Status Report of the PSB Half-Sector and Stripping Foil Test in L4T

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

Internal H0/H- dump Cesare Maglioni, Melanie Delonca Thanks to: R. Chamizo, R. Versaci, O. Aberle, J. Borburgh.
PSB extraction and transfer kickers 01/10/2014 LIU-PS ABT review1 L. Ducimetière, L. Sermeus.
MSI-V J. Borburgh, B. Balhan, E. Carlier, J.M. Cravero, B. Goddard, D. Nisbet, P. Van Trappen, F. Velotti.
BI SW for LINAC4 On behalf of BE/BI/SW BI software development process Specifications List of BI Systems – Not covered: PSB ring systems Conclusions Lars.
Linac 4 PSB BI LTB LT L4T m from PIMS to foil: m new line (to BHZ20) m present Linac2 line Active elements : 4+2bendings; quads,
Review on PSB 160 MeV H- Injection Nov 9-10, 2011 Closeout by P. Cruikshank, M. Giovannozzi, D. Johnson, B. Jones, B. Pine, M. Plum, D. Tommasini.
LINAC 4 Project L4T/L4Z Design Status J.Humbert / B.Riffaud on behalf of EN-MME design team 1 st September 2011 LINAC4 – BEAM COORDINATION COMMITTEE B.Riffaud.
Linac4 FBCT’s 18/ L4 BI BCT review Lars Søby On the behalf of: M. Andersen, D. Belohrad, L. Jensen, Franco Lenardon and J. C. Allica Santamaria.
Technology Department 1 Stripping Foil and instrumentation R. Noulibos - W. Weterings – Pieter Van Trappen Technical meeting 21-mai-2014 L4 – PSB - Injection.
Linac-4 current situation and outlook U. Raich, F. Roncarolo, F. Zocca.
ENEN H- INJECTION: STATUS ON MECHANICAL DESIGN - VACUUM SECTORIZATION - BHZ162 CHAMBER MODIFICATIONS - DUMP AREA - BHZ11 CHAMBER MODIFICATIONS.
Vacuum sectorisation H- Injection Some history Wim Weterings
New injection region 1L1 Engineering Change Request PSB-L-EC-0001 EDMS Wim Weterings PLI Meeting Wednesday 14 th January 2015.
Status of Radiation Protection studies in support of ELENA R. Froeschl and J. Vollaire DGS-RP-AS.
F. Regis, LINAC4 – LBS & LBE LINES DUMP DESIGN.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
Internal H0/H- dump M. Delonca, C. Maglioni On behalf of EN/STI Thanks to: A. Christov, S. Mathot, C. Pasquino, A. Patapenka.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
PSB dump replacement 17 th November 2011 LIU-PSB meeting Alba Sarrió.
Beam Instruments PSB + Transfer Lines B. Mikulec, J-F. Comblin.
Project X RD&D Plan Beam Transfer Line and Recycler Injection David Johnson AAC Meeting February 3, 2009.
LIU-PSB Configuration Management EDMS Documentation, Layout and ECRs Thomas Birtwistle EN-MEF-DC.
East Area BTV upgrade 2015_09_03 S.Burger BE-BI-PM V.Clerc EN-MEF-SI I.Francescut BE-BI-ML V.deJesus EN-MEF-SI M.Lazzaroni EN-MEF-EBE … F61 line.
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
LINAC4 and the Upgrade of the LHC Injector Complex R. Garoby 26 February, 2013.
PS/SPS Days Roberto Losito/Oliver Aberle 13th January 2004
Review on shorter PSB main bending magnets Injection layout with short magnets Advantages & Disadvantages Wim Weterings
PSB Injection Overview + Specification changes ABT LIU Project Review Wim Weterings.
Radiation Protection studies for the Linac4 / Linac2 interface Joachim Vollaire, DGS-RP 28/09/2015 Linac4 Coordination Meeting.
PSB H- injection concept J.Borburgh, C.Bracco, C.Carli, B.Goddard, M.Hourican, B.Mikulec, W.Weterings,
L4 BCC – 1 Sep 2011 F. Roncarolo, U. Raich L.Soby, J.Tan, C.Zamantzas, F. Lenardon, C.Vuitton, G-J.Focker.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
CERN Andrea Apollonio page 1 MACHINE PROTECTION CONSIDERATIONS FOR 50 MeV LINAC4 BIS COMMISSIONING A.Apollonio, B. Mikulec, C. Martin, B. Puccio, F. Roncarolo,
ECR - PSB: New KSW magnet in 16L1 Luis Feliciano, 4 th February.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
Linac4 status and long-term schedule M. Vretenar, Project Meeting  status  timeline  open issues  status  timeline  open issues.
Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,
Linac4 BCC 14/10/2010 Linac4 Measurement and Dump Lines BCC on the Linac4 Transfer Line Status.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
LIU Configuration Management EDMS Documentation, Layout and ECRs This presentation follows the LIU-PSB specific presentation done on 9 th October 2014.
PSB extraction and transfer kickers LIU TE-ABT review, 20 November L. Sermeus.
ESS Front End diagnostic
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
ELENA installation progress F. Butin / ELENA collaboration.
HiRadMat Summary of Phase-I and plans for Phase-II commissioning J. Blanco, N. Conan, V. Kain, K. Cornelis, B. Goddard, C. Hessler, M. Meddahi, C. Theis,
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
Wim Weterings Remy Noulibos
26/11/2015 LIU-PSB meeting, Status of BE and BT kickers and septa 2 Extraction and Recombination Septa and Kickers status Jan Borburgh, M. Atanasov, W.
Linac4-PSB 160 MeV connection readiness review
LINAC4 ADVISORY COMMITTEE
ELENA installation and commissioning status
Installation of an Instrument on a CERN machine
AD consolidation activities in LS2
EC Activities Status for the LIU
BE-BI Software for LINAC4
AWAKE proposals for BE/BI
F. Zocca, F. Roncarolo, B. Cheymol, A. Ravni,
Status of the BI Work Package in the LIU-PSB frame
HALF SECTOR TEST: a test for the future PSB injection
WPs concerned by L4 connection:
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Advanced Research Electron Accelerator Laboratory
(Beam) Commissioning Plan
ThomX – Commissioning Meeting – 25/01/2018
Status of the BI Work Package in the LIU-PSB frame
Presentation transcript:

