Presented by: Department of Transportation - Toll Bridge Program New Benicia-Martinez Bridge Project
Aerial View Of Benicia Bridges New Benicia-Martinez Bridge Existing Benicia- Martinez Bridge
New Benicia-Martinez Bridge Project Remove Median Barrier and place floating slab Remove Asphalt and replace with lightweight fill. Marina Vista Road Complete Remaining work on Marina Vista to new Mococo rail crossing. South Approach Contract Work
New Benicia-Martinez Bridge Project 18” Asphalt Overlay Raise Mococo Bridge by 18” South Approach Contract Work
New Benicia-Martinez Bridge Project Existing Bridge Work Add New Bike/Pedestrian Walkway Demolish Center Median Benicia Martinez Replace 67 Deck Joints Replace Deck Sections
New Benicia-Martinez Bridge Project Replace Deck Joints - 67 Joints spaced 90’ apart Replace Deck Sections Stage 1 Stage 2 Expansion Joint Reconstruction
New Benicia-Martinez Bridge Project Deck Reconstruction Pier 3 to Pier 13 12’ wide replacement (Entire length of truss bridge). Pier 13 Pier 3 Deck Reconstruction Pier 3 to Pier 13 12’ wide replacement localized Areas Partial Deck Reconstruction
New Benicia-Martinez Bridge Project Deck Reconstruction – Typical Section
New Benicia-Martinez Bridge Project Expansion Joint Reconstruction
New Benicia-Martinez Bridge Project Existing Bridge With New Public Access Existing Bridge 74’ 12’11’ 6’ 11’ 12’ median Existing Bridge with New Bicycle & Pedestrian Path Southbound I ’ 12’ shoulder 8’ 12’ 11.5’ 11’ 8’ shoulder Southbound Northbound
New Benicia-Martinez Bridge Project Public Access At North Approach Existing Vista Point New Bicycle & Pedestrian Path
New Benicia-Martinez Bridge Project Bike Path Cross Sections 12’ 2’ 2% Typical Section 12’ 2’ Freeway Traffic Adjacent to Freeway Shoulder 2% 12’ 1.50% Bridge Traffic Existing Concrete Barrier On Existing Bridge
New Benicia-Martinez Bridge Project Mococo Road Public Access to New Toll Plaza MARTINEZ Marina Vista Road New Bicycle & Pedestrian Path South Approach Contract Work
New Benicia-Martinez Bridge Project Bike and Pedestrian Facilities
New Benicia-Martinez Bridge Project North Approach Contract Work Remove Toll Plaza
New Benicia-Martinez Bridge Project Demolish Over crossings Demolish Existing Toll Plaza New Pedestrian/Bike Path Realign I-680/I- 780 SB Traffic North Approach Contract Work Benicia