Quarterly Review January 24, 2002 1 QUARTERLY REVIEW January 24, 2002.

Slides:



Advertisements
Similar presentations
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
Advertisements

1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Protocol & Test Review Spaceport America Student Launch University/Institution Team Members Date.
Data Test Review Spaceport America Student Launch University/Institution Team Members Date.
Flight Readiness Review New Mexico Space Grant Consortium University/Institution Team Members Date.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
Development of Laser Fuser Test Bed Project Number: P07501 Justin McMillan.
Marion M. White Undulator System 07 April 2005 LCLSLCLSLCLSLCLS Undulator System Tests Marion M. White ANL-ASD-LCLS.
Global Magnet Systems including Field Mapping MICE Project Board 28 th June 2011 M Courthold – RAL R Preece - RAL.
WBS & AO Controls Jason Chin, Don Gavel, Erik Johansson, Mark Reinig Design Meeting (Team meeting #10) Sept 17 th, 2007.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
Integration and Test 14 October 2008 Martin Nordby.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
Quarterly Review June 13, QUARTERLY REVIEW June 13, 2001.
RF Cavity / Coupling Coil Module
Quarterly Review October 5, QUARTERLY REVIEW October 5, 2001.
Quarterly Review May 1, QUARTERLY REVIEW May 1, 2002.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
18/19 January 2003IMACS SAC meeting update1 IMACS: Inamori-Magellan Areal Camera and Spectrograph Magellan SAC Status Report 18/19 January 2003 OCIW, Pasadena,
GLAST Large Area Telescope:
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
PACS IIDR 01/02 Mar 2001 Instrument Interfaces1 PACS FPU Opto-mechanical Design Overview and Interfaces J. Schubert MPE.
Quarterly Review August 15, GNIRS Quarterly Review August 15, 2000.
ATLAS Endcap Muon System WBS 3.5 Frank Taylor MIT M&O Request FY06 Toronto August 3, 2005 V1.1.
ASPERA-3 Apr. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 4_25/ Page 1 Monthly Status Report Report due 4/25/00 Schedule statused.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
Telescope Integration and Tests Tuesday Afternoon.
ASPERA-3 Jan. 25, 01 Monthly Status Report ASPERA Monthly Status ReportMonthly 1_25/ Page 1 Monthly Status Report Report due 1/25/01 Schedule statused.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
Magellan F/5 System Status A.Szentgyorgyi / Ann Arbor 25 Sept 2005.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
University of Southern California Center for Systems and Software Engineering Barry Boehm, USC CS 510 Software Planning Guidelines.
1 BROOKHAVEN SCIENCE ASSOCIATES ASD Procurements Gregory Fries Liaison/Manufacturing Engineer NSLS-II ASAC October 22-23, 2009.
ATLAS Muon System WBS 3.5 DoE/NSF M&O Evaluation Group Review BNL 19-Jan-06 Frank Taylor MIT V1.3.
GLAST LAT ProjectFace to Face Managers Meeting 04/14/ Integration and Test 1 GLAST Large Area Telescope: I & T Input to Face to Face Managers.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
GLAST LAT Project – Cost and Schedule ReviewJanuary 27, 2004 AntiCoincidence Detector 1 GLAST Large Area Telescope: Cost/Schedule Review January 27, 2005.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
DBSP-R Upgrade Progress Review The DBSP-R Team DBSP-R Progress Review.
Quarterly Review November 15, GNIRS Quarterly Review #4 November 15, 2000.
ASPERA-3 Mar. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 3_25/ Page 1 Monthly Status Report Report due 3/25/00 Schedule statused.
P. Shanahan Nov 15, 2003 Page 1 MINOS WBS 2.3: Electronics, DAQ and Database Status Accomplishments since May review Near Detector Electronics production.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
G. Carboni - Muon Meeting – Muon Meeting 12/ Agenda IntroductionGiovanni (30’) GEM and TDR AddendumWalter (20’) Update on M1 ratesAlessia.
ATLAS Pixel Detector July 2003 SC Pixel Meeting N. Hartman LBNL 1 Pixel Support Tube WBS Santa Cruz Cost Workshop July 9, 2003.
FourStar Status SAC Meeting 13mar2010 Persson, Murphy, Birk, Monson, Kelson, Uomoto.
LAT Design Integration and Analysis1 GLAST LAT Project24 May 2005 LAT Monthly Status Review 24 May 2005 Design Integration and Analysis LAT Monthly Status.
LAT-PR GLAST LAT ProjectManufacturing Readiness Review, Oct. 12, 2005 LAT Test Stand Manufacturing Readiness Review 1.Introduction Bill Olson.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Oct 17, 2001SALT PFIS Preliminary Design Review Management, Schedule, & Budget 1 Southern African Large Telescope Prime Focus Imaging Spectrograph Management,
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
LCLS-II Prototype Cryomodule Vacuum Vessel and HGRP Tom Peterson 4 December 2014 Design Review.
Content Lessons from writing proposals and work on PTDR How can this meeting help to remedy problems SCT AOB.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Jim Fast Pacific Northwest National Laboratory
Agenda ComCam planning and scheduling (James & Jacques) CCS & CCS-TCS Interface (Tony) Software to use ComCam Software to get data out of ComCam (Mike)
Telescope Assembly, Integration and Verification (AIV) WBS 04C. 14 J
WBS 1.03 Readout Systems Scope, Cost and Schedule
Software Planning Guidelines
COSMOS Status David Sprayberry, Sean Points & Jay Elias
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
Management Breakout: MREFC Budget Summary Victor L
FourStar 4K x 4K JHK imager
LGS Project Meeting December 21, 2006 Agenda SWIFT update - A. Bouchez
GLAST Large Area Telescope
Presentation transcript:

