Discussion of Market Participant Choice for Transmission Connections Stakeholder Session October 14, 2011.

Slides:



Advertisements
Similar presentations
Reliability in the International Arena Alberta Perspective
Advertisements

1 WECC/AESO Membership and Coordinating Operating Agreement WECC Board of Directors Meeting December 2007 Diana Pommen Director Interjurisdictional Affairs.
Cleco Transmission Planning Summit Attachment K November 15, 2007 Terry Whitmore.
Behind the Fence and Contract Change Stakeholder Update September 18, 2012.
Federal Energy Regulatory Commission Large Generator Interconnection Order on Rehearing (Order No A) RM March 3, 2004.
THE STANDARDS DEVELOPMENT PROCESS STEP 1 PUBLIC AND COMMITTEE PROPOSAL STAGE PUBLIC AND COMMITTEE PROPOSAL CLOSING DATE FIRST TECHNICAL COMMITTEE MEETING.
Electricity planning and approval in Alberta Laura Bowman staff lawyer Environmental Law Centre January 7, 2010 Bill 50.
New Cost Estimate Template Issued: December 11, 2014 Effective: January 5, 2015.
Why TADS Is Needed No systematic transmission outage data collection effort exists for all of North America Energy Information Administration data (Schedule.
Does owning a solar array make you a utility?...and other questions A presentation to the Kentucky Environmental Quality Commission Andrew Melnykovych.
Transmission Corridor Zone Designation Process Terrence O'Brien, CEC December 11, 2007 Energy Action Plan.
Energy Storage in California’s Grid of the Future Don Liddell, Douglass & Liddell Co-Founder and General Counsel, California Energy Storage Alliance ​
THE POWER OF POSSIBILITY Electric Transmission System Development in Alberta Neil J. Brausen, P. Eng., Director System Planning APEGGA Calgary Branch Luncheon.
Reliable Power Reliable Markets Reliable People Reliable Power Reliable Markets Reliable People Interconnection Queue Business Practices Stakeholder Consultation.
Fair, Efficient and Open Competition Regulation Metropolitan Centre August 28, 2009 Preferential Sharing of Records Not Available to the Public.
INSAG DEVELOPMENT OF A DOCUMENT ON HIGH LEVEL SAFETY RECOMMENDATIONS FOR NUCLEAR POWER Milestone Issues: Group C. Nuclear Safety. A. Alonso (INSAG Member)
Federal Energy Regulatory Commission Proposed Rule on Small Generator Interconnection RM July 23, 2003.
Reliable Power Reliable Markets Reliable People ISO Rules Update – – Outage Cancellation – Long Lead Time Energy Dispatch Compliance.
Federal Energy Regulatory Commission Large Generator Interconnection Final Rule RM July 23, 2003.
Ontario Overview Dave Short Senior Regulatory Analyst, Regulatory Affairs IESO’s ERO Workshop – June 28, 2006.
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N 1 Network Operating Committee (NOC) June 12 th, 2014.
PacifiCorp Participation in the California ISO. 2 Full participation provides significant benefits beyond those of the Energy Imbalance Market EIM BenefitsFull.
The role of ERE in Costumer Protection Eduard Elezi Albanian Regulatory Authority ERE Conference “Albanian Energy Sector, Challenges and Regulation” Tirana,
Implementation Issues of Sarbanes-Oxley CASE Presentation September 23, 2004 By Denise Farnan.
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
RENEWABLE ENERY & BIOMASS COGENERATION TRAINING – KENYA BY LEWIS B. MHANGO.
E P D K 1 Turkish Electricity Market and Recent Developments Cemal Çelik Energy Expert EMRA-TURKEY March ANTALYA.
Texas Regional Entity Update Sam Jones Interim CEO and President Board of Directors July 18, 2006.
October 8, 2003Ontario Energy Board1 Ontario Energy Board Update E.A. Mills Director – Regulatory Affairs Market Advisory Committee October 8, 2003.
Large Generator Interconnection Procedures Reform Stakeholder Meeting February 19, 2009.
Powering Alberta AESO Annual General Meeting May 14, 2009 Reliable Power Reliable Markets Reliable People.
