Viaduc de Millau. Project timeline 28 June28 June 1989: governmental approval of the middle route1989 19 October19 October 1991: selection of the.

Slides:



Advertisements
Similar presentations
The Millau Viaduct Paris - Barcelona.
Advertisements

MILLAU (France) The highest bridge in the world. Click to advance slides.
Mid-Bay Bridge Connector Phase II and III December 2011 Project Update.
Route 50 Widening Design/Build Project. 2  Virginia Department of Transportation  Shirley Contracting Company  Dewberry  Fairfax and Loudoun Counties.
ENG-1010 Lecture 16 Bridge Design.
County of Fairfax, Virginia Sully District Council Meeting November 19, 2014.
DOT 1 January , 1990 DOT 2 July 23 - August 3, 1990.
The Millau Viaduct Paris - Barcelona The joining up had to be done on a no wind day due to excessive swaying – scary!
South Side Red River Bridge Corridor Study Phase III Preliminary Geotechnical Study Phase IV New Alignment Alternatives Evaluation.
US Highway 17 (Center Street) Sidewalk Feasibility Study Town of Pierson, Florida.
Chubaka Producciones Presenta :.
2012 JANUARY Sun Mon Tue Wed Thu Fri Sat
January 2012 Monday Tuesday Wednesday Thursday Friday Sat/ Sun / /8 14/15 21/22 28/
P Pathophysiology Calendar. SundayMondayTuesdayWednesdayThursdayFridaySaturday January 2012.
Chicas, este calendario si es pa' nosotras !!!!!.
The Algebra of Construction
Whole School Attendance Whole School Attendance 94.64% Overall School Absence 5.36%
Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler.
The Millau viaduct is part of the new E11 expressway connecting Paris and Barcelona and features the highest bridge piers ever constructed. The tallest.
6/23/11 FAIS,LLC Five Apple/Inpatient Specialist Case Study Patient Volume/LOS/ Payor Source Data.
Broadway Street Viaduct Improvement, Pre-Load Testing and Geotech Report Workshop Consultant Presentation Iowa DOT 2 nd April 2007.
Mathematical Modeling Dr. Gerda de Vries University of Alberta.
6/23/11 FAIS, Ind PC Five Apple/Inpatient Specialist Case Study Patient Volume/LOS/ Payor Source Data.
WORD JUMBLE. Months of the year Word in jumbled form e r r f b u y a Word in jumbled form e r r f b u y a february Click for the answer Next Question.
BANDRA-WORLI SEA LINK BY : PRAJAPATI NIHAR V..
Le Midi By Reyes Flores.
DATE POWER 2 INCOME JANUARY 100member X 25.00P2, FEBRUARY 200member X 25.00P5, MARCH 400member X 25.00P10, APRIL 800member.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
VT 100 over the Mad River Bridge Replacement July 13, 2015.
DIFFERENT TYPE OF BRIDGES
There are basically 4 different types of bridges: Arch bridge Suspension bridge Beam bridge Cable-stayed bridge An engineer would choose the correct bridge.
Real Options: The Via Dutra Case Luiz Brandao Via Dutra Case.
TEMPORAL VISUALIZATION OF DATA FROM THE FRENCH SENTINEL NETWORK.
Structures What things do I need to find out in order to predict if what I design will stand up to the use I intend to put it through?
July 2007 SundayMondayTuesdayWednesdayThursdayFridaySaturday
+ Structural engineering and How to reinforce the design of a structure to hold more weight Spring Technical English Program Санкт-Петербург, Рассия.
December 17,  MnDOT signed a highway easment in 1960 with US Steel  The TH 53 is over a ore deposit with shallow strippings, high iron and low.
Bridges and Loads Modified by Matthew Silbernagel.
Public Information Meeting St. George Road - Oak Hill Road Intersection Reconstruction Project.
The highest bridge in the world.
The highest bridge in the world.
Dictation practice 2nd Form Ms. Micaela-Ms. Verónica.
Pine cove pit time lapse drone photos
TIMELINES PHOTOS This is an example text
TIMELINES PHOTOS This is an example text
Process, timeline and overview
McDonald’s Kalender 2009.
McDonald’s Kalender 2009.
13-block rotation schedule
The highest bridge in the world.
McDonald’s Kalender 2009.
Construction Engineering and Management National Central University
Problem Gambling Clicks to Opgr.org
2300 (11PM) September 21 Blue line is meridian..
McDonald’s calendar 2007.
Teacher name August phone: Enter text here.
Circle Chart Template Process Name.
February 2007 Note: Source:.
The highest bridge in the world.
The Millau Viaduct Paris - Barcelona.
The highest bridge in the world.
MONTHS OF THE YEAR January February April March June May July August
McDonald’s calendar 2007.
Ward Park Restroom Timeline
The Millau Viaduct Paris - Barcelona.
Habitat Changes and Fish Migration
The highest bridge in the world.
2015 January February March April May June July August September
Habitat Changes and Fish Migration
Presentation transcript:

Viaduc de Millau

Project timeline 28 June28 June 1989: governmental approval of the middle route October19 October 1991: selection of the high solution, with the viaduct at 2500 m January10 January 1995: declaration of utilité publique (public usefulness), as needed to apply eminent domain or compulsory purchase.1995eminent domain 9 July9 July 1996: choice of the cable-stayed bridge type : decision to contract out both construction costs and future tolls to a private enterprise 16 October16 October 2001: work begins December14 December 2001: laying of the first stone2001 January 2002: laying pier foundations2002 March 2002: start of work on the pier support C8 June 2002: support C8 completed, start of work on piers July 2002: start of work on the foundations of temporary, height adjustable roadway supports August 2002: start of work on pier support C0 September 2002: assembly of roadway begins November 2002: first piers complete 25 February25 February–26 February 2003: laying of first pieces of roadway26 February2003 November 2003: completion of the last piers (Piers P2 at 221 m and P3 at 245 m are the highest piers in the world.) 28 May28 May 2004: the pieces of roadway are several centimetres apart, their juncture to be accomplished within two weeks2004 2nd half of 2004: installation of the pylons and shrouds, removal of the temporary roadway supports 14 December14 December 2004: official inauguration December16 December 2004: opening of the viaduct, ahead of schedule January10 January 2005: initial planned opening date2005

Preliminary studies In initial studies, four options were examined: bypass Millau to the east, requiring two large bridges over the Tarn and the Dourbie; bypass Millau to the west (12 km longer), requiring four bridges; follow the path of Route Nationale 9, providing good access to Millau but at the cost of technical difficulties and intrusion on the town; and traverse the middle of the valley. The fourth option was selected by the government on 28 June It consisted of two possibilities: the high solution, and the low solution, requiring the construction of a 200 m bridge to cross the Tarn, then a viaduct of 2300 m extended by a tunnel on the Larzac side. After long construction studies, the low solution was abandoned because it would have intersected the water table, had negative effects on the town, cost more, and the driving distance would have been longer.28 June1989Larzac After the choice of the high viaduct's path, five teams of architects and researchers simultaneously worked on a technical solution. The original concept for the bridge was devised by French designer Michel Virlogeux. The architects of the bridge are the British firm Foster and Partners. They worked together with the Dutch engineering firm ARCADIS, responsible for the technical design of the bridge.designerMichel VirlogeuxFoster and PartnersDutchARCADIS

Costs and resources The bridge's construction costs amount to €394 million, with a toll plaza 6 km north of the viaduct costing an additional €20 million. The builders, Eiffage, financed the construction in return for a concession to collect the tolls for 75 years, until However, if the concession is very profitable, the French government can assume control of the bridge in The project required about 127,000 m³ of concrete, 19,000 metric tons of steel for the reinforced concrete, and 5,000 metric tons of pre-stressed concrete for the cables and shrouds. The builder claims that the bridge's lifetime will be at least 120 years.m³

Statistics 2,460 metre: total length of the roadwaylength 7: number of piers 77 m: height of Pier 7, the shortestheight 343 m: height of Pier 2, the tallest (245 m at the roadway's level) 87 m: height of a pylonpylon 154: number of shrouds 270 m: average height of the roadway 4.20 m: thickness of the roadway m: width of the roadway 85,000 m³: total volume of concrete usedm³volume 290,000 metric tons: total weight of the bridgemetric tons 10,000–25,000 vehicles: estimated daily traffic €4.90–6.50: typical automobile toll, as of 2005€as of km: horizontal radius of curvature of the road deck