17/09/2012LHC 8:30 meeting LHC Summary Week 37 Coordination: Jorg Wenninger & Jan Uythoven.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress week 19 Monday 11 th May 2015 Coordination: Jan Uythoven, Massimo Giavannozzi, Mike Lamont.
LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
:00 meetingEBH 1  8:40 – 9:30 access for MKB (dilution kicker) LBDS B2 – PLC exchange  Pre-cycle  11:17 – 12:50 RF problem with ion injection.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Pevatron status Sunday 29 th November 2015 Coordination: John Jowett, Mike Lamont, Jan Uythoven Access Loss maps Physics.
From yesterday LHC status Wednesday 26 th Welcome Verena back on shift 07:08 Access in PM85 for piquet EPC (O.Fournier).  Fuse on RD2.R8 circuit.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
:00 meetingEBH 11 Saturday :00 meetingEBH 2  7:58 Fill 2483 (264 bunches) dumped by reference orbit set to zero in.
– Machine closed. Ramp for powering tests & pre-cycle – Pilots through nominal cycle up to collisions. Measure chroma during squeeze. Check dump of pilots.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Production running 1 pb-1Lost to Mon h2062e32EOF studies Tue h17.152e32UFO Q8.L5 Tue h e32OP request Thu h e32OP.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
28/01/2013LHC 8:30 meeting Summary of Week 4 pPb physics Machine Coordination: Mike Lamont & Jan Uythoven Ion coordination: John Jowett.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Wednesday
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Friday 30th September 06:00 Operator dump fill #2171, int. lumi about 75 pb-1 Previous operator dump from physics was on 14 September ! 07:00 Start of.
Monday 21st January & night
Tuesday 11th September LHCb dipole presently fault off
Saturday 30th June - Sunday: Rocky !
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Tue :25 Beams dumped due to RF vacuum interlock
LHC Morning Meeting - G. Arduini
Tuesday 22nd January - morning
Summary of Week 11: 14 – 21 March
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Thursday 17th May 01:11 Fill #2633 dump in squeeze arc circulator load channel Ad1B 03:16 Fill #2644 Stable beams, lumi 5.2e33 cm-2s-1 04:38 Dumped by.
Thursday morning 09:30 Dump of pPb fill.
Lost at 12:05 to power converter (RTQX2.R1) problem
Mon 22/8 – Tue 23/8 00:07 stable beams #2040. Initial luminosities: 2.1x1033 cm-2s-1 18:00 Programmed dump. End of physics #2040. ~83 pb-1 in ~18 hours.
Mike Lamont, Jorg Wenninger
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Week 35 – Technical Stop and Restart
Friday morning 10:30 Optics measurements and corrections.
Wire almost entirely through beam before BLM triggers dump
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Saturday 7th May Sat – Sun night
Summary Thursday h21: Stable beams fill #1303.
Monday – Morning Fill 3265 stable beams since 1:31
Aims for the week Recover from technical stop and precycle at 10A/s
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Summary week 18 Intensity ramp up & production
Thursday 26th July 13:21 Fill 2880 beam dumped
Thursday – Morning Energy matching at injection with H CODs
Monday morning 09:40 Dump fill 2838, integrated ~130 pb-1.
Thursday 22 September 2011.
Friday 14th September 03:15 Beta* at 1 km. Optics measurements, see yesterday. 07:00 Dump. 08:00 Refill with 3 nominal bunches for high beta. 11:15 Beams.
Monday :15 fill 3523 dumped by BPMs IP6
Tuesday In the morning test cycle with probe for Q’ measurement.
Wednesday 23/2 Thanks CRYO!!!.
Thursday
Monday 26th September 7:30 Beam dump, QSP on RQX.R1, lost cryo in ITR1, 91 pb-1. Cryo recovery, needed about 1.5 h. Setting of TI2 collimators to 5 sigma.
Another Immortal Fill….
Tuesday
Presentation transcript:

17/09/2012LHC 8:30 meeting LHC Summary Week 37 Coordination: Jorg Wenninger & Jan Uythoven

Week 37 – what an (MD) week LHC 8:30 meeting 17/09/2012 2e14 6e33 pPb tests Vac wire scanner RF Klystron, I pPb physics 1000 m optics pPb MD – BPMS EDF Q20 LHCb polarity BP Physics

Physics (not the main occupation of the week) LHC 8:30 meeting 17/09/2012 FillLumipb -1 StableDump 3067 (Saturday) h40m Operator 3071 (Sunday) h54mOperator Total lumi of the week: 308 pb-1