Status Report of the PSB Half-Sector and Stripping Foil Test in L4T B. Mikulec for the HST project members LIU-PSB meeting 12/02/2015

History Complexity and related risk of the future PSB H- charge-exchange injection section (LIU-PSB project) has been exposed at several occasions First idea of a test installation of PSB injection equipment in Linac 4: P. Collier at the IEFC workshop March 2012. EDMS note 1224575 (June 2012) with the first concept Installation of a stripping foil unit and of half of the PSB H- injection section of one ring in L4T approved by Linac 4 BCC #43 (04/2013)https://indico.cern.ch/conferenceDisplay.py?confId=246360 and IEFC #97 ( 03/2014) https://indico.cern.ch/event/306665/ HST was integrated in LIU-PSB project (work unit #23) LIU-PSB Meeting 12/02/2015

Work Breakdown Structure LIU-PSB Meeting 12/02/2015

Future PSB H- Injection Section No experience at CERN with H- charge-exchange injection Extremely compact and complex section (4 rings and very limited space); combining equipment from TE/ABT, EN/STI, BE/BI, TE/EPC, TE/VSC, TE/MPE + services Long installation (~4 m) and commissioning (~1.5 m) times; critical for LS2 duration ~2.65 m 1.5 months of cool-down, 4 months of installation, 1 month HW commissioning, 2 weeks cold checkout Courtesy of L. Zuccalli, W. Weterings LIU-PSB Meeting 12/02/2015

Location of the HST Installations L4T: new Linac 4 to Linac 2 transfer line PSB half-sector test installation (temporary installation) H- stripping foil+BTV unit (permanent installation) LIU-PSB Meeting 12/02/2015

Top View of Future PSB Injection Section Stripping foil test - Phase 1 HST – Phase 2 Courtesy of L. Zuccalli, R. Noulibos, B. Riffaud, C. Baud, S. Burger and J. Borburgh LIU-PSB Meeting 12/02/2015