Quarterly Review January 24, QUARTERLY REVIEW January 24, 2002

Quarterly Review January 24, Agenda 0830QR - Project Overview 0930break 0945QR - Technical Progress 1045 Break 1100QR - Management 1200Lunch 1300Tour of design area workstations 1330Hardware tour - Instrument Shop - EE Lab - Blue Room 1400Software - Hardware Demo

Quarterly Review January 24, GNIRS Quarterly Review Table of Contents IntroductionPg 4 Project SummaryPg 6 Configuration & IntegrationPg 23 Project ManagementPg 43 AppendicesPg 64

Quarterly Review January 24, Introduction This is the 7 th GNIRS Quarterly Review GNIRS is in the final design and fabrication phase –All bench assemblies are complete –Bulkhead and Dewar Shell assemblies are complete –Mechanism fabrication is complete –Mechanism testing is underway –OIWFS integration is complete except for the detector We are on track for delivery in October of 2002

Quarterly Review January 24, Outline Project summary –Last QR Response –Progress Overview –Cost and Schedule Status Problems and Concerns Configuration Update Technical Progress Project management Plans for next review

Quarterly Review January 24, Project Summary Response to last QR report Progress overview Summary schedule Work left Budget and expenditures to date

Quarterly Review January 24, Response to October QR - Issues to be Reviewed Completion of items –OIWFS integration –Lens delivery/testing –Mechanism fabrication –Mechanism/optical testing –Fixed Assy 3D/2D design –TE fabrication –Bulkhead fabrication –Dewar component fabrication –Optics procurement ATP (Plan) Design delays –Radiation Shields Rework items OIWFS issues IFU late delivery Change orders Documentation approach

Quarterly Review January 24, Task Status ITEMSTATUSCOMMENT OIWFS component integrationComplete – Detector installation on hold Waiting for Gemini decision on prism. February cut-off date. Lens delivery/testingComplete Mechanism fabricationCompleteSome rework in process Mechanism/optical testingNot Complete – delayed because of fabrication delays Should complete in March Fixed Assembly 3D/2D designNot Complete – Radiation shields still in process Completion expected in January TE fabricationComplete Bulkhead fabricationCompleteFit checks complete except for radiation shields Dewar component fabricationComplete Optics procurementNot Complete – Simulator optics not yet purchased Simulator is in design stage. Not a pacing item. Rescheduled to a later date.