Main problems of the week Vacuum leak on wire scanner Point 4 RF klystron beam 1 …..and many smaller ones LHC 8:30 meeting 17/09/2012

Vacuum leak on wire scanner the scanner is dismounted and a closing flange is mounted. the wire has been recuperated for analysis. the resistivity of all b1 scanners have been measured before and after the opening of the vacuum, integrity check. the broken scanner had scans. all scanners switched to the spare scanners on Wednesday. the scanner mechanics is in the radioactive equipment storage to be released by RP. LHC 8:30 meeting 17/09/2012 LHC.BWS.5L4.B2H1:NB_PTS_SCAN_IN LHC.BWS.5L4.B2H2:NB_PTS_SCAN_IN LHC.BWS.5L4.B2V1:NB_PTS_SCAN_IN LHC.BWS.5L4.B2V2:NB_PTS_SCAN_IN LHC.BWS.5R4.B1H1:NB_PTS_SCAN_IN LHC.BWS.5R4.B1H2:NB_PTS_SCAN_IN LHC.BWS.5R4.B1V1:NB_PTS_SCAN_IN LHC.BWS.5R4.B1V2:NB_PTS_SCAN_IN e-5 mbar

RF Klystron Problem – Line 2 Beam 1 Required (almost) a hand full of accesses distributed over the week.  During the MDs ran with 1 klystron less, but not possible for full intensity beam due to beam induced power in the cavities Checks (Olivier Brunner)  primary "low voltage" circuit checked  controls system and 230 V supply verified  replacement of the gradator and 230/115V transformer  replacement of one 100kV cable (in fact swap with another cable that does not need to carry any current)  careful check of all accessible connections (one found very slightly loose in the klystron gun tank)  replacement of the modulator (to eliminate a "suspicious" HV connection sitting in the oil tank) Fixed on Saturday morning (until TS)  Klystron line 2B1: modulator anode and filament cable swapped, which reduces the load on the suspected faulty HV cable from 25A to a few mA. LHC 8:30 meeting 17/09/2012

pPb test Phase 1 - Monday LHC 8:30 meeting 17/09/2012 Re-phasing and locking tests performed successfully with protons at 450 GeV. Quite some problems with injecting Pb due to issues with RF synchronization and SPS rephasing: 20:50 First Pb bunch injection - circulating at first attempt.  And ended up in the correct bucket ! Setting up of RF, ADT, Q, Q’ etc... 22:00 Vacuum problem WS B1. End of part 1.

pPb Phase 2 – Wednesday/Thursday LHC 8:30 meeting 17/09/2012 Struggling with RF klystron 18:00-19:30 Injection of 15 x 15, first ramp attempt.  Killed by TCT interlocks. TCT settings and position interlocks updated for 35sigma (nom = 26 sigma) on flat top, but update on energy interlocks on gaps was forgotten.  Decide to go back to standard TCT settings, as nominal settings are also OK (35 sigma was pushed by collimation, not MP).

pPb Phase 2 – Wednesday/Thursday LHC 8:30 meeting 17/09/ :30 Second ramp attempt. 4 TeV. 23:00 Re-phasing – found collisions. 00:50 Loss maps on 2 out of 15 bunches (ADT). 01:26 Stable beams, first time pPb.  Lumi’s approaching 10^26 cm-2s-1 Moved collision point +/- 50 cm

ALICE event LHC 8:30 meeting 17/09/2012 Hannes Wessels

High beta* MD and some data taking LHC 8:30 meeting 17/09/2012 Start Thursday around 15:00, optics checks with pilots First cycle: lost on collimator gap-energy interlock (again!) of TCTVs in de-squeeze to 90 m. Second cycle: at 90 m, hit a limit on the current of RTQX in IR1 an IR5  Limits were modified following a MP event with a trip of the triplet circuit. The limits were set based on currents used in OP (ECR) to A (need -300 A for 1 km).  The currents used for 500/1 km were overlooked in the analysis.  A change of limits requires PCs to be OFF… Third cycle: orbit FB becoming unstable in de-squeeze to 500 m. Managed to navigate through switching on/off.  Lost at 500 m after OFC crash during investigations and attempts to switch optics.

