February 26, 2013 Board of Directors Meeting 2012 ERCOT Region Reliability Update.

Slides:



Advertisements
Similar presentations
WECC Board of Directors April 21-23, 2004 Seattle, Washington WECC Procedure for Reporting of System Events Disturbance Reports Rod Maslowski OC Vice Chairperson.
Advertisements

NERC PC Issues Update WECC PCC Meeting John Simpson, RRI Energy Planning Coordination Committee Seattle, WA June , 2010.
Transmission Operator Protection System Misoperations 2014 ERCOT Transmission Protections System Misoperations Data – 138kV and 345kV Combined (Not including.
January 9, 2013 BAL-001-TRE-1 Primary Frequency Response Update for Texas RE RSC.
Rate Plan. Value Story When asked, our customers identify the following topics as ways MidAmerican Energy provides value – Emergency Response.
Why TADS Is Needed No systematic transmission outage data collection effort exists for all of North America Energy Information Administration data (Schedule.
RPEWG Report Milorad Papic (RPEWG Chair) Salt Lake City, February 5, 2014 RS Meeting 1.
Recent ERCOT Events Lessons Learned
ERCOT’S COMPLIANCE ASSESSMENT PROGRAM Mark Henry Compliance Manager March 23, 2005.
ERCOT Compliance Audits Robert Potts Sr. Reliability Analyst March 23, 2005.
Joel Koepke, P.E. ERCOT Operations Support Engineer ERCOT Experiences During Summer 2011.
1 Texas Regional Entity Report December Performance Highlights ERCOT’s Control Performance Standard (NERC CPS1) score for October – Initial.
Texas Regional Entity Compliance Report TAC July 9, 2009.
PDCWG Report to ROS August 12, 2010 Sydney Niemeyer.
U.S. Energy Information Administration Independent Statistics & Analysis ERUS 2014 Bulk Power and Reliability Proposed Changes to Form EIA-411.
January 2008 Texas Regional Entity Report. 2 Performance Highlights ●ERCOT’s Control Performance Standard (NERC CPS1) score for November – ●Scores.
Reliable Power Reliable Markets Reliable People Performance Targets for the Customer Interconnection Process January, 2008.
RTWG Report to TAC August 5, 2010 Howard Daniels.
NERC Event Analysis Update Member Representatives Committee Meeting October 28, 2008 Robert W. Cummings NERC Director of Event Analysis & Information Exchange.
1 TRANSMISSION SYSTEM OVERVIEW NETWORK OPERATING COMMITTEE April 17, 2007 New Mexico Transmission System Overview.
Status Report for Critical Infrastructure Protection Advisory Group
1 Texas Regional Entity Compliance Update July 2007.
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
1 Compliance Update May Control Performance Highlights  NERC CPS1 Performance Performance further declined in March  March performance comparison.
ERCOT Planning WMS 10/20/2010 Target Reserve Margin and Effective Load Carrying Capability of Installed Wind Capacity for the ERCOT System – Methodology.
Curtis Crews, Reliability Services Texas Reliability Entity, Inc. Changes in Relay Misoperations Reporting.
Transmission Outage Process April Purpose In compliance with the Protocols and the Electric Reliability Council of Texas (ERCOT) Operating Guides,
TOP and BA Responsibilities SPP Wind Workshop May 30, 2013.
1 PDCWG Report to ROS October 13, 2011 Sydney Niemeyer.
Electric Reliability Council of Texas (ERCOT) A Success Story… In Progress Ingmar Sterzing United States Association of Energy Economics (USAEE) Pittsburgh.
Page 1 of 13 Texas Regional Entity ROS Presentation April 16, 2009 T EXAS RE ROS P RESENTATION A PRIL 2009.