Quarterly Review January 24, Response to October QR Planned Completions by this Quarterly Review –3D and 2D design of all fixed assemblies –Fabrication of all mechanisms –Fabrication of the Bulkhead Assembly –Mechanical fabrication except for: Rework items Shipping container Items associated with flexure testing –Mechanism and optical subassembly testing –Receive all optics –Electronics fabrication and checkout except for: Some cables Rework items –Initial software coding –Component controller software testing –OIWFS component integration –Change orders for Chile Delivery and for Differential Pressure Switch –Manual outlines

Quarterly Review January 24, Response to October QR ATP –A draft of the ATP and commissioning plan was submitted to Gemini for review; returned with minor comments last week Change Orders are in process –For Chile delivery –For the Differential Pressure Switch Manual outlines –Maintenance Manual in process –Software and Operation manuals are not started

Quarterly Review January 24, Response to October QR Software coding –Component controller software Coding is complete Checkout complete as far as can be done without actual hardware to exercise All checks with the electronics are complete –EPICS software is 95% complete IFU late delivery –Proceeding with mass modules –We will try to integrate the IFU when it becomes available

Quarterly Review January 24, Summary Project Plan

Quarterly Review January 24, Revised Bench Integration Plan

Quarterly Review January 24, Work Left – Integration Plan Two critical areas –Radiation shields –Mechanism testing Need passive shields first so bulkhead can be assembled and wired Active shields needed for integration of bench into dewar Key resources –Electrical technician for wiring –M&P engineer and technician for cleaning and prep work –Scientists for testing –Mechanical engineers and designers for shields –Instrument makers for assembly/rework/testing

Quarterly Review January 24, Project Status - Progress from August ’99 WBS element Mar June October January 5.0 Overall project 53% 66% 80% 86% 5.1 Management & Reporting 51% 61% 71% 80% 5.2 Systems Engineering 100% 100% 100% 100% 5.3 Mechanical 52% 70% 87% 94% Mechanisms 66% 84% 92% 97% Benches 55% 70% 100% 96% Fixed Assemblies 16% 36% 62% 84% 5.4Electronics 63% 59% 86% 71% 5.5Software 49% 63% 85% 86% 5.6Integration 0% 0% 2% 23% 5.7Deliverables 0% 0% 0% 45% 5.8Procurement 54% 67% 77% 86%

Quarterly Review January 24, Progress Overview The delivery date of the instrument is now October 24, 2002 –Delay radiation shield design –Delay in mechanism testing The project is currently 86% complete overall We have completed 170 of 226 total project milestones Our critical path(s) are –Radiation Shields: 3D and 2D design and fabrication –Mechanism testing Electronics fabrication left is mechanism and dewar wiring Software Component Controller code is essentially complete

Quarterly Review January 24, Focus of Last Quarter of Work Design/fabrication activity concentrated on –Radiation shield design –Bulkhead Assembly fabrication/acceptance tests/fit checks –Fit checks and fixes –Mechanism warm tests, flexure tests, rework –Assembly cleaning and wiring, prep for integration and/or cold testing –Final fixed assembly fabrication: trusses, etc. –Telescope simulator design –General design cleanup (configuration control) Procurement –Mechanical –Optical

Quarterly Review January 24, Progress and Schedule Comments Mechanical design virtually complete –Radiation Shields and the Thermal Distribution Assembly remain Fabrication will continue through March on shields Sub-assembly flexure testing complete Mechanism fabrication is essentially complete –Minor rework in process Focus mechanism Prism turret –Filter wheel cleaned and wired, ready for final warm test –Grating Turret ready for cleaning and wiring –Camera cleaning and wiring in progress

Quarterly Review January 24, Budget and Expenditures Baseline Estimate (Jan 99 to completion) Labor$3,391,232 Capital$ 836,462 Total$4,227,694 Current Forecast (Jan 99 to completion) March June October January Labor $2,866,775 $3,002,938 $2,957,389 $2,986,915 Capital $1,074,798 $1,181,900$1,138,285 $1,384,670 Total $3,941,573 $4,184,838$4,095,674 $4,371,585 Performance ratios March June October January BCWS $1,754,979 $2,863,855 $3,085,811 $3,263,216 BCWP $1,611,542 $2,011,383$2,526,319 $2,899,362 ACWP $1,742,651 $2,113,212$2,762,963 $3,339,222 CPI SPI

Quarterly Review January 24, Problems and Concerns Top level integration has been delayed by 2 months until April 1st –Radiation shield design taking longer than expected –Mechanism rework required to pass flexure tests and fit checks –Focus mechanism design/fab/assembly took longer than expected Radiation shield fabrication will extend into March Documentation (Manuals) –Maintenance manual outline started; procedures documented as carried out –delayed by focus on mechanism testing and radiation shields OIWFS prism installation –OIWFS complete except for installing detector –prism needs to be installed and tested before benches integration into the dewar – latest date for receipt is 3/4/2002 (with installation hardware) IFU –Proceeding with mass models –There is a chance for integration if it arrives in February

