?