Scope of the Project – Phase 1 Phase 1: Permanent installation of one H- stripping foil+BTV unit 2012 L4T layout of section 1.1 Location for H- stripping foil unit Future location for BI laser stripping installation (not part of this project, but modifications to L4T have been included in stripping foil ECR EDMS 1376356) LIU-PSB Meeting 12/02/2015

Foil Handling Mechanism Radiation Hard Camera Mirrors and Optical Filters Stepping motor 1 mm thick Chromox (Al2O3 doped with CrO2) scintillating screen, engraved with calibration marks. The BTV has a position accuracy of ±0.2 mm and for a large range of beam intensities remotely controlled optical filters are included. Magnetic coupling Foil Changer Beam Observation System (BTV) with Screen in Beam Rear View Showing mirror Courtesy W. Weterings LIU-PSB Meeting 12/02/2015

Foil Handling Mechanism Radiation Hard Camera Mirrors and Optical Filters Stepping motor A stripping foil current measurement will be made by means of taking the electrical signal from the foil holder Beam Magnetic coupling Foil Changer Beam Observation System (BTV) with Screen Retracted Rear View Showing mirror Courtesy W. Weterings LIU-PSB Meeting 12/02/2015

Foil Handling Mechanism Radiation Hard Camera Mirrors and Optical Filters Stepping motor Magnetic coupling Foil Changer Beam Observation System (BTV) with Screen retracted Vacuum Chamber Courtesy W. Weterings LIU-PSB Meeting 12/02/2015

Foil Handling Mechanism Final configuration to be installed in Linac4 transfer line (L4T) sector 1.1 Courtesy W. Weterings LIU-PSB Meeting 12/02/2015

New Layout of L4T sector 1.1 Beam Current Transformer (BCT) PIMS Beam Vacuum Valve Vacuum Valve To optimise intervention time and avoid foil damage due to differential pressure, the system is installed in a dedicated vacuum sector. Stripping Foil Test Stand Courtesy W. Weterings LIU-PSB Meeting 12/02/2015

Test Program for Part 1 Lifetime of different foils and foil holders Controls of foil changer including interlock with screen insertion Commissioning and optimisation of the instrumentation at the stripping foil (screen + mirrors + camera, foil temperature and current measurement from foil holder) Rough estimate of stripping efficiency of different foil types and thicknesses Need 2 well cross-calibrated BCTs (L4T.BCT.0107 and L4Z.BCT.0273); H0 will not be detected and H- will cancel with p (but H- signal negligible), so expect transmission of ~98%! Detection of foil breakage (foil current) Hope to be able to obtain a rough estimate of emittance growth through the foil using the SEM grids in L4Z line Beam size on foil will be similar to situation at PSB injection Tests can be performed in parallel to Linac 4 beam tests (except for emittance measurements of H- beam at end of line) LIU-PSB Meeting 12/02/2015

Status of Phase 1 – Stripping Foil Test Stand ECR done and L4T layout of section 1.1 modified Holes drilled for new supports Rack platform in b.400 modified and permanent rack installed Cables being pulled (will be finished end March) Stripping foil unit: ~90% of components delivered, 2 vacuum tanks expected for end February; start assembling beginning of March BTV hardware available; being assembled System will first be tested in lab including interlocking with BTV screen movement Installation at latest this summer LIU-PSB Meeting 12/02/2015

HST – Phase 2 Phase 2: Temporary installation of half of the future PSB H- injection chicane + external dump Around location of debuncher (L4T sector 4.5) Install L4T only up to this point (plus line between 2 vertical bends) Positive ‘side effect’: Commission already L4T line until debuncher LIU-PSB Meeting 12/02/2015

HST Implementation LIU-PSB Meeting 12/02/2015

HST Implementation Courtesy B. Riffaud and J-P. Corso LIU-PSB Meeting 12/02/2015

Schematic Layout of HST SHIELDING Shielding: 0.8 m iron + 0.8 m concrete. Lateral shielding thickness: 20 cm. LIU-PSB Meeting 12/02/2015