Quarterly Review January 24, This Page Intentionally Left Blank

Quarterly Review January 24,

Quarterly Review January 24, GNIRS Configuration Most design work complete Remaining work as “punch list”

Quarterly Review January 24,

Quarterly Review January 24, Shield Status Passive shields (2 sets) –3D design complete –Detailing in progress –Fabrication proceeding as design completes Active shields –3D design in progress –Accurate weight estimate possible

Quarterly Review January 24, Active Shield

Quarterly Review January 24, Passive & Active Shields (exploded)

Quarterly Review January 24, Weight Budget Revised Value = 4052 lb –limit = 4409 lb –increase 56 lb from last QR, -61 lb from 3/01 –change mainly due to shields, hence only small c.g. change Spot check hardware against models –true weights within 2% of models

Quarterly Review January 24, This Page Intentionally Left Blank

Quarterly Review January 24,

Quarterly Review January 24, Subsystem Testing Basic philosophy remains unchanged –All subsystems tested prior to integration –Quantify performance for mechanism motion tables, flexure compensator

Quarterly Review January 24, Subsystem Testing (2) All mechanisms have undergone functional testing –Some testing on focus remains (1/17) –Need to complete clean/cold tests –Turrets flexure performance determined, provides initial input for flexure compensator settings Optical tests on camera, collimator remain –No alignment required –Fore-optics aligned and tested

Quarterly Review January 24, Subsystem Testing (3) OIWFS integration nominally complete –System aligned and tested with warm MUX –Need to install science detector –Still limited time to install and check S-H prism

Quarterly Review January 24, OIWFS Issues All OIWFS software accounted for MUX readout working Some setup information incomplete Electronics documentation incomplete Operating software is working Mechanism status (9/20/01) –Zero is displaced on gimbal Y-axis –Otherwise, hardware appears OK

Quarterly Review January 24, Software Components Top Level –Instrument Sequencer –Interfaces to detector, wavefront sensor, components controller, OCS Components Controller –Control (CAD, CAR, Apply) –Status and Alarm database (SAD) Low Level Software –Motor control –Temperature readback –Pressure monitoring

Quarterly Review January 24, Software Work Remaining - Design Alarm and Status Propagation –Complete WCS/DHS header information –If necessary

Quarterly Review January 24, Software Work Remaining - Coding Low Level (Hardware Interfacing) –No remaining coding planned Components control –Tweak engineering user interface Instrument Sequencer and Interfaces –Engineering User interface (ongoing)

Quarterly Review January 24, Software Work Remaining - Testing Low Level –Prefer fully wired system for end-to-end test –Motors Multiple motors simultaneously Determine distances between limits, switches, etc Set speeds, acceleration, backlash parameters Actual mechanism(s) needed –Temperature Probes Set calibration curve and individual offsets –Pressure Sensor Verify operation in final configuration

Quarterly Review January 24, Software Work Remaining - Testing Upper Level -- EPICS –Engineering screens provide next level of test Top Level -- OCS compliance –use OCSwish new tool, in use in Hawaii, verifies OCS interface

Quarterly Review January 24, Software Work Remaining Simulation allows testing without hardware –Works only for motors. Additional work –Lab Support –Conversion to GEM7 or GEM8 –powerPc on Detector controller –Mechanism testing Set configuration files

Quarterly Review January 24, Software Work Remaining Software is done when –Motors, temperature readback, etc, work at command line (low level) –Engineering Screens provide required control and readback –OCSwish/Acceptance test proves compliance with Gemini system –GNIRS works on the telescope

Quarterly Review January 24, Software Interface Issues Array Controller –Interfaced correctly to instrument sequencer? OCS –OCSwish will help, but it’s new to us OIWFS –real testing is not GNIRS concern.