High beta* MD and data taking Fourth cycle: started with OFB checks at injection. No problems found.  Optics checks along the way. 03:30 – 6:30 beta beat / optics measurements at 1 km  After applying the corrections calculated from the data taken in June 2012 we performed the measurements. The beta-beat went down from ~30% to less then 10% after applying the corrections. LHC 8:30 meeting 17/09/2012

1000 m LHC 8:30 meeting 17/09/2012 Further optics Results  Off-momentum measurements were also done to check the dispersion. No big difference between the measurement and the model was found.  A k-modulation measurements was also performed to measure the beta* at IP1 and IP5. To be analyzed offline. Filled with 2 x 3 small indivs of about 3e10 p+ for collisions  TOTEM and ALFA collimator and pot set-up. Scraping and some retraction to take some data mmALFA touching the beam

pPb MD LHC 8:30 meeting 17/09/2012 Plan to inject 318 p+, max 2e10, against 4 Pb bunches Pb injection fine, problems with RF/bucket/super cycle seem to be fixed p+ injection difficult. Dumped by BPMS in IP6 Struggle throughout the night  Rhodri came in for BPMS. Reduce bunch intensity. BPMSA.A4L6.B1 vertical channel shows additional triggers even with one probe of 1e10. This channel more sensitive than others. 04:20 all p+ bunches injected. 04:35 Dumped on BPMS:  pPb did not make it, but important lesson learned: needs work from BI and see which additional BPMS attenuators will be needed for the proton – ion run. One BPMS channel seems to be worse than others.

Test ramp with 2 batches of 8 LHC 8:30 meeting 17/09/2012 Reversed LHCb polarity to negative Split beam process: going into collision first in point 1 and 5, then in 8 Quite some corrections for going into collisions in 1 and 5 Beam position at collimator Needs to be corrected – reason for tests

Saturday morning Q20 optics LHC 8:30 meeting 17/09/2012 Bad trajectory, source in the SPS. Seems the SPS orbit at 450 GeV has changed on Q20.  SPS extraction to be revisited…

First fill on Saturday evening LHC 8:30 meeting 17/09/2012 CMS and ATLAS a bit off… ALICE again limited to ~0.5E30 cm-2s-1. Initial ‘Luminosity’ signal in LHCb very low (good thing). Not possible to exceed 2E30 cm-2s-1. It seems that we were optimising on beam-gas? After ~1 hour of scanning overlap was found (off in both Xing & Sep).

Sunday 16 th September LHC 8:30 meeting 17/09/2012 Nice Fill, operator dump Losses Losses YEAH!

Fill #3068: vacuum point 4 11:36 Fill dumped at flat top due to BGI. Lifetime was good. Vacuum activity at BGI. No gas injection but HV was on. Switched off HV from BGI. LHC 8:30 meeting 17/09/2012 1e-6 mbar

Fill # :13 Lost when going into collision. Losses on TCP IP7 B1, running sum 8 (655 ms). BBQ does not show instability. LHCb lumi going up a bit before ATLAS and CMS LHC 8:30 meeting 17/09/2012

Dump when going into collision, no.1 LHC 8:30 meeting 17/09/2012 LHCb lumi ATLAS, CMS and TCP losses 1 Gy/s Dump threshold around 1.7 Gy/s

Comparison fill of Saturday evening: no dump LHC 8:30 meeting 17/09/2012 LHCb lumi (very small) TCP ATLAS lumi Almost no lumi LHCb, TCP down at moment ATLAS going into collision 1 Gy/s

Fill #1370 (no. 2) 17:01 Again lost when going into collision. LHCb lumi coming up too quickly LHC 8:30 meeting 17/09/2012 LHCb lumi TCP 1 Gy/s

Fill 3071: YEAH 20:08 Stable beams, initial lumi 6.5e33 cm-2s-1 Reverting to the settings of yesterday (thus delaying LHCb luminosity wrt to IP1/5) seems to work.  At the end of the collision beam process we had to trim IP8 Xing plane by -140um and the levelling by 200um before switching ON the levelling. LHC 8:30 meeting 17/09/2012 LHCb lumi TCP 1 Gy/s

A week in which we learned a lot! pPb  Found bug in RF synchronization and SPS rephasing  First pPb data taking with low intensity bunches  For 2e10 p+ intensity bunches we need to change the attenuators on the BPMS in IP m beta*  Optics is good  First tests of collimation and moving in Roman Pots Q20 optics  Needs more work to optimise extraction on the SPS side LHCb polarity swtiched Should not go into collision in LHCb before ATLAS and CMS  Split Beam Processes for going into collision will help  To be commissioned after the TS The RF klystron line 2B1 needs a new cable We started Technical Stop 3 – back on Friday evening LHC 8:30 meeting 17/09/2012