February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)

Slides:



Advertisements
Similar presentations
MICE Target Report Video Conference 15/03/07 Chris Booth Sheffield 15 th March 2007.
Advertisements

Plans for Diagnostic Removals, Storage, and Re-installations during NSTX Upgrade Outage B. Stratton NSTX Team Meeting 9/13/2011.
Engineering Operations Outage Status: Post-run diagnostic calibrations have been completed and in-vessel work can start on PCHERS, FIDA, MPTS, and the.
August NSTX-U Team Meeting. Engineering Operations August 15, 2014 NSTX-U In-Vessel installations and calibrations have concluded, and activities have.
Chubaka Producciones Presenta :.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
2012 JANUARY Sun Mon Tue Wed Thu Fri Sat
MICE RF TEST STAND Major Milestones (2006) –Testing of BURLE 4616 circuit September 2006 –Testing of 4616 circuit with full amplitude and phase control.
Michael Scharfenstein FAC October LCLS Environment, Safety & Health Michael Scharfenstein ES&H Coordinator.
E. Michael Saleski PPS and April 20, 2006 LCLS Personnel Protection System and Beam Containment System E. Michael Saleski.
NCSX NCSX DCT Project Meeting Raki Slide 1 Electrical Power Systems (WBS 4) S. Ramakrishnan NCSX PROJECT – D TO C Site DC Transmission PROJECT MANAGEMENT.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
TENNESSEE VALLEY AUTHORITY WATTS BAR NUCLEAR PLANT Ed Freeman Engineering Manager 1.
Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
Machine Installations and Construction Management Erik D. Perry Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318.
NSTX-U Engineering Operations January 28, 2015 NSTX-U Engineering Operations Al vonHalle January 28, 2015 NSTX-U Supported by Culham Sci Ctr York U Chubu.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
+ STAR HFT Upgrade – Installation and Integration Rahul Sharma Brookhaven National Laboratory.
Mark Bowen Acting Theme Leader – Technologies for Radio Astronomy CSIRO Astronomy and Space Science 14 October 2010 Australia Telescope Users Committee.
The NSTX-U Electric Arc Introductory comments on the process of recovery Stewart Prager May, 2015.
Princeton University Plasma Physics Laboratory EVMS Certification Review NSTX Project Overview Ron Strykowsky October 4-6, 2011.
Quality Assurance Readiness for Operations Review Judy Malsbury, Head of QA Princeton Plasma Physics Laboratory NSTX Upgrade LSB B318 December 9-11, 2014.
NSTX-U Transition to Operations Al vonHalle Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318 October 2 nd & 3.
Electrical Integration CM38 Steve Griffiths & Ian Mullacrane.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
F Booster Long Straight Corrector Upgrade Technical Status and Schedule for Installation Craig Drennan DOE Tevatron Operations Review March 27, 2007.
1 NSTX Upgrade Progress Report May 7 th, 2013 Ron Strykowsky, Erik Perry, Tim Stevenson, Larry Dudek, Steve Langish, Tom Egebo, Mike Williams and the NSTXU.
April NSTX-U Team Meeting. Engineering Operations April 25, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in mid-June to shift activities.
WORD JUMBLE. Months of the year Word in jumbled form e r r f b u y a Word in jumbled form e r r f b u y a february Click for the answer Next Question.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the manager of the construction activities in the Test Cell.
Engineering Operations FY08 Outage: In-Vessel Work: –BSE Vacuum Vessel Interfaces Completed –Liquid Lithium Divertor Tray trial fit-ups –HHFW Antennas.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
NSTX Response to the Lessons Learned Report NSTX TF Coil Repair Review September 3-4, 2003 Al von Halle.
Comment on the LHCb upgrade cooling plan Paolo Petagna Meeting on CO 2 Cooling CERN 11 March 2015.
NCSX Field Period Assembly (FPA) Operations, Cost and Schedule, Staffing, and Metrology Utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
NSTX Upgrade Project – Final Design Review June , NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL.
Goddard Space Flight Center Cryogenics and Fluids Branch Status of the AMS-02 Cryocooler January 2007 TIM.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
Engineering Operations Outage Schedule Center Stack casing is scheduled to go back in the vessel today Complete NB armor, Diagnostic calibrations, clean/photo/close,
Thermosiphon project management and quality assurance EN/CV/DC Presentation done by Elena Perez Rodriguez For further information contact
NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14.
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Tom Egebo PPPL Review of the NSTX TF Coil Repair Effort September 3 - 4, 2003 Cost & Schedule to Completion Supported by Columbia U Comp-X General Atomics.
Engineering Operations Outage Status: Tile cleaning is complete Tentatively planning on 2 LITER operation. Design Review upcoming Shielding of HHFW/in-vessel.
Anthony Indelicato DOE-Princeton Site Office February 2014 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
NSTX NSTX Team Meeting –Masa Ono August 14, 2015 Masa Ono February 5, 2016 NSTX-U Team Meeting.
July 2007 SundayMondayTuesdayWednesdayThursdayFridaySaturday
Engineering Operations Outage Schedule The vessel & beamline are under vacuum. 1st Bake-out complete. Air leaks found and fixed. The OH coil will be installed.
Engineering Operations TF Commissioning Mechanical testing of TF flag/box assemblies complete, inner bundle installed, and all joints made up. Joint resistance.
Standard Design Process Overview
TF Fabrication Progress is being made on TF bundle fabrication activities but the schedule remains tight. All 24 outer conductors have been machined but.
SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile NCSX Startup (WBS 85) C.A.Gentile NCSX CD-4 Startup.
Safety Department Fire Drills.
WP-46 XFEL 3rd harmonic system XFEL Project Progress Report (1-2010)
Software and Systems Integration
TIMELINES PHOTOS This is an example text
TIMELINES PHOTOS This is an example text
McDonald’s Kalender 2009.
McDonald’s Kalender 2009.
McDonald’s Kalender 2009.
McDonald’s calendar 2007.
McDonald’s calendar 2007.
ESHAC #8 Safety Readiness Review Thomas Hansson, ESH
Review of hardware commissioning
2015 January February March April May June July August September
Presentation transcript:

February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014) to shift activities to the preparations for installing the new centerstack. All Buswork reinstalled in the NTC by mid–May. Centerstack, flex bus and umbrella covers in place by late August. Clean/Photo/Close in early September, followed immediately by the initial pump-down. NSTX-U turned over to Operations by mid-October. A limited Centerstack bake is planned for late October. Field Coil Power Testing and the ISTP to CD-4 complete by mid-November. –Assumes that a full-bake and some preparations for Physics Operations will occur after CD-4 –Vessel Entry? 1 Transition to Operations Milestones to CD-4

February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U The NSTX-U Activity Certification Committee (ACC), comprised of representatives from PPPL Engineering, Research, Safety, and the DOE PSO is currently reviewing technical and safety systems for NSTX-U –Safety Assessment Doc. (SAD) –Design review documentation and chit resolution –Interviews with cognizant engineers –Plans for pre-operational & integrated system testing –Safety/interlock systems –Physical walk-downs of equipment –Resolution of remedial steps recommended by ACC A PPPL Internal QA Audit of NSTX-U Start-Up Documentation will begin in April An Operational Readiness Review (ORR) is being arranged through the DOE PSO, and is prerequisite for our safety certificate prescribing allowable operating parameters. 2 Approvals for Operations

February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U MG#1 Weld Repairs –Spider Arm weld repair procedures developed and approved by PPPL Engineering, General Electric Co., and our preferred subcontractor. –The Statement of Work has been approved. –Actual weld repairs should be completed in ~ 1 month once a contact is in place and crews mobilized. –Re-assembly, clean-up, controls testing and balancing complete by September Field Coil Power Conversion (FCPC) Commissioning –AC primary Power Systems have been maintained and are ready to support operations –Primary power protective relaying is being calibrated and set. –34 new rectifier firing generators have been delivered to FCPC. Testing in progress –Electromagnetic fault relaying is being replaced with a PLC based system. –New fiber-optics being installed between rectifiers and the Junction Area. –All systems should be ready to support individual rectifier power testing by late March. 3 Preparations for Operations

February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U Digital Coil Protection System (DCPS) –Algorithm development for CD-4 is complete. –Installation of the new water system PLC in March. –Expect to have DCPS hardware and software ready to support multiple rectifier dummy load testing by late May. Power System Real Time Controls (PSRTC) –DCPS Algorithms will be applied to the new PSRTC. –Simulation models and testing (PTP-034) by June. PF1 Field Changes –PF1A Upper and Lower Coils will be powered. –PF1B Upper and Lower will not be powered at the start of the run (terminated into resistors and MOV’s). –FCPC has been configured. –Connections/labeling in the test cell still required. 4 Preparations for Operations

February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U Ip Calculator –Concept established and schematics are being developed. –All parts are expected to be at PPPL by late March. –System testing in May. –Operational by end of July. Stand Alone Digitizers (SAD II) –Plug in replacements for the SAD I. –System FDR in late March. –Assembly/testing complete in May. High Harmonic Fast Wave (HHFW) Compliant Center Conductors –Testing of the prototype successfully completed in the RF test stand. –FDR is scheduled for late February. –Work package being developed to remove HHFW components for upgrades in late February. –All parts to complete antennas not expected until mid-April. 5 Preparations for Operations

February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U Neutral Beam #2 –Primary power systems and protective relaying being prepared to start power supply testing in March. –NB#2 is expected to be ready to pump-down in June. –Refrigerator start-up and cryogenic cool-down as early as July. –Need to be able to start ion source pre-operational testing (PTP-11) in September to complete the NB#2 CD-4 in November. 6 Preparations for Operations