Review of TADS Data for 2012 Voltage Class Name Metric AC Transmission Outages - Failed Protection System Equipment AC Transmission Outages - Human Error.
Texas Regional Entity Report Mark Henry June 6, 2008.
Compliance Update September Control Performance Highlights  NERC CPS1 Performance ERCOT’s August score was ERCOT’s CPS1 scores show significant.
Target Reserve Margin (TRM) and Effective Load Carrying Capability (ELCC) of Wind Plants Evaluation - Input and Methodology ERCOT Planning 03/25/2010.
NERC Event Analysis Overview ERCOT ROS Meeting Austin, Texas May 15, 2006.
Grid Reliability Metrics by Jim Dyer Electric Power Group, LLC January 29, 2004 Washington, DC Transmission Reliability Research Review.
PDCWG Report to ROS Sydney Niemeyer Chair NRG Energy Don Blackburn Vice Chair Luminant Energy.
1 Texas Regional Entity Report November Performance Highlights  ERCOT’s Control Performance Standard (NERC CPS1) score for September –
Grid Operations Report To ERCOT Board Of Directors December 16, 2003 Sam Jones, COO.
Severe Winter Weather Resource Outage Analysis Chad Thompson Operations Working Group September
PDCWG Report to ROS March 11, 2010 Sydney Niemeyer.
Impacts and Actions Resulting from the August 14, 2003 Blackout Minnesota Power Systems Conference November 2, 2003.
Role of Account Management at ERCOT 2006 TAC Subcommittee Review ERCOT Board February 21, 2006.
Operations Update ERCOT Board Meeting March 18, 2003.
PDCWG Report to ROS January 13, 2011 Sydney Niemeyer.
ERCOT DYNAMICS WORKING GROUP Report to ROS August 16, 2007 Vance Beauregard, American Electric Power.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Operations Update Kent Saathoff TAC Meeting March 6, 2003.
1 Compliance Update April Control Performance Highlights  NERC CPS1 Performance Performance further declined in March  March performance comparison.
Bywater Reliability Update Gary Huntley Entergy New Orleans, Inc. Regional Manager Entergy New Orleans, Inc. July 28, 2010.
Transition Plan Network Operations Model Change Requests 5/26/2010.
1 Compliance Update June Control Performance Highlights  NERC CPS1 Performance April Performance  April performance comparison April 2007:
Compliance Update July Control Performance Highlights  NERC CPS1 Performance ERCOT’s May score was 146.1; June’s score was May has typically.
Page 1 of 21 Texas Regional Entity ROS Presentation June 11, 2009 T EXAS RE ROS P RESENTATION J UNE 2009.
Integrated Reliability Measures Heide Caswell, Team Lead, Reliability Metrics Working Group (RMWG) Director of Network Performance, PacifiCorp Compliance.
1 Compliance Update May Control Performance Highlights  NERC CPS1 Performance April Performance  April performance comparison April 2007:
Target Reserve Margin (TRM) and Effective Load Carrying Capability (ELCC) of Wind Plants Evaluation - Input and Methodology ERCOT Planning 03/25/2010.
MOPC Meeting Oct , 2016 Little Rock, AR
Modeled Load Levels in the Valley
Compliance Report to ERCOT BOD December 2006
Phase Angle Limitations
David Kee Chair CPS Energy Sydney Niemeyer Vice Chair NRG Energy
WECC Regional Standards Update
Compliance Report to ERCOT TAC February 2007
Impacts and Actions Resulting from the August 14, 2003 Blackout
Workshop Session 1: Overview
WECC August 2017 Reliability Workshop James Merlo, PhD
Workshop Session 1: Overview
WECC August 2017 Reliability Workshop James Merlo, PhD
Presentation transcript:

February 26, 2013 Board of Directors Meeting 2012 ERCOT Region Reliability Update

2 NERC became aware of discrepancies between the design and actual field conditions of transmission facilities and issued a Level 2 Alert, the Recommendation to Industry Consideration of Actual Field Conditions in Determination of Facility Ratings, in Oct Periodic assessments began July 2011 with reports due every 6 months, with the final report due Jan NERC Alert includes a temporary amnesty for possible violations of FAC-009, as these types of discrepancies would normally result in violations. Priority# miles % Miles Assessed # of Circuits % Circuits with Discrepancies # of Discrepancies % Remediation Complete High671699%3518%14755% Medium %8277%11845% Low908413%7944%27935% ERCOT Region Data NERC Facility Ratings Alert

3 For the ERCOT Region: ●Most prominent discrepancy found is Clearance to Underbuild (~76% of total discrepancies), followed by Ground to Structure Clearance (~10% of total). ●A total of 544 discrepancies have been reported to date, or approximately 1 discrepancy every 31 miles of line inspected. ●Most entities have chosen to remediate the discrepancies as they are found or temporarily de-rate lines until the remediation is complete, rather than permanently de-rate the lines.

4 ERCOT Region Lessons Learned Received from entities (since start of EA process) 95 (70 from Feb 2011 Winter Event) Published on NERC web14 Submitted to EAS for approval5 Top 3 event causes continue to be Equipment Failure, Weather, and Relaying Issues. Generation trips >450 MW average 18 per quarter. Texas RE receives, prepares and shares lessons learned from events. Events

5 Frequency Control and Primary Frequency Response ●Frequency Control Performance continues to improve (managed by ERCOT Load Frequency Control). CPS1 scores have shown continuous improvement since start of Nodal market. ●Primary Frequency Response provided by generating units during loss of generation events is showing a gradual decline. ERCOT target is 420 MW per 0.1 Hz. NERC minimum is 286 MW per 0.1 Hz. Efforts are targeting improved governor response from all units, especially those providing Responsive Reserve Service (RRS).  Leader lines show min/max for the quarter  Boxes indicate 25%/75% quartiles  Red/black lines in each box show the average and median values for the quarter

6 Since start of Nodal market, the system frequency profile has seen a shift to the right to a band center of Hz. This is attributed to the impact of recurring Time Error corrections. The frequency profile is also showing a slightly narrower shape, in part due to the percentage of generation units that have reduced turbine governor deadband settings from Hz to Hz. ERCOT has averaged about 10 Time Error Corrections each month, always for slow Time Error. Time Error average is about second per day time accumulation. Frequency Control and Primary Frequency Response

7 Protection System Misoperations Data ●Texas RE’s analysis of misoperation data is shared with ERCOT System Protection Working Group (SPWG) each quarter. ●ERCOT region trends are similar to other regions based on NERC Protection System Misoperation Task Force information. ●Focus continues to be on working with entities to reduce misoperations due to human error (e.g. relay setting errors, wiring errors, etc.)

8 Protection System Misoperations Data ●>94% of total misoperations are dependability-based (vs. security-based). ●Incorrect settings, relay failures, and communication failures comprise 75% of the total misoperations. ●Misoperations from microprocessor-based relays continue to be the dominant type, in part due to the large installed base of microprocessor relays as well as the complexity in applying and setting these devices.

9 Protection System Misoperations Data ●Registered entities are taking an aggressive approach in addressing protection system misoperations when they occur. Average time to complete corrective actions is 36 days. ●This far exceeds the time frames proposed in the NERC PRC standard, which will allow 180 days for an entity to develop a corrective action plan.

10 Texas RE continues to monitor and track incidents of substation intrusion, copper theft, possible sabotage, and cyber threats Infrastructure Protection Reports

11 Generation Availability Data System (GADS) ●Mandatory GADS quarterly reporting began Jan 2012 for units >50 MW, not including wind. Reporting for units rated greater than 20 MW begins in 2013 (not including wind). ●A limited data set is available at this point, with only 12 months of unit- specific information available for approximately 360 ERCOT-region units. ●Texas RE’s analysis of GADS data is shared with the Performance Disturbance Compliance Working Group (PDCWG) each quarter. ●Analysis of GADS data will continue to evolve as the process matures. Ultimately, ERCOT-region GADS metric data may be used as input into the Long-Term Reliability Assessment (LTRA) process.

12 Most common immediate de-rate cause was due to low Btu coal (26% of total). Most common immediate forced outage causes were gas combustor issues, transmission problems, gas fuel issues, and waterwall issues Immed. De-Rates Immed. Forced Outages # of Events Total Duration hours hours Total Capacity MW Generation Availability Data System (GADS)

13 TADS reports are submitted annually by March 1 each year for circuits >200kV, for both automatic and non-automatic outages. Review and analysis of 2012 TADS will be completed by March 15. NERC Section 1600 data request changes are in process to include circuits between kV as well as change the reporting interval to quarterly. Texas RE’s analysis of TADS data is shared with the annually OWG. Similar to GADS, analysis of TADS data will continue to evolve as the process matures. Voltage Class Name Metric AC Circuit kV Outages per Circuit AC Circuit kV Outages per 100 miles per year Transmission Availability Data System (TADS)