Quarterly Review January 24, Project Management Project Status Schedule & Planning Milestones Budget and Expenditures Organization Plans for Next Review

Quarterly Review January 24, Project Status – Overview We are still on track for 2002 delivery – current ship date Oct 3 Critical path is Radiation Shield design and fabrication Mechanism testing and bench integration is a close second –Mechanism-to-bench fit checks are done –Mechanism cold tests are beginning –Bench integration completes in March Assembly of Post-Slit bench –Bench +Prism, Grating and Camera Turrets, Acquisition Mirror and Collimator Assembly of Pre-Slit bench –FW, Slit/Decker, and fore-optics Mating of Pre-Slit, OIWFS and Post-Slit benches Software and electronics are working –Test and debug completed –Software checks with actual hardware in process OIWFS integration is complete –Detector installation remains to be done at a later date

Quarterly Review January 24, Project Status – WBS 5.2 Systems Engineering All planned tasks in this work element are complete Activities over this quarter included –Oversight of the top level design and interfaces –Coordination of mechanism cleaning and assembly –Mechanism warm tests –Mechanism flexure tests –Fore-optics testing –Resources 1.5 Scientists

Quarterly Review January 24, Project Status – WBS 5.3 Mechanical Mechanism% Camera99 Detector Focus92 Environ Cover99 Acquisition Mirror89 Slit Decker95 Filter Wheel95 Grating Turret98 Gratings100 Prism Turret95 Prisms100 Motor Drives100 Bench% Post-Slit100 OIWFS100 Collimator95 POM/Offner100 Fixed Assembly % Entrance Window100 Cryo-cooler59 Molecular Sieve100 Thermal Dist.75 LN 2 Pre-Cool83 Opt Bench Mount100 Environ Cover Filter100 Bulkhead100 Passive Rad Shield68 Active Rad Shield17 Front Dewar Shell100 Rear dewar Shell100 Vert Inst Frame100 Horiz Inst Frame100 Dewar Mount Truss100 TE Mount Truss100 Shipping Container0 Handling Fixture100 Ballast Weights100

Quarterly Review January 24, Project Status – WBS 5.3 Mechanical All mechanism fabrication complete –Only activity is in rework of items found in testing Collimator assembly complete – waiting assembly/alignment Fixed assembly 3D/2D design and fabrication remaining –Radiation shields (passive and active) –Thermal distribution assembly –Cryo-cooler and manifold Resources –2 ME’s, 3 MD, 4 IM, 1 M&P Eng, 1 Procurement

Quarterly Review January 24, Project Status – WBS 5.4 Electrical Design activities are completed Instrument Controller electronics thermal enclosure complete Work remaining –Fabricate the Thermal Enclosure to Dewar cables –Harness the cold mechanisms and cold bench as they become available –Support software testing –Harness the Bulkhead Assembly –Dewar warm-up controller fabrication Resources –0.25 EE, 1 ET

Quarterly Review January 24, Project Status – WBS 5.5 Software Component Controller code complete Code has been tested as far as possible before integration Testing with mechanisms is underway Lookup tables for individual mechanisms remain Array controller code interface is yet to be verified High level (EPICS) code 99% complete Resources –1 SE

Quarterly Review January 24, Project Status – WBS 5.8 Procurement Major items remaining in procurement –Passive and Active radiation shields –Cryo-cooler assembly –LN 2 Pre-cool assembly There are no major vendor fabrication contracts –Remaining work is radiation shields and small parts/components Resources –1 Tech Associate, production

Quarterly Review January 24, Project Status – Optics Instrument optics procurement complete –Optics for Telescope Simulator remain Filters (still an open item) –7 filters ordered through UH consortium; 2 failed spec and vendor may replace Tasks left include –Camera alignment(s) –Collimator alignment –Optics alignment tests of assembled benches Resources –1 Optical Tech, 0.25 OE

Quarterly Review January 24, This Page Intentionally Left Blank

Quarterly Review January 24, Project Milestones by Quarter As of 1/16/02

Quarterly Review January 24,

Quarterly Review January 24,

Quarterly Review January 24, Planned FTE Projection

Quarterly Review January 24, FTE Projection Table shows the resources forecast through delivery and training Approximately 16,600 hrs total needed to finish the project –This does not include commissioning or the impact of the pending change order for delivery to Chile

