CMX Production Status Presented to the L1Calo Meeting on Monday 22-Sept-2014 by Dan Edmunds for the CMX Group.

Slides:



Advertisements
Similar presentations
02/06/2014James Leaver Slink Transition Card. 02/06/2014James Leaver Slink Transition Card Simple 6U board: –Provides interface between FED and Slink.
Advertisements

Controller Tests Stephen Kaye Controller Test Motivation Testing the controller before the next generation helps to shake out any remaining.
CMS Week March presented by John Coughlan RAL FED Hardware Status Pre-Series Manufacture Final Production Plans.
ROD R&D Status K. Johns, C. Armijo, J. Steinberg (U. Arizona) H. Chen, F. Lanni, J. Mead (BNL) L. Hervas (CERN) A. Meyer, A. Kielburg-Jeka, A. Straessner.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
2012 CALENDAR. JANUARY 2012 Sunday 日 Monday 月 Tuesday 火 Wednesday 水 Thursday 木 Friday 金 Saturday 土
Uli Schäfer 1 JEM: Status and plans Pre-Production modules Status Plans.
Endcap Muon meeting: UC Davis, Feb , 2005 J. Hauser UCLA 1 TMB and RAT Status Report Outline: Current status of TMB and RAT boards Noise measurements.
January 2012 Monday Tuesday Wednesday Thursday Friday Sat/ Sun / /8 14/15 21/22 28/
Uli Schäfer 1 JEM: Status and plans Pre-Production modules Status Plans.
3 May 2005Claudio Campagnari (UCSB)1 Status of Rod Production at UCSB This report covers the last two weeks Reporting for: Dan Callahan Susanne Kyre Stephen.
ROD R&D Status K. Johns, C. Armijo, J. Steinberg (U. Arizona) H. Chen, F. Lanni, J. Mead (BNL) L. Hervas (CERN) A. Meyer, A. Kielburg-Jeka, A. Straessner.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
Uli Schäfer 1 JEM: Status and plans Production / commissioning Plans.
Uli Schäfer 1 Production modules Status Plans JEM: Status and plans.
GLAST LAT ProjectF-to-F, June 15, TrackerR.P. Johnson 1 GLAST Large Area Telescope: Tracker, W.B.S Face-To-Face June Meeting Robert Johnson.
MONDAYTUESDAYWEDNESDAYTHURSDAYFRIDAYSATURDAYSUNDAY WEEK WEEK WEEK WEEK WEEK CALENDAR PROJECT.
INJECTORS BLM BI-TB on Proton Injector start-up. Summary of actions 2 BLM SystemComments LINAC2 8 movable detectors.
Status and planning of the CMX Philippe Laurens for the MSU group Level-1 Calorimeter Trigger General Meeting, CERN May 24, 2012.
John Coughlan CMS Week Mar FED Update FED Production Status Transition Card.
Update on APV25-SRS Electronics Kondo Gnanvo. Outline Various SRS Electronics Status of the APV25-SRS UVa Test of the SRU with multiple.
Atlas L1Calo CMX Card CMX is upgrade of CMM with higher capacity 1)Inputs from JEM or CPM modules – 40 → 160Mbps (400 signals) 2)Crate CMX to System CMX.
Status of the CSC Track-Finder Darin Acosta University of Florida.
Introducing A New Process For Reporting Financial Data to DPI A Revised Format For The PI-1505 AC.
Hardware status GOLD Generic Opto Link Demonstrator Assess the use of optical backplane connectivity for use on L1Calo Uli Schäfer 1.
L1Topo-phase0 Uli Schäfer 1. Topo GOLD successfully used to explore technologies and initially verify 6.4Gb/s link integrity over moderate length electrical.
Update on the HBD Craig Woody BNL DC Meeting June 8, 2005.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
CSC EMU Muon Sorter (MS) Status Plans M.Matveev Rice University August 27, 2004.
CSC Endcap Muon Port Card and Muon Sorter Upgrade Status May 2013.
CMX status and plans Yuri Ermoline for the MSU group Level-1 Calorimeter Trigger Joint Meeting CERN, October 2012,
CMX status Yuri Ermoline for the MSU group Mini-TDAQ week, CERN, 9-11 July 2012,
Upgrade of the CSC Endcap Muon Port Card and Optical Links to CSCTF Mikhail Matveev Rice University 17 August 2012.
Upgrade of the CSC Endcap Muon Port Card Mikhail Matveev Rice University 1 November 2011.
Status and planning of the CMX Wojtek Fedorko for the MSU group TDAQ Week, CERN April , 2012.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
CMX Hardware Status Chip Brock, Dan Edmunds, Philippe Yuri Ermoline, Duc Bao Wojciech UBC Michigan State University 25-Oct-2013.
CMX Hardware Overview Chip Brock, Dan Edmunds, Philippe Yuri Wojciech Michigan State University 12-May-2014.
06/02/02CERN - LARG meeting1 CALIBRATION BOARD STATUS  Status of the DMILL chips used on the calib. boards  Low Offset Op Amps: Offset measurements 
PMG, Aug 03, 2000 Slide 1 Schedule In preparation Done Started Done Started Half done.
ATLAS Trigger / current L1Calo Uli Schäfer 1 Jet/Energy module calo µ CTP L1.
John Coughlan Tracker Week October FED Status Production Status Acceptance Testing.
CMX Hardware Overview Chip Brock, Dan Edmunds, Philippe Yuri Wojciech Michigan State University 19-May-2014.
March 2005, USCMS Trigger video meetingD. Acosta1 Revised Schedule for SP Pre-Production Continued testing of first two pre-production boards over next.
Tracker Week October CCLRC, Rutherford Appleton Laboratory, Oxon, UK Imperial College, London, UK Brunel University,
SP04 Production Lev Uvarov RICE Muon Trigger Meeting August 27, 2004.
SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:
22AUG07 Gun System Update1 Rich Andrews. 22AUG07 Gun System Update2 Gun System Coaxial coupler Gun Cavity Solenoid Magnet Compensator Magnet.
SRS Trigger Processor Option Status and Plans Sorin Martoiu (IFIN-HH)
1 HBD: Update and Schedule Itzhak Tserruya DC Meeting, BNL, April 13, 2005 Outline:  Full scale prototype status  Light source test  Construction Schedule.
Upgrade of the CSC Endcap Muon Port Card with Spartan-6 FPGA Mikhail Matveev Rice University 30 April 2012.
J. Linnemann, MSU 2/12/ L2 Status James T. Linnemann MSU PMG September 20, 2001.
FEE Electronics progress Mezzanine layout progress FEE64 progress FEE64 initial testing Test mezzanine. A few of the remaining tasks 2nd October 2009.
TEL62 update Franco Spinella INFN-Pisa 28/3/2012 CERN- TDAQ WG.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
1 Status of Validation Board, Selection Board and L0DU Patrick Robbe, LAL Orsay, 19 Dec 2006.
VC707 Evaluation Kit Xilinx Virtex-7 In_0 GTX MHz IDELAY 8B/10B Serilizer 7 0 7IDELAY 0=>K28.5 0=>K28.1 D(15:0) K(1:0) 8B/10B IDELAYCTRL LHC_Clk.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
CMX: Update on status and planning Yuri Ermoline, Wojciech Dan Edmunds, Philippe Laurens, Chip Michigan State University 7-Mar-2012.
News about the WA104 Programme C. Montanari – INFN and CERN technical working group meeting, September 16,
Status Report of the PC-Based PXD-DAQ Option Takeo Higuchi (KEK) 1Sep.25,2010PXD-DAQ Workshop.
DAQ / Trigger Card for HCAL SLHC Readout E. Hazen - Boston University
DCFEB Production for LS2
Upgrade of the CSC Endcap Muon Port Card and Optical Links to CSCTF
University of California, Los Angeles Endcap Muon Purdue
CCB to OH Tests at Rice M.Matveev Rice University May 12, 2016.
Joint Meeting Wrap-up I’ve cheated Partially justified?
CMX Status and News - post PRR -
CMX scope and functionalities
STAR-CBM Joint Workshop Heidelberg, Physikalisches Institut
Presentation transcript:

CMX Production Status Presented to the L1Calo Meeting on Monday 22-Sept-2014 by Dan Edmunds for the CMX Group

This talk describes the production of the CMX cards, the problem that we had with the backplane connectors on some of these cards, and the outlook for delivery of cards for the M6 test and the completion of all CMX cards. The CMX cards were produced in a prototype build of 4 cards in February 2014 and a production build of 20 cards in June Sept-20142

In addition to the 7 CMX cards that were at CERN, we shipped an additional 4 cards to be installed for the M5 test. That test began on September 8th. These 4 cards were in Geneva by August 29th. We currently have 2 more cards at MSU that are tested and ready to use. One of these cards is a dual Virtex card that I prefer not to ship to CERN at this time. 22-Sept-20143

We have 1 additional card that is through the MSU Final Assembly process and ready for MSU Testing. Currently I’m not working on testing that card. Rather I’m working with the a ”first article” card that has had its backplane connectors replaced. 22-Sept-20144

During the June build of the 20 production CMX cards there were 9 cards that I did not accept because of poor alignment of their backplane connectors. Typically these connectors had been pressed in too far. Originally the assembly house was going to replace the backplane connectors on these 9 cards. I did not pressure the assembly house to immediately do this repair work because I was working with the other 11 production cards and I wanted to give them time to develop a safe effective re-work process to replace these connectors. 22-Sept-20145

By the beginning of September they were still having trouble developing a method to replace the backplane connectors in a way that I felt was safe for the rest of the card. We mutually decided that it was best if they sent out these 9 cards to a re-work house that specializes in this type of repair work. The original assembly house is paying for this specialized re-work. 22-Sept-20146

I asked to examine a ”first article” card with replaced connectors before I would approve work on the other 8 cards. I received the first article card late Thursday afternoon September 18th. In testing this card I specifically want to verify that all 400 processor connections to the backplane are working correctly. That is a test that we do during MSU Testing of all of CMX cards. I hope to give the go ahead to replace the backplane connectors on the remaining 8 cards by Tuesday September 23rd. The rework of these remaining 8 cards is expected to take one week. 22-Sept-20147

As you may have heard, at one time we were having trouble with one SFP optical transmitter on one CMX card. During the testing of subsequent production cards we found the same problem with the same or different SFP transmitter channel on a few other cards. We now know that in all cases these SFP transmitters work fine if their associated GTX transceiver is given a single reset after the FPGA is Configured. After one transceiver reset we have not seen any SFP errors on any channels for as long as we have run tests. 22-Sept-20148

As far as I know at this time we will not have a problem supplying 4 more tested standard production CMX cards for the M6 test in October. As far as I know at this time we will not have a problem completing MSU Final Assembly and MSU Testing of all 24 of the CMX cards. 22-Sept-20149

The following is a link to the current CMX Card Production Status. This file gives the status of each CMX card and includes notes and information about the production of the CMX cards. /hardware/details/cmx_production_status.txt /hardware/details/cmx_production_status.txt The final slides of this talk are a snapshot from this CMX production status file and provide a line of information about each of the 24 CMX cards. 22-Sept

22-Sept

22-Sept