C. Haber 6-Mar-08 Integrated Stave Electrical/Mechanics/Cooling Update March 6, 2008.

Slides:



Advertisements
Similar presentations
10-Nov-2005US ATLAS Tracking Upgrade Santa Cruz 1.
Advertisements

Sci-Fi tracker for IT replacement 1 Lausanne 9. December 2010.
ATLAS SCT Endcap Detector Modules Lutz Feld University of Freiburg for the ATLAS SCT Collaboration Vertex m.
Layer 0 Grounding Requirement in terms of noise performance Grounding/Shielding studies with L0 prototype Summary Kazu Hanagaki / Fermilab.
The Origami Chip-on-Sensor Concept for Low-Mass Readout of Double-Sided Silicon Detectors M.Friedl, C.Irmler, M.Pernicka HEPHY Vienna.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
November Vertex 2002 Kazu Hanagaki1 Layer 0 in D0 Silicon Tracker for run2b Kazu Hanagaki / Fermilab for D0 run2b Silicon Tracker group Motivation.
LHCC referees meeting, 10 October 2005Børge Svane Nielsen, NBI1 Status of the FMD LHCC referees meeting, 10 October 2005 Børge Svane Nielsen Niels Bohr.
1 Module and stave interconnect Rev. sept. 29/08.
Module Production for The ATLAS Silicon Tracker (SCT) The SCT requirements: Hermetic lightweight tracker. 4 space-points detection up to pseudo rapidity.
Brenna Flaugher Oct. 31 th CDF Meeting1 RunIIb Silicon Project Successful Lehman Review Sept Workshop at LBL 10/23-10/25: Wednesday-Thursday  hybrids.
The LHCb Inner Tracker LHCb: is a single-arm forward spectrometer dedicated to B-physics acceptance: (250)mrad: The Outer Tracker: covers the large.
PXL Electronics Status update for HFT TC meeting on May 11, 2010 at LBNL 1HFT TC 05/11/ LG.
WP7&8 Progress Report ITS Plenary meeting, 23 April 2014 LG, PK, VM, JR Objectives 2014 and current status.
1 SBS Spectrometer / GEP5 Conf.. 2 Tracking Requirements Requirements Tracking Technology DriftMPGDSilicon High Rate: MHz/cm 2 (Front Tracker)
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
SVX4 chip 4 SVX4 chips hybrid 4 chips hybridSilicon sensors Front side Back side Hybrid data with calibration charge injection for some channels IEEE Nuclear.
U.S. ATLAS Executive Meeting Upgrade R&D August 3, 2005Toronto, Canada A. Seiden UC Santa Cruz.
13 Dec. 2007Switched Capacitor DCDC Update --- M. Garcia-Sciveres1 Pixel integrated stave concepts Valencia 2007 SLHC workshop.
17/06/2010UK Valencia RAL Petals and Staves Meeting 1 DC-DC for Stave Bus Tapes Roy Wastie Oxford University.
Leo Greiner IPHC testing Sensor and infrastructure testing at LBL. Capabilities and Plan.
Material calculation of petal core variants Sergio Díez Cornell with input from many people CERN AUW, 3 rd Nov 2014.
1 Module and stave interconnect Rev. sept. 29/08.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
Status of SVD Readout Electronics Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012.
VG1 i T i March 9, 2006 W. O. Miller ATLAS Silicon Tracker Upgrade Upgrade Stave Study Topics Current Analysis Tasks –Stave Stiffness, ability to resist.
M. Gilchriese Module Assembly and Attachment at LBNL M. Gilchriese for F. Goozen April 2000.
PXL Cable Options LG 1HFT Hardware Meeting 02/11/2010.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
DOE Rev of Run IIb Sep 24-26, Detector Production WBS James Fast Fermilab.
Y. Ikegami, T. Kohriki, S. Terada Y. Unno (KEK), K. Hara (Univ. of Tsukuba) G. Barbier, F. Cadoux, A. Clark, D. Ferrere, S. Gonzalez-Sevilla, D. La Marra,
The LHCb Outer Tracker Front End, what does it look like and what is the status Talk for the LHCb Electronics Working Group /TS A Collaboration.
ATLAS PIXEL SYSTEM OVERVIEW M. Gilchriese Lawrence Berkeley National Laboratory March 11, 1999.
D. Nelson October 7, Serial Power Overview Presented by David Nelson
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
LHC CMS Detector Upgrade Project FPIX Cooling Update Stefan Grünendahl, Fermilab For the FPIX Mechanical Group, 29 January 2015 Stefan Grünendahl,
Stave Hybrid/Module Status. Modules Stave Module Building 2 Mechanical Chip Gluings Mechanical Wirebonding Electrical Chip Gluings Electrical Wirebondings.
Sensor testing and validation plans for Phase-1 and Ultimate IPHC_HFT 06/15/ LG1.
L0 Module Testing and Analog Cable What we built so far: –No.3 First prototype with SVX4 (L1 hybrid) –No.4 with irradiated sensor –No.5 Installed on the.
Pixel power R&D in Spain F. Arteche Phase II days Phase 2 pixel electronics meeting CERN - May 2015.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
Walter Sondheim 6/9/20081 DOE – Review of VTX upgrade detector for PHENIX Mechanics: Walter Sondheim - LANL.
Strip Tracker Costing Analysis Status Carl Haber July 25, 2011.
Rutherford Appleton Laboratory Particle Physics Department 1 Serial Powering Scheme Peter W Phillips STFC Rutherford Appleton Laboratory On behalf of RAL.
PHENIX Safety Review Overview of the PHENIX Hadron Blind Detector Craig Woody BNL September 15, 2005.
Jan 24, 2005Tracking Upgrades Welcome and Agenda Carl Haber 1 US ATLAS: Meeting on SLHC Tracking Upgrades Jan 2005 Lawrence Berkeley Lab Welcome.
EOS and type I Prototype Service Modules Mike Dawson (Oxford), Rob Gabrielczyk (RAL), John Noviss (RAL) 19 th January 2015 ATLAS Upgrade Activities, Oxford.
March 25, FVTX Monthly/Quarterly Report June, 2009 Technical Status, Cost & Schedule Melynda Brooks, LANL.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
Juan Valls - LECC03 Amsterdam 1 Recent System Test Results from the CMS TOB Detector  Introduction  ROD System Test Setup  ROD Electrical and Optical.
DOE CD-2/3a Review of the BTeV Project – December 14-16, BTeV Pixel Detector Pixel Module Assembly and Half-Plane Assembly Guilherme Cardoso James.
C. Haber / M. Gilchriese Integrated Stave Electrical/Mechanics/Cooling Update February 6, 2008.
Technical Design for the Mu3e Detector Dirk Wiedner on behalf of Mu3e February Dirk Wiedner PSI 2/15.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
1 FANGS for BEAST J. Dingfelder, A. Eyring, Laura Mari, C. Marinas, D. Pohl University of Bonn
Update on the activities in Milano M. Citterio and N. Neri on behalf of INFN and University of Milan SuperB Meeting: SVT Parallel Session.
SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012.
2 March 2012Mauro Citterio - SVT Phone meeting1 Peripheral Electronics Some updates Mauro Citterio INFN Milano.
SiW Electromagnetic Calorimeter - The EUDET Module Calorimeter R&D for the within the CALICE collaboration SiW Electromagnetic Calorimeter - The EUDET.
SVD Electronics Constraints
Markus Friedl (HEPHY Vienna)
Technical Design for the Mu3e Detector
Hybrid Pixel R&D and Interconnect Technologies
Integrated Stave Electrical and Assembly
Presentation transcript:

C. Haber 6-Mar-08 Integrated Stave Electrical/Mechanics/Cooling Update March 6, 2008

C. Haber 6-Mar x 3 cm, 6 chips wide 10 x 10 cm, 10 chips wide 1 meter, 3 cm strip, 30 segments/side 192 Watts (ABCD chip), ~2.4 % Xo + support structure 1 meter, 2.5 cm strip, 40 segments/side Watts W/chip) ~1.9 – 2.2 % Xo + support Stave-07 Stave cm, 9 cm strip, 6 segments/side Stave-08 Prototypes and Designs Build and test Study

C. Haber 6-Mar-08 3 Introduction With regard to the Single Sided approach, the arguments about simplicity, material, and cost, have been presented already. This effort is tightly coupled to the alternative powering efforts, in particular serial, but we would hope to include aspects of DC-DC as well, in the future. We are concerned that in a large, for example, serial system, grounding, shielding, and modularity issues may be critical Our goal, therefore, is to build and test a realistic scale system early-on, and include enough options and flexibility to be useful. With regards to the above, and also to assembly and production issues, we want to confront as much of the full problem as possible, now.

C. Haber 6-Mar-08 4 Aspects Status overview Components Fixtures Electrical testing Additional critical tests Alternatives

C. Haber 6-Mar-08 5 Issues From Valencia Progress on testing and fabrication of Stave-07 Irradiation of hybrids glued directly on silicon surface Thermal performance of bridged hybrid Planning for Spring 2008 module review

C. Haber 6-Mar-08 6 Status Overview Central goal is assembly and test of Stave Confront assembly, test, and measurement issues relevant to future Have built ~30 hybrids, and operated 5 in a serial chain with good performance Have built and are studying 4 modules with hybrid on the silicon and 1 “reference” module with hybrid off the silicon Effort on gluing and alignment procedures implicit in module building Bus cable has been fabricated –Extra clock lines have been added to allow options for clock distribution included 1 clock for 30 module or 1 clock for 10 modules All components required to build Stave-2007 are in-hand. Bridged hybrid has been further simulated and clarified Irradiation plans underway

C. Haber 6-Mar-08 7 Components 3 cm p-in-n sensors based upon ATLAS-98 Fanouts – from SCT 6 ABCD chip, serial powered ceramic hybrid –Approx 30 built and tested with good yield Stave mechanical core –Ready and waiting Assembly fixtures –In use Interface pc boards Bus cable fabrication complete, delivered DAQ system (NI-PXI card + LV software) Power supplies

