Earthquake Recovery Programme Pre-Synod Archdeaconry Meetings June – August 2015
Global Settlement Review Insurance Claims Process – 3 years of negotiations and building assessments during multiple earthquakes Global Settlement completed 22 Dec 2013 Funds received 31 March 2014
The Past Year CPT Recovery Team appointed by July 2014 Schedule of Works completed by Oct 2014 Adopted by the Church Property Trustees in Nov 2014 Communicated to Parishes in Dec 2014 –Jan 2015
Recovery Programme Progress 230 projects in Recovery Programme 108 projects completed to date: 29 Vicarages 1 New Build 53 Churches 25 Halls and other buildings 7 projects currently under construction 35 projects in the planning phase
Schedule Overview Pegasus 16% of projects are in Pegasus Archdeaconry 33% of projects have been completed 7 total loss (new build) projects 1 completed (St Saviour’s at Holy Trinity Church) Planning commences for balance over major works projects to be completed (over $200,000): 2 in planning phase 1 in construction phase Planning begins for remaining 3 projects in minor repair projects (under $50,000) 3 currently underway Balance to be completed by mid-2017
Schedule Overview Pegasus By Dec 2015, 50% of projects are scheduled to be completed All projects are scheduled to completed by Dec 2018