Lead from the front Texas Nodal 1 Texas Nodal Quality Center Update Eileen Hall Ken Kasparian November 27, 2007
Lead from the front Texas Nodal 2 Quality Center Reports Provide Updated reports posted current as of 11/20/07 Test result and defect data available weekly Trend interval will be weekly as data is available Defect trend available for program on project level Future reports will show data on vendor-level
Lead from the front Texas Nodal 3 Quality Center Reports Test Results per Project Active Defects by Severity by Project per Testing Phase (FAT, iTEST) New, Open, Fixed, Test, Reopen Excludes Closed and Deferred Active Defect by Project Trend Active Defects by Severity Trend % Defects by Severity
Lead from the front Texas Nodal 4 Nodal Test Results per Project
Lead from the front Texas Nodal 5 More project teams utilizing Quality Center Increase visibility into CMM, S&B, EMS, MPIM, NMMS
Lead from the front Texas Nodal 6 Nodal FAT Active Defects by Severity by Project (Note - Does not include Closed and Deferred)
Lead from the front Texas Nodal 7 Nodal Active Defects by Project Trend
Lead from the front Texas Nodal 8 Nodal Active Defects by Severity Trend
Lead from the front Texas Nodal 9 Nodal % Defects by Severity (Note – Does include Closed and Deferred)