Quarterly Review January 24,

Quarterly Review January 24,

Quarterly Review January 24, Organization Chart

Quarterly Review January 24, Director, NOAO J. Mould Director, NOAO J. Mould Gemini Projects Project Manager N. Gaughan Gemini Projects Project Manager N. Gaughan Administrative Assistant M. Bowersock Administrative Assistant M. Bowersock Project Scientist, Systems Engineering J. Elias Project Scientist, Systems Engineering J. Elias Mechanical Engineers G. Muller Mechanical Engineers G. Muller Optical Engineer M. Liang Optical Engineer M. Liang Electrical Engineer J. Penegor Electrical Engineer J. Penegor Mechanical Designers J. Andrew D. Rosin E. Downey Mechanical Designers J. Andrew D. Rosin E. Downey Programmer P. Ruckle Programmer P. Ruckle Project Assistant D. Eklund (.5) Project Assistant D. Eklund (.5) Electrical Tech R. George Electrical Tech R. George Support Scientists D. Joyce B. Gregory Support Scientists D. Joyce B. Gregory Procurement & Vender Liaison A. Davis Procurement & Vender Liaison A. Davis ETS L. Daggert ETS L. Daggert General Technician J. Pina General Technician J. Pina Instrument Makers J. Stein R. Bennett R. Harris J. Irvine Instrument Makers J. Stein R. Bennett R. Harris J. Irvine M&P B. Ditsler M&P B. Ditsler

Quarterly Review January 24, Plans for Next Review The next Quarterly Review will be held in the April 2002 timeframe The project will be into the Integration and Test Phase –Flexure testing planned start in late April Mechanical design will be complete Mechanical fabrication will be complete –except for items associated with flexure testing and shipping container –Some rework items as identified in integration may remain Electronics fabrication and checkout completed –Some rework items as identified in integration may remain Component Controller Software completed and operating with the Electronics –EPICS level software will still be in work OIWFS integration will be completed Manuals will have started –Outlines will be done –Manual drafts will have started

Quarterly Review January 24, Conclusions The current project status shows us to be over 86% complete We are on track to deliver in October 2002 We are near the end of the design phase –Radiation shield design is taking longer than anticipated –Mechanism testing and rework is taking longer than planned We are near the end of the fabrication phase All mechanisms have passed warm functional and flexure tests –Exception is focus mechanism which has yet to be fully tested The estimated cost of GNIRS is $ 4,371,585 –January ’99 to delivery

Quarterly Review January 24, Appendix A – Images Appendix B – Milestones, WBS Chart

Quarterly Review January 24, Appendix A Configuration and Fabrication Images

Quarterly Review January 24, OIWFS with Assemblies

Quarterly Review January 24, Complete Foreoptics Assembly

Quarterly Review January 24, Short Cameras Fit-Checked on Turret

Quarterly Review January 24, Four Cameras – Long Blue and Red (far left and right) and Short Blue and Red (center)

Quarterly Review January 24, Detector Focus Frame Assembly

Quarterly Review January 24, Grating & Prism Turrets and Cold Test Fixtures

Quarterly Review January 24, Grating Turret Fit Check into Optical Bench

Quarterly Review January 24, Pre-Slit Bench Fit Check

Quarterly Review January 24, Prism Turret Mounted to Cold Test Fixture

Quarterly Review January 24, Slit Slide Fit Check

Quarterly Review January 24, Optical Bench Preliminary Fit Check Ed Hileman

Quarterly Review January 24, Optical Bench Fit Check & Team Randy Bennett, Ed Hileman, Al Davis, John Stein, Gary Muller, Dick Joyce, John Andrew

Quarterly Review January 24, View down Collimator to Optical Path

Quarterly Review January 24, Assembled Bulkheads & Dewar Shells before Painting

Quarterly Review January 24, Vacuum Testing of Chamber

Quarterly Review January 24, Tangent Bars & Collimator Gimbal Mount Ring

Quarterly Review January 24, Bulkhead after Painting

Quarterly Review January 24, Bulkhead Detail

Quarterly Review January 24, Bulkheads being Assembled Al Davis, Gary Muller

Quarterly Review January 24, Fully Assembled Bulkhead & Dewar Shells Ed Hileman

Quarterly Review January 24, Full Assembly on Handling Cart

Quarterly Review January 24, Appendix B Milestones WBS Chart

Quarterly Review January 24, Milestones since MFR (3/01)

Quarterly Review January 24, WBS - Total Project

Quarterly Review January 24, This Page Intentionally Left Blank