PIP Update 3 September 26 th, 2012. L1 Future Plans  Installation is halted until further notice (plan for 2014 shutdown or when needed)  Substation.

Slides:



Advertisements
Similar presentations
Seminar on Circuit Breaker
Advertisements

Medium-Voltage Switchgear - Then and Now -
Substation L1/ MCC L1 Update March 21 st, Current Location.
LCW Upgrades - Final Booster RF Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions.
1 Water and Wastewater System Information. 2 PWCSA Water Purchase Key Points From April 21, 2008 Meeting With PWCSA PWCSA is willing to re-open discussions.
Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys.
State of Wyoming Capitol Upgrades and Renovation projects Photos of the skylight and lighting project will be shown in chronological order, followed by.
1 BROOKHAVEN SCIENCE ASSOCIATES Electrical Power Status Thomas Nehring Conventional Facilities Advisory Committee Review October 5-6, 2010.
Transmission Bridges All calls through an exchange require the use of a transmission bridge. The main requirements of a transmission bridge are : 1) The.
Proton Source Task Shutdown 2014 RFQ Injection Linac Tank 1 to 2 emmittance probe and Collimator NTF Beam Line Repair 400 MeV Turbo Station Replacement.
CBC AUTOJH SYSTEM CONTROLS CHAPTER 10. CBC AUTOJH OBJECTIVES Discuss Operation and Function of controls for Manual and Automatic Climate Control System.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
PIP Update June 25 th Agenda Summary Update – Current Activities/Updates – Ryan Crawford: Anode Supply Update – Peter Prieto: BPM Update – CY Tan:
PIP Update Linac Utilities for 2014 shutdown Matthew Gardner, 4/23/14.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
PIP Update April 30 th Agenda Summary Update – Current Activities/Updates – Nathan Eddy – Booster Longitudinal Damper.
Texasheart.org Main Substation (MSS1) 13,800 volts Analogies: Chest Pain = Corona Minor Stroke = Tracking Cardiac Arrest = Arcing (may not be able to resuscitate.
All Experimenters Meeting PIP Report William Pellico on behalf of PIP team 4/7/2013.
PIP Update Jan Agenda Summary Update – Current Activities – Updates (Ken, Pat and John) – Additional Meetings/Notes.
PIP Update June 3 rd Agenda Summary Update – Current Activities – Updates Ken Domann – Budget & Schedule Ryan Crawford – Anode Supply Update – Additional.
2015 Shutdown Joe Compton 3/11/2015. RIL PIP Work  Install operational laser notcher  5 days  Dave Johnson & Todd Johnson.
Frankfurt (Germany), 6-9 June 2011 Louise Jakobsen, Danish Energy Association – Denmark – Session 3 – Paper 0811 Louise Jakobsen, Danish Energy Association.
G1 to G1b LOW VOLTAGE Schematic to Pictorial. You will now draw the Pictorial by following the Schematic.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
PIP Update July 30 th Agenda Summary Update – Current Activities/Updates – Project Controls Update: K. Domann – Linac Lattice – Valeriy Kapin.
Utility Engineers, PC.  Generation  Transmission  Distribution.
Matthew Gardner, 8/20/14.  Replace old water based AC system with conventional rooftop AC system. Drain and abandon old water lines.  Remove old air.
Substation L1/ Booster Substation Y-BE2 Update #3 August 15,2012.
Update on X Band Klystron Modulator Installation.
SERVICE ENTRANCE EQUIPMENT
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Electric Energy Notes.
PIP Update Aug. 21 st Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
Substation L1/ MCC L1 Update #2 July 27,2012. Status of Procurement  Substation  All approval drawings submitted  Testing is expected to take place.
Consolidation needs for the Electrical Distribution, Control Cables and Optical Fibres Equipment F. Duval.
PIP Update Dec 17 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
July 15, 2013 Photo by Greg Vogel. Shutdown Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster.
PIP Update Jan. 16 th Agenda Summary Update – Current Activities/Updates – Shutdown ScheduleHighlights – Upcoming Talks, Reports, Meetings Updates/Talks:
PIP Update Oct 29 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
PIP Update July 29 th Agenda Summary Update – Current Activities – Updates Tom Kubicki (Station 20,21,22 – Gallery and Equipment Work) – Additional.
July 29, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Trying to.
WELCOME!. Who is T&T Power Group? WELCOME! Who is T&T Power Group? What can we do for you?
Presentation Topic: Circuit Breakers Represented to: Dr. M. Riaz Khan Represented by: M. Mujahid.
Energy Coal, HSEC, September 2009 ICAM : Oil Circuit Breaker Explosion Incident date: Saturday 5 th September, 2009 Before After.
Science A Physics – P1 Science A Physics – P1 Topic 2b : Transmission of Electricity Topic 2b : Transmission of Electricity.
FESS/Ops Shutdown Summary Nov 9 th, CUB Status – Boiler #1 ON Primary Recirculating Pump repaired Second Belly Pump to be Wired – Boiler #2 OFF.
PIP Update Sept Agenda Summary Update – Current Activities Updates/Talks: Ken Domann - Schedule Update and Statusing Ryan Crawford - Linac MCC/Transformer,
FESS/Ops Shutdown Summary Week Ending 3Aug12. CUB Shut-Down Activities Shut Down Plant on July 21 hrs. Electrical – High Voltage Air Switch/Fuse.
PRELIMINARY VERSION Mechanical integration in the ESS Accelerator tunnel HENRY PRZYBILSKI.
PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
PIP Update May Agenda Summary Update – Activities – Budget – Plans Update Slides – Solid StateTom – ModulatorsRene – High Power Ferrite Testing.
AUTOMATIC CIRCUIT RECLOSER
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
S A Griffiths CM42 June 2015 Electrical & Control.
It’s…….
SUB-STATIONS.
YETS & LS2 Works EN-El on LHC / Power distribution
CUB Outage Schedule April 21, 2006.
Role of Fuel Pump Relay (FPR) in Fuel Delivery System in an Automobile
HV Battery Assembly.
the CERN Electrical network protection system
The Safe Use of Electricity
Schematic to Pictorial
Schematic to Pictorial
HEES Wales Update 17th March 06.
Presentation transcript:

PIP Update 3 September 26 th, 2012

L1 Future Plans  Installation is halted until further notice (plan for 2014 shutdown or when needed)  Substation moved to ME-7  Will be completely assembled and tested  Program breakers  Start SCADA programming  Moving forward with hatch installation  Should have quotes shortly  Paint tested positive for lead, will need to be dealt with at install  Rewriting specification for transformer to allow for three separate cores  Design review will be held sometime in the future  Temporary wiring is nearly finished and will remain in place

MCC-L1-1 Install  Installation will take place shortly  MCC will be moved downstairs sometime in October  Power will be shut off by the end of the week  DHP-L2-2 will be taken down  MCC  No air conditioning  Temporary sump pump  Overhead Crane  Hydraulic lift  Internal control wiring  Completed in advance  Electricians only need to connect 480V and some 120V circuits  Should be a 1 day install

Booster MCC  Universal Specification written  Can be used in West or East side  Will not be a SmartStart (LINAC MCC)  PLC and HMI will be purchased later  Programmed in house  Will not be purchased this year

Booster Substation  Contract awarded to Federal Pacific  9/13/12  $152,370  Extra transformer ordered  9/25/12  $55,254  When Booster substation replaced all oil filled transformers for Booster will be replaced with dry-type  Expect substation and transformer around Jan. or Feb.  Federal is going to try and get them to us by the end of the year  Siemens switchgear will likely make this impossible

Booster Anode Supply  Awaiting performance requirements  Design will begin in October  Install will occur 2014 fiscal year  Steve Hays and I will be visiting a pump house manufacturer in the near future to assess their capability of producing the anode supply