Capital Improvements Element (CIE) Annual Update Adoption Public Hearing April 5, 2011
Overview Legislative Requirements CIE Update Summary Policy Amendments Interlocal Agreement Requested Action Presentation Outline
Overview Legislative Requirements CIE Update Summary Policy Amendments Interlocal Agreement Requested Action Presentation Outline
Capital Improvements Element Required element in the Comprehensive Plan Designed to consider the need for, and location and timing of, public facilities Ensures public facilities will be available and adequate to provide acceptable levels of service (LOS) Ensures that the Comprehensive Plan is financially feasible Overview
Concurrency The premise of concurrency is that public facilities and services will be available concurrent with the impacts of development Local government sets LOS standards, and concurrency ensures that those LOS standards will be achieved and maintained Overview
Level of Service (LOS) Standards Identified for concurrency-related facilities Parks and recreation Roads Schools Solid waste Stormwater Water and wastewater Provide a quantitative tool to analyze the impacts of land use changes Overview
Financial Feasibility Must demonstrate ability to achieve and maintain adopted LOS standards For any facilities required to achieve LOS: Projects in FY1-FY3 must be funded through a committed funding source Projects in FY4-FY5 may be funded by committed or planned sources Overview
Funding Sources Committed funding source: An existing source and amount of revenue presently available to a local government Planned funding source: A revenue source not currently available, such as a potential grant Overview
Capital Improvements Element Includes Location and timing of needed facilities Principles for construction, extension or increase in facility capacity Principles for correcting existing deficiencies Estimated costs and projected revenue sources A capital improvements schedule (CIS) that ensures that adopted LOS standards are achieved and maintained Overview
Capital Improvements Element Data and Analysis Goals, Objectives and Policies Capital Improvements Schedules Overview
Capital Improvements Element Data and Analysis Projected public facility demand Levels of service for public facilities Summary of revenues and expenditures Identification of any deficiencies Overview
Capital Improvements Element Goals, Objectives and Policies Plan for and manage public facilities to adequately serve existing and new residents Require maintenance of adopted LOS standards Coordinate development approval with the Capital Improvements Program Require future development to bear its fair share cost for facility improvements Maintain a Concurrency Management System Overview
Capital Improvements Element Schedules For each concurrency-related facility Capital Improvements Schedule 10-Year Facilities Work Plan OCPS District Capital Outlay Plan Long Term Concurrency Management Systems (LTCMS) Overview
Overview Legislative Requirements CIE Update Summary Policy Amendments Interlocal Agreement Requested Action Presentation Outline
2005 Growth Management Legislation Enacted penalties for not adopting an annual update of the Capital Improvements Element (CIE) by December 2008 CIE and Capital Improvements Schedule (CIS) must demonstrate financial feasibility Legislative Requirements
2009 Growth Management Legislation Delayed the CIE requirements to December 2011 County’s update continued to meet the financial feasibility standards during the grace period Department of Community Affairs (DCA) currently reviews CIE under the guidelines provided in 2009 Legislative Requirements
2011 Legislative Proposals Further delay annual update requirement to 2013 Remove financial feasibility requirement Allow annual adoption at local level (no state review) Remove state-mandated concurrency for transportation, schools and parks Legislative Requirements
Overview Legislative Requirements CIE Update Summary Policy Amendments Interlocal Agreement Requested Action Presentation Outline
Summary Few changes from the CIE Update Identified deficiencies have been addressed by policy or with projects included on the CIS Deficient roads or schools have been included in Long Term Concurrency Management Systems (LTCMS) CIE Update
Summary Revised the list of backlogged Concurrency Service Areas (CSAs) for schools Backlogged CSAs previously identified will meet LOS by 2017; backlogged CSAs added this year must meet LOS by 2020 Backlogged CSAs are addressed in the OCPS District Work Plan CIE Update
Policy Amendments CIE1.1.13: Updates reference to the CIP CIE : Adds language indicating that projected school LOS information and CSA boundary maps are provided annually by OCPS CIE : Updates reference to the OCPS District Capital Outlay Plan CIE Update
Policy Amendments CIE1.3.18: Creates a separate LTCMS for additional backlogged CSAs PS6.1.1: Clarifies language related to the LTCMS for schools PS6.1.11: Clarifies that CSA boundaries are reviewed annually with the CIE update CIE Update
First Amended and Restated School Interlocal Agreement (ILA) Revises ILA provision requiring an ILA amendment for modifications to CSAs and LTCMS Adds language stating that such changes can be made solely by amending the Comprehensive Plan These revisions were coordinated with DCA, DOE, OCPS and affected municipalities CIE Update
Timeline LPA AdoptionNovember 18, 2010 BCC AdoptionApril 5, 2011 DCA NOILate May, CIE Update
Overview Legislative Requirements CIE Update Summary Policy Amendments Interlocal Agreement Requested Action Presentation Outline
Make a finding of consistency with the Comprehensive Plan and adopt Amendment B-CIE-1 (the annual CIE update), which includes amendments to the Capital Improvements and Public School Facilities elements Approve the First Amended and Restated Interlocal Agreement for Public School Facility Planning and Implementation of Concurrency Action Requested
Capital Improvements Element Annual Update Adoption Public Hearing April 5, 2011