Inventory of the Half Sector Test Install another stripping foil+BTV unit, half of the injection chicane (BSW3+BSW4) including the H0/H- dump and the H0/H- current monitor In addition: 1 standard + 1 diamond BLM, 2 BCTs (stripping efficiency cross-check), 1 BTV + external beam dump+shielding (including vacuum valve) 2 sector valves enclosing the installation, pumping groups Strategy: Use where possible prototypes, spares or not yet required Linac 4 equipment and cabling (e.g. standard BLM and BCTs) Requires ~1.3 m space (half-sector with stripping foil unit). L4-T-EP-0002 rev 1.0 LIU-PSB Meeting 12/02/2015

Courtesy B. Riffaud and J-P. Corso (2014 version) LIU-PSB Meeting 12/02/2015

Test Program for Part 2 Stripping foil BSW3+4 H0/H- dump Special BLM Drawing of H0/H- monitor provided by F. Zocca Stripping foil More precise stripping efficiency measurement of H0 and H- BSW3+4 Powering and control of half of the chicane magnets Refine chicane parameters Current stability, precision and interlocking H0/H- dump Aperture check Temperature cross-check with simulated values  refine cooling needs Interlocking (temperature and pressure drop – define operational thresholds) Special BLM Diamond BLM to measure secondaries close to H0/H- dump; evaluate operational conditions for foil degradation measurement and fast losses H0/H- current monitor: new development! Sensitivity check for H-; comparison to theory Influence on measurement if beam passes besides the monitor (use thicker foil; simulate circulating beam)? Interlocking – essential for dump protection Interlock system test for part of PSB injection (BIS + SIS) Prepare and test new applications + controls LIU-PSB Meeting 12/02/2015

Proposed Operation Plan to run only during daytime and week days Commissioning planning in work; manpower to operate the HST still to be sorted out Cannot run at higher intensity because of limitations due to prompt radiation Maybe single full-intensity shots with RP agreement towards end of operation Operating Scenario Phase 1 (2 months) Phase 2 (2 months) Max. pulse current 40 mA Max.+avg. pulse length 0.5-1 μs 10 μs Max. repetition rate 0.833 Hz Pulse period 1.2 s Max. number of particles/pulse 2.5E11 2.5E12 Particle energy [MeV] 160 MeV Particle energy [J] 2.563E-11 J Max. energy/pulse 6.4 J 64 J Mean power/pulse 5.33 W 53.3 W Beam designation Pencil beam Low-intensity beam 1σ beam size ~1.9 x 2.4 mm2 ~2.2 x 3.3 mm2 Change Phase 2 to 10 us max. and make it last for 2 months (no phase 3 due to prompt radiation). LIU-PSB Meeting 12/02/2015

Prompt Radiation and Activation Studies Temporary dump installation: use a spare 160 MeV dump core, reuse trolley from 100 MeV commissioning dump and modify shielding. Assumption in RP analysis : Beam power of 53 W (prompt dose rate) Up to 5% of H0/H- on the internal dump (“unshielded”) The rest into the “shielded” beam dump Detailed layout implemented in FLUKA I. Leitao EN/STI J. Blaha DGS/RP LIU-PSB Meeting 12/02/2015

Prompt Dose Rate Issue : Limit prompt radiation levels in the Linac 2 technical gallery (already classified by RP due to losses from Linac 2) Linac4 Linac2 LIU-PSB Meeting 12/02/2015

implemented during HST Prompt Radiation Shielding optimized with regard to the available space (streaming along the sides of shielding) to be confirmed with transport (meeting next week) Note still to be published by RP Prompt dose rate (Linac 4 level) Prompt dose rate (b.363 level) Courtesy of J. Blaha implemented during HST Exclusion area to be LIU-PSB Meeting 12/02/2015

RP Recommendations Exclusion area (new doors with crash bar) in compliance with egress requirements already implemented during this winter technical stop (only panels to be added during operation) Area only used as emergency corridor for Linac 2 (route: Linac 2 tunnel up to service gallery) Relocate PAXS22 to new door Dose rate objective: at new door radiation levels should not exceed 5-10 μSv Relocate PMI from end of L4T close to temporary dump for monitoring purposes and simulation cross-check Work and dose planning for HST removal still to be done LIU-PSB Meeting 12/02/2015