Liberalization of Electricity Market in Taiwan Su, Jin-sheng Energy Commission Ministry of Economic Affairs August 8, 2001.
OSC Meeting April 27, Transmission Cost Allocation Overview.
Overview of WECC and Regulatory Structure
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
Renewable Generation Interconnection Ken Brunkenhoefer Distributed Generation Consultant
Iowa State University Ames, IA July 5, 2011 Wind on the Wires – Wind and Transmission Issues Beth Soholt Wind on the Wires
1 Overview of Reliability Requirements XYZ Cooperative Date: abc.
The Electric Reliability Organization: Getting from here to there. Gerry Cauley Director, Standards ERO Project Manager ERO Slippery Slope NERC Today Uphill.
The Energy Policy Act of 2005 and Its Revisions to PURPA November 11, 2005 Grace D. Soderberg Assistant General Counsel National Association of Regulatory.
ATC Planning Zone Meeting Teresa Mogensen Director, Transmission Planning & Service Scott Barnhart Manager, Transmission Planning.
Reliable Power Reliable Markets Reliable People Transition of Authoritative Documents – Information Session September 2009 Doyle Sullivan Evelyn Kelly.
Role of the Commission and Recent Policy Actions Interconnection Workshop Carol Revelt Utah Public Service Commission December 4, 2007.
Reliable Power Reliable Markets Reliable People RAS Guideline Initiative March 23, 2009.
Reliable Power Reliable Markets Reliable People AESO Integrated Market Roadmap March 2009 Stakeholder Session.
Utah Geothermal Power Generation Workshop Regulatory Issues August 17, 2005 Presented by Becky Wilson Utility Economist Utah Public Service Commission.
International Atomic Energy Agency Roles and responsibilities for development of disposal facilities Phil Metcalf Workshop on Strategy and Methodologies.
Reliable Power Reliable Markets Reliable People Hanna Region Transmission Development Ramaiah Divi, P.Eng Manager, Central System Planning.
Page 1 of 13 Texas Regional Entity ROS Presentation April 16, 2009 T EXAS RE ROS P RESENTATION A PRIL 2009.
Yellowhead Area Transmission System Development
Outage Planning Subcommittee Mark Wilson. Outage Planning Subcommittee Created to address Market Participant concerns with existing rules and procedures.
Distributed Generation Registration June 30, 2008.
The EU’s Third Energy Package European Code Development UNC Transmission W/S - 4 th December 2008.
An Overview of: Generation Connections: Transmission Connection Cost Responsibility Review July
North America Energy Standards Board Craig L. Williams, Specialist Ld.Sr. ISAS Meeting January 13, 2016 Phoenix, AZ W ESTERN E LECTRICITY C OORDINATING.
Transition Plan Network Operations Model Change Requests 5/26/2010.
Current Nodal OS Design 1.The NMMS database will have an OWNER and an OPERATOR designation for each piece of equipment in the model. The OWNER and OPERATOR.
Kansas City Power & Light and KCP&L Greater Missouri Operations – Suggestions for Chapter 22 Revisions Missouri Public Service Commission Meeting Aug 31,
DRAFT – FOR DISCUSSION PURPOSES ONLY © 2013 New York Independent System Operator, Inc. All Rights Reserved. EIPC Roll-Up Powerflow Model Zach Smith Director,
UTC STUDY OF DISTRIBUTED GENERATION AND RECOMMENDATIONS Presentation for the Washington Future Energy Conference October 19, 2011.
Open Access Transmission Tariff Amendment No. 9 Greg Broeking, Chief Financial Officer March 7, 2012.
Direct Participation Enrollment Process for 2017 DRAM
GMD Data Request NERC Rules of Procedure Section 1600
Workshop Session 1: Overview
The Electric Reliability Organization: Getting from here to there.
Workshop Session 1: Overview
Solar Energy Commercialization Utility Scale Business:
North America Energy Standards Board
OUTLINE Legislative context, NERSA vision and NERSA mission
Energy Storage Roadmap & Flexibility Roadmap Information Session
Presentation transcript:

Discussion of Market Participant Choice for Transmission Connections Stakeholder Session October 14, 2011

2 Agenda Purpose Overview - what and why? Background AESO Connection Process Eligibility Own model TFO requirements and obligations Legislative framework Next steps

3 Purpose AESO issued a discussion paper September 29, 2011 –Sets out concepts for discussion on market participant choice Purpose of today’s session –Present the concepts –Provide additional clarification –Identify next steps –Facilitate discussion –Respond to questions

4 Overview What? –The possibility of enabling a market participant who requests system access service to design, build, own and operate the transmission facilities dedicated to connecting its facilities to the AIES –Market participant would become a transmission facility owner (TFO) in addition to taking system access service Why? –Some market participant concerns with cost & schedule for connections –AESO supports practices that foster efficiencies and are in the public interest Next Steps –Requesting open discussion and written comments by October 31

Current Connection Example Incumbent TFO assigned the transmission line connection 5

Proposed Connection Example Participant owns transmission connection to the grid TFO facilities connection 6

7 Background Investigation –Obtained input from functional areas within the AESO: project managers, planning, operations, standards, legal, etc. –Sought input from market participants - TFOs, AUC, DOE & customer associations –Legal review Considered several options –Design, build, own and / or operate Initial determination –“Own” model –Transfer is an option between TFOs (AUC approval required) –ISO Rule 9.1 may need to be revised (AUC approval required)

8 Current Process Participant files application for service (Stage 0) Incumbent TFO part of process, e.g. PPS (Stage 1 & 2) Project assigned to incumbent TFO (Stage 3)

9 Current Process - Authority Section 35(1)(a) of the EUA: 35(1) On receipt of Board approval of a needs identification document the Independent System Operator, in accordance with that approval, may (a) direct the owner of a transmission facility to submit, for Board approval under the Hydro and Electric Energy Act, a transmission facility proposal to meet the need identified AESO assigns all participant connections to the incumbent TFO during Stage 3 of the Connection Process Incumbent TFO prepares and files facility application Joint NID and Facility applications filed for some projects

10 Proposed Process Participant files application for service (Stage 0) and declares intention to be a TFO (accepts obligations & responsibilities) Incumbent TFO assists with connection (Stages 1 & 2) AESO requests “proposal” from participant (Stage 3)

11 Proposed Process - Authority Section 35(1)(b) of the EUA: 35(1) On receipt of Board approval of a needs identification document the Independent System Operator, in accordance with that approval, may (b) request market participants to submit, for approval by the Independent System Operator, a proposal to meet the need identified AESO asks participant for proposal If proposal is accepted by the AESO, participant files facility application Commission still approves NID and facility applications

Connection queue administration Market participant may changes its election part way after Stage 0 Connection project is cancelled and queue position revoked Market participant must submit a new system access service request and receive a new queue position

13 Eligibility - Participants The following are categories of Market Participants that connect directly to the AIES: –Generators –Loads –Dual use –Industrial system designations (ISD) –Distribution facility owners (DFO) Which of these should be eligible to provide their own connections, and why or why not?

14 Eligibility – Connections The following are connection types that may be eligible: –T-taps –Switching stations –In / Out arrangements –Others? The following are connection types that are non-eligible: –System lines –System upgrades –Connections serving multiple customers

15 Own Model Market Participant would assume responsibility for entire transmission asset life cycle –Legal ownership of transmission facilities –Design, construct, maintain, replace, upgrade, retire asset –File a tariff –Operate asset –May be required to upgrade to allow other participants to use the asset –Transfer of transmission facilities to another party after energization can occur provided all legal, legislative and regulatory requirements are met AESO can not initiate transfer of assets

16 TFO Requirements and Obligations TFOs (new and incumbent) are responsible to comply with requirements and obligations including: –Electric Utilities Act (e.g. provide access) –Hydro Electric and Energy Act (e.g. permit and license) –Public Utilities Act –Surface Rights Act (e.g. rights of way) –Transmission Regulation –Alberta Utilities Commission rules –ISO Rules –ISO Tariff –Alberta Reliability Standards (e.g. all TFO related standards) –Transmission TFO Terms and Conditions (e.g. agreements) –TFO capital and operating cost recovery through Transmission Tariff applications to the AUC, as applicable TFOs (new and incumbent) are treated the same AESO may direct TFOs to undertake certain activities

17 Legislative Framework Market Participant Choice is supported by legislation: –Electric Utilities Act, s. 35(1)(b) the AESO may “request market participant(s) to submit, for approval by the Independent System Operator, a proposal to meet the need identified” –Hydro and Electric Energy Act references not limited to TFOs but to “persons’’ in respect of transmission facilities Legislated obligations to make transmission facilities available include: –Electric Utilities Act, s. 39(3)(e): each owner of a transmission facility must provide the AESO the use of such facilities –Transmission Regulation, s. 28(3):generators may not prohibit access to the transmission interconnection facilities

18 AESO Rules Section 24(1) of the Transmission Regulation sets out assignment to incumbent TFOs based on service areas –AESO Rule 9.1 codifies the T-Reg s. 24(1) assignments Section 24(2) of the Transmission Regulation allows for alternate arrangements –Market Participant Choice could be an alternate arrangement –AESO Rule 9.1 may need to be revised to allow for s. 24(2) arrangements Facility and NID applications could allow for compliance with section 24 of the Transmission Regulation

19 Next Steps Stakeholders provide written comments on the Discussion Paper –Comments due October 28, 2011 AESO posts stakeholder comments received –November / December 2011 AESO replies to stakeholder comments received Stakeholder information session held (if required) AESO prepares and posts a Recommendation Paper Stakeholder information session held (if required) Stakeholders provide written comments on the Recommendation Paper Implementation –May include items such as: ISO rules changes, as required Connection process changes, as required

Thank you