C. Haber 6-Mar ABCD BeO Ceramic Hybrid ~30 fabricated and tested Yield is (surprisingly) good! Represents a density maxima Includes HV-GND options within serial scheme Analog performance is right-on-target Ceramic flatness is engineered by printing but not perfect. Ground layer Power layer Analog power Digital power Analog current LVDS section Serial power section

C. Haber 6-Mar-08 9 Hybrid HV-GND options HV in HV Gnd AV-MOD AG-MOD AC gnd

C. Haber 6-Mar Fixtures for Assembly AND Test

C. Haber 6-Mar Module Assembly and Test Fixture  volve a  single fixture for assembly, bonding, inspection, and test.

C. Haber 6-Mar Bus Cable Signal Layout Serial current link Serial current return HV distribution Clock & Command lines Data Readout 1/hybrid Port Card

C. Haber 6-Mar Bus Cable: Shielding  l foil, 50 um thick, can be grounded to each hybrid

C. Haber 6-Mar DAQ

C. Haber 6-Mar HV Supply for 30 step serial system GENH V 0-5 A Constant current or constant voltage mode 30 step ABCD system will require ~120 V and 0.75 A. Supply is in-hand, preparing to test using hybrid test board daisy chain and then bus cable

C. Haber 6-Mar Electrical testing Hybrid performance –verified Serial powering with increasing drops –5 OK, new supply allows full 30 drop test Data transmission in a multi-drop system –5 test board system OK, now confront full bus cable, Santa Cruz Module performance –In progress, see slides Grounding and shielding on a stave –upcoming Effect of glue Radiation effects

C. Haber 6-Mar Module Performance Reference module (hybrid off silicon) shows excellent performance, low leakage, low noise, and correct gain Assembly of 4 “hybrid-on” modules has been a learning curve and not without incident One module shows good leakage and analog performance while the others have larger currents. Adopting additional safeguards and procedures in order to control performance. Note – for Stave-06 multiple good “glued-on” modules were built and characterized Input 2fc ref Glued on

C. Haber 6-Mar continued Ref Glued on

C. Haber 6-Mar Additional Critical Tests Glue studies –Once we get the module assembly process under-control, plan a systematic glue testing program –Temperature cycling –Load with thermal filler (BN) –… –Needs to be repeated on n-in-p sensors as well. Irradiations –See slides Bridged hybrid –See slides

C. Haber 6-Mar Irradiation plans Irradiations are in planning phase both at BNL and LBNL BNL is looking at BNL, Boston, and Los Alamos sites LBNL would use on-site 55 MeV protons Hope to have first runs in the next few months A key set of questions here are what would constitute a meaningful measurement? –Conditions –Particle type –Specifics of detector design One point of view holds this to be purely a surface issue which could be addressed with a gamma source…opinions? Ultimate skepticism? Note: CDF and D0 have run with glued hybrids for >5 years

C. Haber 6-Mar Alternatives The bridged hybrid has always been the ATLAS preference FEA indicates reasonable performance for this alternative However the ultimate material reduction would come from reducing the hybrid substrate even more –A kapton flex or other thin film hybrid with essentially no substrate, glued directly on the silicon, would minimize material –We are not wed to the ceramic technology – it was convenient and low risk for us. –We would be happy to see others pick this challenge up and move it forward! –Since the 6 chip serial hybrid is known to work electrically, we are importing the layout into a fine-pitch printed board design which could be adopted for flex or other etched approaches. We can make this available to the community.

C. Haber 6-Mar FEA Models of Bridged Hybrid - I Since the Valencia meeting we have completed FEA analysis of basic thermal performance with bridged hybrid Multiple models to achieve reliability and understanding ¼ simple model, similar to ANSYS model by others, air treated as “solid” under bridge ½ model with air box to allow for 3D air effects (not just under bridge), no air flow Air gap ¼ model Air box for 1/2 ½ model

C. Haber 6-Mar FEA Models of Bridged Hybrid -II Multi-hybrid model Multi-hybrid model, with air flow included(so far 0.01 m/sec) For simplicity, all studies so far done with tube wall temperature fixed at -28C, 0.25 W/IC and no detector heating. Goal is to compare first with glued hybrid under same conditions More details are here and herehere

C. Haber 6-Mar Short Summary Good agreement among models Modest effect of gas flow Reduced K means lower than nominal K in structure. No optimization of structure yet For comparison, nominal design (hybrids glued on silicon) for comparable assumptions yields max sensor temperature of about -22.5C ModelIC Peak Temp(C) Bridge Gradient(C) Sensor T Max(C) ¼ model ½ model With air flow -15C gas ¼ model Reduced K

C. Haber 6-Mar Conclusions Focused attempt to address the plans and issues discussed in Valencia All components for Stave-2007 are in-hand Approach is friendly to alternatives – bridges etc We welcome the participation, input, or suggestions of the community Look forward to preparing for the June review