Linac4 Masterplan OLD (end 2014): Installation NEW (since last week): Commissioning 50 MeV 100 MeV 160 MeV Reliability Run Half Sector Test 5 months 4 weeks 5 weeks 3 months YETS Ready for 50 MeV protons OLD (end 2014): NEW (since last week): Add min. of 3 months delay due to PIMS brazing problems! This means HST installation shifting to ~April 2016 and beam tests from ~August 2016 mid-October until November 2014: H- stripping foil permanent test stand installation (replace stripping foil system with vacuum pipe) April – June 2015: HST services, cabling and what else can be installed (BCT + vacuum pumping module?) November 2015: install everything else – will this be feasible (dump shielding installation?) J. Coupard LIU-PSB Meeting 12/02/2015

Budget Requests (Baseline 4) Management, Planning and Operation 30 kCHF Design Office, Integration, Installation and Services 331 kCHF Radioprotection and Safety 50 kCHF Dumps 46 kCHF BSW Magnets, Stripping Foil and Controls 165 kCHF Power Converters and Transformers for BSW 120 kCHF Beam Instrumentation 106 kCHF Vacuum Systems 153 kCHF Total 1001 kCHF (Part 1: ~1/4th of cost) Shielding blocks could amount to max. 100 kCHF if to be ordered new… Part 1: design office, stripper foil system (mainly controls), vacuum equipment, cabling + rack, survey, transport Cost for the PERMANENT installation: ~233 kCHF HST cost: ~768 kCHF LIU-PSB Meeting 12/02/2015

EVM LIU-PSB Meeting 12/02/2015

Material from Linac 4, LIU-PSB or from other sources BSW magnets + electronic modules (LIU-PSB spares) BSW powering systems will be reusable after modifications H0/H- monitor + electronics and H0/H- dump (LIU-PSB spare) stripping foil + screen system (LIU-PSB spares) Dump chariot from Linac4 commissioning dump, some dump controls borrowed from LIU-PSB; use spare Linac 4 dump core Dump shielding blocks borrowed temporarily (tbc) BCTs from Linac 4 (incl. cabling + electronics), BLMs + electronics from Linac 4 (incl. cabling) or LIU-PSB, 1 screen from PS spares Recuperate big fraction of vacuum components (pumping groups + supports, gauges, valves) + controls and cabling for temporary installation from Linac 4 Displace one Linac 4 radiation monitor Adapt existing Linac 4 beam interlock hardware Installation beam + alignment jacks from Linac 4 commissioning LIU-PSB Meeting 12/02/2015

Status of Phase 2 – HST Layout drawings under approval (SPLLJLHS0001) HST Engineering Specifications (including a chapter on safety) will be written once the layout + drawings are approved Rack area in b.400 modified for temporary rack installation; cables already partly being pulled Equipment will be ready for installation Progress to be followed closely: procurement for BSW power converters, H0/H- current monitor electronics Detailed installation planning started with RP and J. Coupard Lateral shielding to be sorted out with transport Gathering information to elaborate commissioning planning LIU-PSB Meeting 12/02/2015

External Dump Shielding Lateral wall needs to be stabilised. Meeting between transport, RP and EN-STI next week. LIU-PSB Meeting 12/02/2015

Organisation Indico site available (under LIU-PSB) HST Twiki website: https://twiki.cern.ch/twiki/bin/view/PSBHalfSectorTest/WebHome Mailing lists: LIU-PSB-HALFSECTOR-TEST@cern.ch liu-psb-HST-WP-holders@cern.ch Installation planning integrated in Linac 4 installation coordination meetings (organised by J. Coupard) LIU-PSB Meeting 12/02/2015

Conclusions Stripping foil and PSB half-sector test will be beneficial To evaluate each sub-system before installation in the PSB Check if functionality conform to specifications Could correct design or operational issues before LS2  technical risk reduction To prepare the single parts, controls and applications in advance To reduce the commissioning time for the Linac 4-to-PSB connection and reduce the risk concerning the LS2 duration Installation slots: dependent on Linac 4 commissioning planning! Permanent installation (stripping foil test) currently ongoing and in time HST preparations well underway Beam tests in parallel with Linac 4 160 MeV commissioning and reliability run LIU-PSB Meeting 12/02/2015

to everybody contributing! A great thanks to everybody contributing! LIU-PSB Meeting 12/02/2015